In addition to the performance standards and design criteria
requirements of this article, the applicant shall comply with the
following water quality requirements of this article.
A. Adequate storage and treatment facilities will be provided to capture and treat stormwater runoff from developed or disturbed areas. The recharge volume computed under §
129-44 may be a component of the water quality volume if the applicant chooses to manage both components in a single facility. If the recharge volume is less than the water quality volume, the remaining water quality volume may be captured and treated by methods other than recharge/infiltration BMPs. The required water quality volume (WQv) is the storage capacity needed to capture and to treat a portion of stormwater runoff from the developed areas of the site produced from 90% of the average annual rainfall (P). To achieve this goal, the following criterion is established:
(1) The following calculation formula is to be used to determine the
water quality storage volume, (WQv), in acre-feet of storage for the
East Branch Perkiomen Creek watershed:
|
WQv = [(P)(Rv)(A)]/12
|
Equation: § 129-43.1
|
|
Where:
|
---|
|
|
WQv
|
=
|
Water Quality Volume (acre-feet)
|
---|
|
|
P
|
=
|
Rainfall Amount equal to 90% of events producing this rainfall
(in)
|
---|
|
|
A
|
=
|
Area of the project contributing to the water quality BMP (acres)
|
---|
|
|
Rv
|
=
|
0.05 + 0.009(I) where I is the percent of the area that is impervious
surface (impervious area/A*100)
|
(2) The P value for the five PennDOT rainfall regions is shown in Figure
B-2 in Appendix B of the Model Ordinance within this plan and as shown
in Appendix Table B-5. Since the East Branch Perkiomen Creek is in PennDOT Region
4, the P value to be utilized to meet this requirement is 1.95 inches.
B. Design of BMPs used for water quality control shall be in accordance
with design specifications outlined in the Pennsylvania Handbook of
Best Management Practices for Developing Areas or other applicable
manuals. The following factors shall be considered when evaluating
the suitability of BMPs used to control water quality at a given development
site:
(1) Total contributing drainage area.
(2) Permeability and infiltration rate of the site soils.
(3) Slope and depth to bedrock.
(4) Seasonal high water table.
(5) Proximity to building foundations and well heads.
(7) Land availability and configuration of the topography.
(8) Peak discharge and required volume control.
(10)
Efficiency of the BMPs to mitigate potential water quality problems.
(11)
The volume of runoff that will be effectively treated.
(12)
The nature of the pollutant being removed.
(13)
Maintenance requirements.
(14)
Creation/protection of aquatic and wildlife habitat.
(16)
Enhancement of aesthetic and property value.
C. To accomplish the above, the applicant shall submit original and
innovative designs to the municipality for review and approval. Such
designs may achieve the water quality objectives through a combination
of BMPs (best management practices).
Stormwater runoff from all development sites shall be calculated
using either the rational method or a soil cover complex methodology.
A. Any stormwater runoff calculations shall use generally accepted calculation
technique that is based on the NRCS soil cover complex method. Table
129-49-1 summarizes acceptable computation methods. It is assumed
that all methods will be selected by the applicant based on the individual
limitations and suitability of each method for a particular site.
(1) The
municipality may allow the use of the Rational Method to estimate
peak discharges from drainage areas that contain less than 200 acres.
The Rational Method is recommended for drainage areas under 100 acres.
B. All calculations consistent with this Part
2 using the soil cover complex method shall use the appropriate design rainfall depths for the various return period storms according to the region for which they are located as presented in Table B-1 in Appendix B of this Part
2. If a hydrologic computer model such as HEC-1 or HEC-HMS is used for stormwater runoff calculations, then the duration of rainfall shall be 24 hours. The SCS 'S' curve shown in Figure B-1, Appendix B of this Part
2 shall be used for the rainfall distribution.
C. Runoff curve numbers (CN) for both existing and proposed conditions to be used in the soil cover complex method shall be obtained from Table B-2 in Appendix B of this Part
2. For the purposes of existing conditions flow rate determination, undeveloped land shall be considered as "meadow" in good condition, unless the natural ground cover generates a lower curve number or Rational 'C' value (i.e., forest), as listed in Table B-2 or B-3 in Appendix B of this Part
2. For areas of prior mining disturbance (i.e., strip mining, mine spoil areas, etc.), the designer must first locate in which of mining affect area the site is located, using the Management District Map in Appendix D. The appropriate curve number or Rational 'C' value from Table B-2 or Table B-3 should then be used.
D. All calculations using the Rational Method shall use rainfall intensities
consistent with appropriate times of concentration for overland flow
and return periods from the design storm curves from PA Department
of Transportation Design Rainfall Curves (1986) (Figures B-2 to B-3). Times of concentration for overland flow shall be calculated
using the methodology presented in Chapter 3 of Urban Hydrology for
Small Watersheds, NRCS, TR-55 (as amended or replaced from time to
time by NRCS). Times of concentration for channel and pipe flow shall
be computed using Manning's equation.
E. The designer shall consider that the runoff from proposed sites graded
to the subsoil will not have the same runoff conditions as the site
under existing conditions even if topsoiled and seeded. The designer
may increase their proposed condition CN or C value to reflect proposed
soil conditions.
F. Runoff coefficients (c) for both existing and proposed conditions for use in the Rational Method shall be obtained from Table B-3 in Appendix B of this Part
2.
G. Where uniform flow is anticipated, the Manning equation shall be used for hydraulic computations, and to determine the capacity of open channels, pipes, and storm sewers. Values for Manning's roughness coefficient (n) shall be consistent with Table B-4 in Appendix B of this Part
2. Outlet structures for stormwater management facilities
shall be designed to meet the performance standards of this Part 2
using any generally accepted hydraulic analysis technique or method.
H. The design of any stormwater detention facilities intended to meet
the performance standards of this Part 2 shall be verified by routing
the design storm hydrograph through these facilities using the storage-indication
method. For drainage areas greater than 200 acres in size, the design
storm hydrograph shall be computed using a calculation method that
produces a full hydrograph. The municipality may approve the use of
any generally accepted full hydrograph approximation technique that
shall use a total runoff volume that is consistent with the volume
from a method that produces a full hydrograph.
|
Table 129-49-1. Acceptable Computation Methodologies for
Stormwater Management Plans
|
---|
|
Method
|
Method Developed by
|
Applicability
|
---|
|
TR-20
(or commercial computer package based on TR-20)
|
USDA NRCS
|
Applicable where use of full hydrology computer model is desirable
or necessary
|
|
TR-55
(or commercial computer package based on TR-55)
|
USDA NRCS
|
Applicable for land development plans within limitations described
in TR-55
|
|
HEC-1, HEC-HMS
|
U.S. Army Corps of Engineers
|
Applicable where use of full hydrologic computer model is desirable
or necessary
|
|
PSRM
|
Penn State University
|
Applicable where use of a hydrologic computer model is desirable
or necessary; simpler than TR-20 or HEC-1
|
|
Rational Method
(or commercial computer package based on Rational Method)
|
Emil Kuichling (1889)
|
For sites less than 200 acres, or as approved by the Municipality
and/or Municipal Engineer
|
|
Other methods
|
Varies
|
Other computation methodologies approved by the Municipality
and/or Municipal Engineer
|