A. 
At various specified stages of construction of streets and ways, utilities, and other improvements, inspections shall be mandatory and shall be made and certified in writing by the Department of Public Works Superintendent, or representative of the appropriate agency involved (e.g., Water Department, Fire Districts No. 1 and No. 2, and the Electric Light Department).
B. 
Construction of streets and installation of utilities may be phased, provided that each section shall not be less than 500 feet.
C. 
The applicant shall be responsible for engaging, at his expense, a qualified engineer to set all lines, grades and stakes to the satisfaction of the DPW Superintendent.
D. 
In order to make arrangements for proper inspection of street construction and installation of utilities, a seventy-two-hour notice shall be given by the applicant to the designated individual or agency before the following construction stages:
(1) 
Before clearing and grubbing, the Tree Warden shall be notified to designate those trees which are to be preserved in the tree belt.
(2) 
The roadway shall be inspected by the DPW Superintendent upon completion of each of the following construction stages:
(a) 
Subgrade (and subbase if necessary).
(b) 
Gravel base.
(c) 
Binder course.
(d) 
Surface course.
(3) 
The installation of the sanitary and storm drainage systems and related structures shall be inspected by the DPW Superintendent, or Board of Health as appropriate, before the filling and compacting of the utility trenches.
(4) 
After the filling and compacting of the utility trenches, the applicant shall have an inspection of installed drainage lines and sewer mains performed by means of a television camera. This inspection shall be conducted at the applicant's expense, and the results forwarded to the DPW Superintendent.
(5) 
The water system and appurtenant facilities shall be inspected by the representative of the respective Water District.
(6) 
The installation of sidewalks shall be inspected by the DPW Superintendent upon completion of subgrade base course, as well as permanent binder and finish course.
(7) 
The installation of curbs, where required, and loaming and seeding operations shall be inspected by the DPW Superintendent.
(8) 
At the completion of all the improvements in the subdivision, including loaming and seeding, curbs, monuments, plantings and signs, the DPW Superintendent shall make an inspection before final release of the performance guarantee.
E. 
Each specified construction stage shall be completed to the satisfaction of the DPW Superintendent or appropriate agency and given in writing, before further work shall be done. Any development which progresses beyond an inspection stage without written approval of the DPW Superintendent or appropriate agency shall be required to return the construction to the status necessary to perform the required inspection.
F. 
Cost of inspections shall be paid by the applicant in accordance with the Fee Schedule (see appendix[1]) on a per-lineal-foot of street basis, as measured along the street center line of the definitive plan and such amounts shall be paid to the Town Treasurer in cash or official bank check prior to endorsement of the definitive plan.
[1]
Editor's Note: The appendixes are available in the Town offices and on the Town website: www.southhadley.org.
G. 
It shall be the responsibility of the applicant to engage qualified individuals to provide engineering supervision during construction to ensure proper construction of improvements in accordance with the approved plan.