Table 308.1
| |||
---|---|---|---|
Peak Rate Control Standards
| |||
(Peak Flow Rate of the Post-Construction Design Storm
Shall be Reduced to the Peak Flow Rate of the Corresponding Predevelopment
Design Storm Shown in the Table)
| |||
Post-Construction Design Storm Frequency
(24-hour duration)
|
Predevelopment Design Storm
| ||
New Development Regulated Activities
|
Redevelopment Regulated Activities
| ||
2-year
|
1-year
|
2-year
| |
5-year
|
5-year
|
5-year
| |
10-year
|
10-year
|
10-year
| |
25-year
|
25-year
|
25-year
| |
50-year
|
50-year
|
50-year
| |
100-year
|
100-year
|
100-year
|
Table 309.1
| |||
---|---|---|---|
Acceptable Computation Methodologies for SWM Site Plan
| |||
Method
|
Developed By
|
Applicability
| |
TR-20
(or commercial computer package based on TR-20)
|
USDA NRCS
|
Applicable where use of full hydrology computer model is desirable
or necessary
| |
TR-55
(or commercial computer package based on TR-55)
|
USDA NRCS
|
Applicable for land development plans where limitations described
in TR-55 are met
| |
HEC-1/HEC-HMS
|
US Army Corps of Engineers
|
Applicable where use of a full hydrologic computer model is
desirable or necessary
| |
Rational Method
(or commercial computer package based on Rational Method)
|
Emil Kuichling (1889)
|
For sites up to 5 acres, or as approved by the municipality
| |
Other methods
|
Varies
|
Other computation methodologies approved by the municipality
|