Upon recording of the final plat, the applicant may start to
install or implement the approved stormwater management controls,
subject to the provisions of the above. If site development or building
construction does not begin within two years of the date of final
approval of the subdivision or land development plan, then before
doing so, the applicant shall resubmit the stormwater management plans
to verify that no condition has changed within the watershed that
would affect the feasibility or effectiveness of the previously approved
stormwater management controls. Further, if for any reason development
activities are suspended for two years or more, then the same requirement
for resubmission of the stormwater management plan shall apply. The
terms of these subsequent reviews shall be subject to the provisions
of this Part 2 and any amended additional ordinances subsequently
passed.
Procedures for approving plan modifications. Requests for modifications
in the final approved stormwater management controls shall be submitted
to the Borough Engineer as follows:
A. If the request is initiated before construction begins, the stormwater
plan must be resubmitted and reviewed according to the original procedures.
B. If the request is initiated after construction is underway, the Borough
Engineer shall have the authority to approve or disapprove the modification,
based on field inspection, provided that the request changes in stormwater
controls do not result in any modifications to other approved borough
land use/development requirements. The Borough Engineer shall maintain
a record of all changes approved for the stormwater management controls
and shall submit these to Borough Council with the final as-built
plans for the development, prior to the acceptance of any improvements
by the Borough and/or the release of any bond money for improvements
being constructed. If no bond money was required, this information
must be submitted prior to the Borough's final inspection of
the plan is completed and approval is granted.