[Ord. 1141, 10/11/2012]
1. 
The Borough Engineer or his designee shall inspect all phases of the installation of the permanent stormwater management facilities as deemed appropriate by the Borough Engineer.
2. 
During any stage of the work, if the Borough Engineer or his designee determines that the permanent stormwater management facilities are not being installed in accordance with the approved stormwater management plan, the Shillington Borough Council shall revoke any existing building permits and issue a cease-and-desist order until a revised stormwater management plan is submitted and approved, except as directed by the Borough Engineer or Conservation District, as specified in this chapter.
3. 
A final inspection of all stormwater management facilities shall be conducted by the Borough Engineer or his designee to confirm compliance with the approved stormwater management plan prior to the issuance of any occupancy permit.