[Ord. 1984-4, 8/6/1984, § 1; as amended by Ord. 1988-1, 8/1/1988]
1. 
No unauthorized person shall uncover, make any connections with or opening into, use, alter, or disturb any wastewater sewer or a storm sewer without first obtaining a written permit from the Manager.
2. 
There shall be three classes of permits for connections to the Borough's wastewater facilities: Class I - Residential, Class II - Commercial, and Class III - Industrial. In all cases, the owner shall make application for a permit to connect to the Borough's wastewater facilities on a special form furnished by the Borough. The permit application shall be supplemented by wastewater information required to administer this chapter. A permit and inspection fee as established from time to time by the Borough Council for a Class I, for a Class II, or for a Class III connection permit shall be paid to the Borough at the time the application is filed.
3. 
Connections to a storm sewer shall be subject to a permit and inspection fee as established from time to time by the Borough Council. Such connections shall be subject to the provisions of this chapter and the approval of the Manager.
[Ord. 1984-4, 8/6/1984, § 2]
The costs and expenses incidental to the building sewer installation and connection to the Borough's wastewater facilities shall be borne by the owner. The owner shall indemnify the Borough from any loss or damage that may directly or indirectly be occasioned by the installation of the building sewer.
[Ord. 1984-4, 8/6/1984, § 3]
A separate and independent building sewer shall be provided for every building, except where one building stands at the rear of another on an interior lot and no private sewer is available or can be constructed to the rear building through an adjoining alley, court yard, or driveway, the building sewer serving the front building may be extended to the rear building and the whole considered as one building sewer. The Borough assumes no obligation or responsibility for damage caused by or resulting from any single building sewer which serves two buildings.
[Ord. 1984-4, 8/6/1984, § 4]
Existing building sewers may be used for connection of new buildings only when they are found, on examination and test by the Manager to meet the requirements of this chapter.
[Ord. 1984-4, 8/6/1984, § 5]
The size, slope, alignment, construction materials, trench excavation and backfill methods, pipe placement, jointing and testing methods used in the construction and installation of a building sewer shall conform to the Building and Plumbing Code or other applicable requirements of the Borough. In the absence of code provisions, or in amplification thereof, the materials and procedures set forth in appropriate specifications of the ASTM and WPCF shall apply.
[Ord. 1984-4, 8/6/1984, § 6]
Whenever practicable, the building sewer shall be brought to a building at an elevation below the basement floor. In buildings in which any building drain is too low to permit gravity flow to the Borough's wastewater sewer, wastewater carried by such building drain shall be lifted by an approved means and discharged to a building sewer draining to the Borough's sewer.
[Ord. 1984-4, 8/6/1984, § 7]
1. 
No person shall connect roof, foundation, areaway, parking lot, roadway, or other surface runoff or groundwater drains to any sewer which is connected to a wastewater treatment facility unless such connection is authorized in writing by the Manager.
2. 
Except as provided in § 18-507, Subsection 1, above, roof, foundation, areaway, parking lot, roadway, or other surface runoff or groundwater drains shall discharge to natural outlets or storm sewers.
[Ord. 1984-4, 8/6/1984, § 8]
1. 
The connection of a building sewer into a wastewater sewer shall conform to the requirements of the building and plumbing code or other applicable requirements of the Borough, or the procedures set forth in appropriate specifications of the ASTM or the WPCF. The connections shall be made gastight and watertight and verified by proper testing. Any deviation from the prescribed procedures and materials must be approved in writing by the Manager before installation.
2. 
The connection of a surface runoff or groundwater drain to a storm sewer or natural outlet designed to transport surface runoff or groundwater drainage shall conform to the requirements of the applicable building code or other applicable requirements the Borough. The connection of any such drain to a wastewater sewer under special permit as provided under § 18-507, Subsection 1, of this Part 5 shall conform to the requirements specified by the Manager as a condition of approval of such permit.
[Ord. 1984-4, 8/6/1984, § 9]
The applicant for a building sewer or other drainage connection permit shall notify the Manager when such sewer or drainage connection is ready for inspection prior to its connection to the Borough's facilities. Such connection and testing as deemed necessary by the Manager shall be made under the supervision of the Manager.
[Ord. 1984-4, 8/6/1984, § 10]
Excavations for building sewer installation shall be adequately guarded with barricades and lights so as to protect the public from hazard. Streets, sidewalks, parkways, and other public property disturbed in the course of work shall be restored in a manner satisfactory to the Borough.
[Ord. 1984-4, 8/6/1984, § 11]
The Manager shall not issue a permit for any class of connection to the Borough's wastewater sewers or wastewater treatment facilities unless there is sufficient capacity, not legally committed to other users, in the wastewater sewers and treatment facilities to convey and adequately treat the quantity of wastewater which the requested connection will add to the system. The Manager may permit such a connection if there are legally binding commitments to provide the needed capacity.