[Amended 5-16-2023 ATM by Art. 32]
The purpose of the Floodplain District is to:
A. 
Ensure public safety through reducing the threats to life and personal injury.
B. 
Eliminate new hazards to emergency response officials.
C. 
Prevent the occurrence of public emergencies resulting from water quality, contamination, and pollution due to flooding.
D. 
Avoid the loss of utility services which, if damaged by flooding, would disrupt or shut down the utility network and impact regions of the community beyond the site of flooding.
E. 
Eliminate costs associated with the response and cleanup of flooding conditions.
F. 
Reduce damage to public and private property resulting from flooding waters.
A. 
The Floodplain District is herein established as an overlay district and includes all special flood hazard areas within the Town of North Andover designated as Zones A, AE, AH, AO, A99, V or VE on the Essex County Flood Insurance Rate Maps (FIRMs) dated July 19, 2018, issued by the Federal Emergency Management Agency (FEMA) for the administration of the National Flood Insurance Program. The map panels of the Essex County FIRMs that are wholly or partially within the Town of North Andover are panel numbers 25009C0207F, 25009C0209F, 25009C0217F, 25009C0226F, 25009C0227F, 25009C0228F, 25009C0229F, 25009C0233F, 25009C0236F, 25009C0237F, 25009C0238F, 25009C0239F, 25009C0241F, 25009C0242F, 25009C0243F, 25009C0244F, 25009C0377F and 25009C0381F, dated July 19, 2018. The exact boundaries of the district shall be defined by the 1% chance base flood elevations shown on the FIRM and further defined by the Essex County Flood Insurance Study (FIS) report dated July 19, 2018. The FIRM and FIS report are incorporated herein by reference and are on file with the Town Clerk, Planning Board, Building Official and Conservation Commission.
B. 
Areas designated as floodplain on the North Andover Flood Insurance Rate Maps may be determined to be outside the Floodplain District by the Building Inspector, in consultation with the Director of the Division of Public Works, if an accurate topographic and property line survey of the area conducted by a registered professional engineer or land surveyor shows that the floodplain contour elevation does not occur in any area of proposed buildings, structures, improvements, excavation, filling, paving, or other work activity. The person requesting the determination shall provide any other information deemed necessary by the Building Inspector, in consultation with the Director of the Division of Public Works, to make that determination. If the Building Inspector, in consultation with the Director of the Division of Public Works, determines that the Flood Insurance Rate Maps are in error, the subject area shall not be regulated as occurring within the Floodplain District, and any such determination shall be noted on the Flood Insurance Rate Maps. Nothing in this section shall prohibit the Conservation Commission, Board of Health, or other Town officials or Board from making nonzoning determinations of the floodplain or performing their official duties.
The Town of North Andover hereby designates the position of Building Inspector to be the official floodplain administrator for the Town of North Andover.
The Town of North Andover requires a permit for all proposed construction or other development in the Floodplain District, including new construction or changes to existing buildings, placement of manufactured homes, placement of agricultural facilities, fences, sheds, storage facilities or drilling, mining, paving and any other development that might increase flooding or adversely impact flood risks to other properties.
The Town's permit review process includes the requirement that the proponent obtain all local, state and federal permits that will be necessary in order to carry out the proposed development in the Floodplain Overlay District. The proponent must acquire all necessary permits, and must demonstrate that all necessary permits have been acquired.
In Zones A, A1-30, and AE, along watercourses that have not had a regulatory floodway designated, the best available federal, state, local, or other floodway data shall be used to prohibit encroachments in floodways which would result in any increase in flood levels within the community during the occurrence of the base flood discharge.
In A Zones, in the absence of FEMA BFE data and floodway data, the Building Department will obtain, review and reasonably utilize base flood elevation and floodway data available from a federal, state, or other source as criteria for requiring new construction, substantial improvements, or other development in Zone A and as the basis for elevating residential structures to or above base flood level, for floodproofing or elevating nonresidential structures to or above base flood level, and for prohibiting encroachments in floodways.
Within Zones AO and AH on the FIRM, adequate drainage paths must be provided around structures on slopes, to guide floodwaters around and away from proposed structures.
In A1-30, AH, AE Zones, all recreational vehicles to be placed on a site must be elevated and anchored in accordance with the zone's regulations for foundation and elevation requirements or be on the site for less than 180 consecutive days or be fully licensed and highway ready.
In a riverine situation, the Building Inspector shall notify the following of any alteration or relocation of a watercourse:
A. 
Adjacent communities, especially upstream and downstream.
B. 
Bordering states, if affected.
C. 
NFIP State Coordinator, Massachusetts Department of Conservation and Recreation 251 Causeway Street, 8th floor, Boston, MA 02114.
D. 
NFIP Program Specialist, Federal Emergency Management Agency, Region I 99 High Street, 6th Floor, Boston, MA 02110.
If the town/city acquires data that changes the base flood elevation in the FEMA mapped special flood hazard areas, the town/city will, within six months, notify FEMA of these changes by submitting the technical or scientific data that supports the change(s). Notification shall be submitted to:
A. 
NFIP State Coordinator, Massachusetts Department of Conservation and Recreation 251 Causeway Street, 8th floor, Boston, MA 02114.
B. 
NFIP Program Specialist, Federal Emergency Management Agency, Region I 99 High Street, 6th Floor, Boston, MA 02110.
A. 
The Town will request from the State Building Code Appeals Board a written and/or audible copy of the portion of the hearing related to the variance, and will maintain this record in the community's files.
B. 
The Town shall also issue a letter to the property owner regarding potential impacts to the annual premiums for the flood insurance policy covering that property, in writing over the signature of a community official that i) the issuance of a variance to construct a structure below the base flood level will result in increased premium rates for flood insurance up to amounts as high as $25 for $100 of insurance coverage and ii) such construction below the base flood level increases risks to life and property. Such notification shall be maintained with the record of all variance actions for the referenced development in the floodplain overlay district.
A variance from these Floodplain Bylaws must meet the requirements set out by state law, and may only be granted if: 1) good and sufficient cause and exceptional nonfinancial hardship exist; 2) the variance will not result in additional threats to public safety, extraordinary public expense, or fraud or victimization of the public; and 3) the variance is the minimum action necessary to afford relief.
A. 
The Floodplain District is established as an overlay district to all other districts. All development in the district, including structural and nonstructural activities, whether permitted by right or by special permit, must be in compliance with MGL c. 131, § 40 and with the following:
(1) 
Section of the Massachusetts State Building Code which addresses floodplain and coastal high-hazard areas (currently 780 CMR 120G);
(2) 
Wetlands Protection Regulations, Department of Environmental Protection (DEP) (currently 310 CMR 10.00);
(3) 
Inland Wetlands Restriction, DEP (currently 310 CMR 13.00);
(4) 
Minimum Requirements for the Subsurface Disposal of Sanitary Sewage, DEP (currently 310 CMR 15, Title 5);
B. 
Any variances from the provisions and requirements of the above-referenced state regulations may only be granted in accordance with the required variance procedures of these state regulations.
C. 
The floodplain management regulations found in this Floodplain District part shall take precedence over any less restrictive local laws, bylaws or codes.
A. 
Within Zones A1-A30 and AE, along watercourses that have a regulatory floodway within the Town of North Andover, on the Essex County FIRMs dated July 19, 2018, encroachments, including fill, new construction, substantial improvement, and other development are prohibited in the regulatory floodway which would result in any increase in flood levels within the community during the occurrence of the base flood discharge. However, a registered professional engineer may provide hydrologic and hydraulic analysis performed in accordance with standard engineering practice proof and certification to the Building Commissioner, in conjunction with the Director of the Division of Public Works, demonstrating that such encroachments shall not increase flood levels during the occurrence of the 100-year flood, and if the Building Commissioner, in conjunction with the Director of the Division Public Works, approves this certification, such encroachments shall not be deemed to be prohibited.
B. 
Subdivision proposals.
(1) 
All subdivision proposals filed in accordance with MGL c. 41, §§ 81S and 81T (or any revisions to the Subdivision Control Law referencing the submission of preliminary or definitive subdivision plans), respectively, and development proposals, shall be designed so that:
(a) 
Such proposals minimize flood damage;
(b) 
All public utilities and facilities are located and constructed to minimize or eliminate flood damage; and
(c) 
Adequate drainage is provided to reduce exposure to flood hazards.
(d) 
When proposing subdivisions or other developments greater than 50 lots or five acres (whichever is less), the proponent must provide technical data to determine base flood elevations for each developable parcel shown on the design plans.
(2) 
Existing contour intervals of site and elevations of existing structures must be included on the plan proposal.
(3) 
The applicant shall circulate or transmit one copy of the development plan to the Conservation Commission, Planning Board, Board of Health, Town Engineer, and Building Commissioner for comments which will be considered by the appropriate permitting board prior to issuing applicable permits.
The following uses of low flood damage potential and causing no obstruction to flood flows are encouraged, provided they are permitted in the underlying district and they do not require structures, fill or storage of materials or equipment:
A. 
Agricultural uses such as farming, grazing, truck farming, horticulture, etc.
B. 
Forestry and nursery uses.
C. 
Outdoor recreational uses, including fishing, boating, play areas, etc.
D. 
Conservation of water, plants, wildlife.
E. 
Wildlife management areas, foot, bicycle, and/or horse paths.
F. 
Temporary nonresidential structures used in connection with fishing, growing, harvesting, storage, or sale of crops raised on the premises.
G. 
Buildings lawfully existing prior to the adoption of these provisions.
The degree of flood protection required by this bylaw is considered reasonable but does not imply total flood protection.
If any section, provision or portion of this bylaw is deemed to be unconstitutional or invalid by a court, the remainder of the bylaw shall be effective.
The provisions shall be enforced by the North Andover Building Inspector. The Building Inspector, upon being informed in writing of a possible violation of this bylaw or on his own initiative, shall make or cause to be made an investigation of facts and an inspection of the premises where such violation may exist. If the Building Inspector is so informed in writing and declines to act, he/she shall, within 14 days of his receipt of such information, give to his informant, in writing, his reasons for refraining from taking any action. The Building Inspector, on evidence of any violation after investigation and inspection, shall give written notice of such violation to the owner and to the occupant of such premises, and the Building Inspector shall demand in such notice that such violation be abated within such reasonable time as may be given by mail addressed to the owner at the address appearing for him/her on the most recent real estate tax records of North Andover, and to the occupant at the address of the premises of such seeming violation. If, after such notice and demand, such violation has not been abated within the time specified, the Building Inspector or the Selectmen shall institute appropriate action or proceedings in the name of the Town of North Andover to prevent, correct, restrain, or abate any violation of this bylaw.
100-YEAR FLOOD
See "base flood."
AREA OF SPECIAL FLOOD HAZARD
The land in the floodplain within a community subject to a 1% or greater chance of flooding in any given year. The area may be designated as Zone A, AO, AH, A1-30, AE, A99, V1-30, VE, or V.
BASE FLOOD
The flood having 1% chance of being equaled or exceeded in any given year.
COASTAL HIGH-HAZARD AREA
The area subject to high-velocity waters, including but not limited to hurricane wave wash or tsunamis. The area is designated on a FIRM as Zones V, V1-30, and VE.
DEVELOPMENT
Any man-made change to improved or unimproved real estate, including but not limited to building or other structures, mining, dredging, filling, grading, paving, excavation or drilling operations or storage of equipment or materials. (44 CFR Part 59)
DISTRICT
The Floodplain District.
EXISTING MANUFACTURED HOME PARK OR SUBDIVISION
A manufactured home park or subdivision for which the construction of facilities for servicing the lots on which the manufactured homes are to be affixed (including, at a minimum, the installation of utilities, the construction of streets, and either final site grading or the pouring of concrete pads) and which is completed before the effective date of the floodplain management regulations adopted by a community.
EXPANSION TO AN EXISTING MANUFACTURED HOME PARK OR SUBDIVISION
The preparation of additional sites by the construction of facilities for servicing the lots on which the manufactured homes are to be affixed (including the installation of utilities, the construction of streets, and either final site grading or the pouring of concrete pads).
FEDERAL EMERGENCY MANAGEMENT AGENCY (FEMA)
The agency that administers the National Flood Insurance Program. FEMA provides a nationwide flood hazard area mapping study program for communities as well as regulatory standards for development in the flood hazard areas.
FLOOD BOUNDARY AND FLOODWAY MAP
An official map of a community issued by FEMA that depicts, based on detailed analyses, the boundaries of the 100-year and 500-year floods and the 100-year floodway. (For maps done in 1987 and later, the floodway designation is included on the FIRM.)
FLOOD HAZARD BOUNDARY MAP (FHBM)
An official map of a community issued by the Federal Insurance Administrator where the boundaries of the flood and related erosion areas having special hazards have been designated as Zone A or E. (44 CFR Part 59).
FLOOD INSURANCE RATE MAP (FIRM)
An official map of a community on which FEMA has delineated both the areas of special flood hazard and the risk-premium zones applicable to the community.
FLOOD INSURANCE STUDY (FIS)
An examination, evaluation, and determination of flood hazards, and, if appropriate, corresponding water surface elevations, or an examination, evaluation and determination of flood-related erosion hazards.
FLOODWAY
The channel of a river, creek or other watercourse and the adjacent land areas that must be reserved in order to discharge the base flood without cumulatively increasing the water surface elevation more than the designated height. (Base Code, Chapter 2, Section 202)
FUNCTIONALLY DEPENDENT USE
A use which cannot perform its intended purpose unless it is located or carried out in close proximity to water. The term includes only docking facilities, port facilities that are necessary for the loading and unloading of cargo or passengers, and ship building and ship repair facilities, but does not include long-term storage or related manufacturing facilities. (44 CFR Part 59; also referenced, Standard ASCE 24-14).
HIGHEST ADJACENT GRADE
The highest natural elevation of the ground surface prior to construction next to the proposed walls of a structure. (44 CFR Part 59).
HISTORIC STRUCTURE
Any structure that is:
A. 
Listed individually in the National Register of Historic Places (a listing maintained by the Department of Interior) or preliminarily determined by the Secretary of the Interior as meeting the requirements for individual listing on the National Register;
B. 
Certified or preliminarily determined by the Secretary of the Interior as contributing to the historical significance of a registered historic district or a district preliminarily determined by the Secretary to qualify as a registered historic district;
C. 
Individually listed on a state inventory of historic places in states with historic preservation programs which have been approved by the Secretary of the Interior; or
D. 
Individually listed on a local inventory of historic places in communities with historic preservation programs that have been certified either:
(1) 
By an approved state program as determined by the Secretary of the Interior; or
(2) 
Directly by the Secretary of the Interior in states without approved programs. (44 CFR Part 59).
LOWEST FLOOR
The lowest floor of the lowest enclosed area (including basement or cellar). An unfinished or flood-resistant enclosure, usable solely for parking of vehicles, building access or storage in an area other than a basement area, is not considered a building's lowest floor, provided that such enclosure is not built so as to render the structure in violation of the applicable nonelevation design requirements of NFIP Regulation 60.3.
MANUFACTURED HOME
A structure, transportable in one or more sections, which is built on a permanent chassis and is designed for use with or without a permanent foundation when connected to the required utilities. For floodplain management purposes, the term "manufactured home" also includes park trailers, travel trailers, and other similar vehicles placed on a site for greater than 180 consecutive days. For insurance purposes, the term "manufactured home" does not include park trailers, travel trailers, and other similar vehicles.
MANUFACTURED HOME PARK OR SUBDIVISION
A parcel (or contiguous parcels) of land divided into two or more manufactured home lots for rent or sale.
NEW CONSTRUCTION
For floodplain management purposes, structures for which the start of construction commenced on or after the effective date of the first floodplain management code, bylaw, regulation or standard adopted by the authority having jurisdiction, including any subsequent improvements to such structures. New construction includes work determined to be substantial improvement (Referenced Standard ASCE 24-14) For the purpose of determining insurance rates, "new construction" means structures for which the start of construction commenced on or after the effective date of an initial FIRM or after December 31, 1974, whichever is later.
NEW MANUFACTURED HOME PARK OR SUBDIVISION
A manufactured home park or subdivision for which the construction of facilities for servicing the lots on which the manufactured homes are to be affixed (including, at a minimum, the installation of utilities, the construction of streets, and either final site grading or the pouring of concrete pads) is completed on or after the effective date of the floodplain management regulations adopted by a community.
RECREATIONAL VEHICLE
A vehicle which is:
A. 
Built on a single chassis;
B. 
Four hundred square feet or less when measured at the largest horizontal projection;
C. 
Designed to be self-propelled or permanently towable by a light duty truck; and
D. 
Designed primarily not for use as a permanent dwelling but as temporary living quarters for recreational, camping, travel, or seasonal use. (44 CFR Part 59).
REGULATORY FLOODWAY
See "floodway."
SPECIAL FLOOD HAZARD AREA
The land areas subject to flood hazards and shown on a Flood Insurance Rate Map or other flood hazard map as Zone A, AE, A1-30, A99, AR, AO, AH. (Base Code, Chapter 2, Section 202)
START OF CONSTRUCTION
The date of issuance for new construction and substantial improvements to existing structures, provided the actual start of construction, repair, reconstruction, rehabilitation, addition, placement or other improvement is within 180 days after the date of issuance. The actual start of construction means the first placement of permanent construction of a building (including a manufactured home) on a site, such as the pouring of a slab or footings, installation of pilings or construction of columns.
Permanent construction does not include land preparation (such as clearing, excavation, grading or filling), the installation of streets or walkways, excavation for a basement, footings, piers or foundations, the erection of temporary forms or the installation of accessory buildings such as garages or sheds not occupied as dwelling units or not part of the main building. For a substantial improvement, the actual "start of construction" means the first alteration of any wall, ceiling, floor or other structural part of a building, whether or not that alteration affects the external dimensions of the building. [Base Code, Chapter 2, Section 202]
STRUCTURE
For floodplain management purposes, a walled and roofed building, including a gas or liquid storage tank that is principally above ground, as well as a manufactured home. (44 CFR Part 59) "Structure," for insurance coverage purposes, means a walled and roofed building, other than a gas or liquid storage tank, that is principally above ground and affixed to a permanent site, as well as a manufactured home on a foundation. For the latter purpose, the term includes a building while in the course of construction, alteration, or repair, but does not include building materials or supplies intended for use in such construction, alteration, or repair, unless such materials or supplies are within an enclosed building on the premises.
SUBSTANTIAL DAMAGE
Damage of any origin sustained by a structure whereby the cost of restoring the structure to its before-damaged condition would equal or exceed 50% of the market value of the structure before the damage occurred.
SUBSTANTIAL IMPROVEMENT
Reconstruction, rehabilitation, addition or other improvement of a structure, the cost of which equals or exceeds 50% of the market value of the structure before the start of construction of the improvement. This term includes structures which have incurred substantial damage, regardless of the actual repair work performed.
SUBSTANTIAL REPAIR OF A FOUNDATION
When work to repair or replace a foundation results in the repair or replacement of a portion of the foundation with a perimeter along the base of the foundation that equals or exceeds 50% of the perimeter of the base of the foundation measured in linear feet, or repair or replacement of 50% of the piles, columns or piers of a pile, column or pier supported foundation, the Building Inspector shall determine it to be substantial repair of a foundation. Applications determined by the building official to constitute substantial repair of a foundation shall require all existing portions of the entire building or structure to meet the requirements of 780 CMR. [As amended by MA in 9th Edition BC]
VARIANCE
A grant of relief by a community from the terms of a floodplain management regulation. (44 CFR Part 59)
VIOLATION
The failure of a structure or other development to be fully compliant with the community's flood plain management regulations. A structure or other development without the elevation certificate, other certifications, or other evidence of compliance required in § 60.3 is presumed to be in violation until such time as that documentation is provided. (44 CFR Part 59).
ZONE A
The 100-year floodplain area where the base flood elevation (BFE) has not been determined. To determine the BFE, use the best available federal, state, local, or other data.
ZONE A1-A30 AND ZONE AE (FOR NEW AND REVISED MAPS)
The 100-year floodplain where the base flood elevation has been determined.
ZONE A99
Areas to be protected from the 100-year flood by federal flood protection system under construction. Base flood elevations have not been determined.
ZONE AH AND ZONE AO
The 100-year floodplain with flood depths of one foot to three feet.
ZONE V
A special flood hazard area along a coast subject to inundation by the 100-year flood with the additional hazards associated with storm waves. Base flood elevations have not been determined.
ZONE V1-30 AND ZONE VE (FOR NEW AND REVISED MAPS)
A special flood hazard area along a coast subject to inundation by the 100-year flood with additional hazards due to velocity (wave action). Base flood elevations have been determined.
ZONES B, C, AND X
Areas identified in the community Flood Insurance Study as areas of moderate or minimal flood hazard. Zone X replaces Zones B and C on new and revised maps.[1]
[1]
Editor's Note: Original § 4.2, Phased Development, which immediately followed this section, expired 7-1-2009 and is therefore no longer included in the Zoning Bylaw.