No building, structure, sign or land shall be erected, constructed,
reconstructed, altered, converted, removed, maintained, moved, added
to, used or the use therein changed unless and until a building and
zoning permit is obtained from the Zoning Administrator. The permit
requirements shall apply to all permanent, temporary, seasonal, part-time
or movable buildings, structures, signs or uses, unless exempted elsewhere
in this chapter. No building and zoning permit shall be issued by
the Zoning Administrator except in conformity with the provisions
of this chapter, unless he receives a written order from the Zoning
Hearing Board in the form of an administrative review, special exception
or variance as provided by this chapter.
Applications for a building and zoning permit shall be filed
by the property owner, his authorized agent or an individual with
a proprietary interest in the property, said individual to hereafter
be known as the applicant. Applications shall be submitted to the
Zoning Administrator and contain the following:
A. Building and zoning permit application form. On a form supplied by
the Zoning Administrator, the applicant shall provide information
to describe the size, location, and nature of the proposed building,
structure or use. The applicant shall sign the application form to
verify the accuracy of the information.
B. Plot plan. All applications for a building and zoning permit shall
be accompanied by a plot plan in accordance with the following:
(1)
Three copies of the plot plan shall be submitted. In lieu thereof,
an 8 1/2 inches by 11 inches plot plan is acceptable, provided
it is suitable for photocopying.
(2)
The plot plan shall show, where applicable, size, shape, and
dimensions of the lot; size and location of all existing buildings;
size, location and use of all proposed buildings, additions or alterations;
parking lots, parking spaces, driveways, signs and other site improvements;
and other information as may be necessary to determine conformance
with this chapter.
(3)
Engineering, architectural or surveyor's plans may be required
by the Zoning Administrator where necessary to accurately depict the
proposed work on a property.
(4)
The Zoning Administrator may waive the plot plan requirement
where the applicant satisfactorily demonstrates that minimum standards
are greatly exceeded.
C. Other permit prerequisites. At the time of application, the applicant
shall produce, where applicable, a valid sewage permit, road encroachment
permit, Labor and Industry approval, subdivision approval or other
approval preliminary to issuance of the building and zoning permit.
D. Application fee. All applications for a building and zoning permit
shall be accompanied by a fee in accordance with the current schedule
of fees resolution adopted by the Township Supervisors.
When an applicant fails to: 1) complete and sign the building and zoning permit application form, 2) submit a plot plan, 3) pay the required application fee, 4) secure and produce other permit prerequisites, or 5) submit other information required by the Zoning Administrator, the application for a building and zoning permit shall be deemed incomplete. The Zoning Administrator may notify the applicant to request supplemental information to complete the application. Such notice shall prescribe a time period, not to exceed 30 days, for completion of the application by submission of the supplementary information. Failure to complete the application shall result in written disapproval, in accordance with §
250-258 of this chapter.
After an application has been determined to be complete, the
Zoning Administrator shall take official action to approve or disapprove
the permit application in accordance with the following:
A. Approval. When a completed application is found to conform with the
provisions of this chapter the Zoning Administrator, within 20 days
of application completion, shall issue an approved building and zoning
permit. Issuance of the permit shall be accompanied by an approved
plot plan, where applicable, and a placard for display on the premises
during the construction or alteration period. Building and zoning
permits are nontransferable and are valid for work authorized therein
only for the owner and the property so designated.
B. Disapproval. When a completed application is found not to conform with the provisions of this chapter the Zoning Administrator, within 20 days of application completion, shall disapprove the application for a building and zoning permit. Plot plans submitted with the application shall also be disapproved. The disapproval shall be in writing, citing the deficiencies of the application. Appeals for a disapproval by the Zoning Administrator shall be taken in the manner set forth in Articles
XXVII and
XXVIII and §§
250-272 and
250-273.
All approved building and zoning permits for properties located
in the Township shall include the following disclaimer:
"The majority of the lands within the INS - Institutional Zoning
District are located within an area where land is used for military
operations. Owners, residents, and other users in this district, and
in the Township overall, may be subjected to inconvenience, discomfort,
and the possibility of injury to property and health arising from
normal and accepted military operations and practices including, but
not limited to, noise, vibration, odors, dust, the operation of machinery
of any kind including aircraft and military vehicles, and the discharge
of weapons. Owners, occupants, and users in this district, and in
the Township overall, should be prepared to accept such inconveniences,
discomfort, and possibility of injury from such military operations,
and are hereby put on official notice that Federal and State laws
may bar them from obtaining a legal judgment against such military
operations."