A.
Reviewing authority. The Planning Board shall be responsible for subdivision and site plan reviews unless otherwise stated in this chapter. In this capacity, the Planning Board, or its designee, shall act in accordance with the provision outlined in Chapter 7, Article I, of the City Code, establishing the Planning Board.
[Amended 9-9-2024 by Ord. No. 2024-94]
(1)
Preapplication conference;
(2)
Neighborhood meeting. Neighborhood meetings are required at the discretion of the City Planner or the Planning Board. A neighborhood meeting is an opportunity for the applicant to provide an advance presentation of the application materials to the abutters in an informal setting. The meeting allows the applicant to hear questions or concerns, and for the abutters to receive information in advance of the formal Planning Board meeting which is intended to create common understandings and a well-informed process;
(3)
Sketch plan review. Sketch plan review may be required at the discretion of the City Planner based on the complexity of the project and does not constitute substantive review of an application for purposes of 1 M.R.S.A. § 302. The purpose of the sketch plan is to obtain preliminary feedback from the Planning Board and the public on the proposed project prior to extensive site planning and engineering work is undertaken. Where a sketch plan review is deemed necessary, the review is required prior to the submission and review of a final plan; and
(4)
Final plan review.
B.
Review process. Subdivision and site plan review process may include:
[Amended 9-9-2024 by Ord. No. 2024-94]
C.
Applications.
[Amended 9-9-2024 by Ord. No. 2024-94]
(1)
Application receipt and completeness review.
(a)
When an application is submitted, the City Planner shall schedule an application review conference for the following week.
(b)
When an application is received, the City Planner, or their designee, shall:
[1]
Give a dated receipt to the applicant.
[2]
Notify by mail all property owners within 500 feet of any portion of the property submitted for subdivision and site plan review; public and private rights-of-way do not limit the 500-foot distance measurement.
[3]
Notify by mail the City Clerk and the reviewing authority of municipalities that abut or include any portion of the subdivision or site plan.
(c)
Within 30 days after receiving an application, the City Planner shall notify the applicant, in writing, either that the application is complete or, if the application is incomplete, the specific additional material needed to complete the application.
[1]
Application completeness shall be determined based upon the submission requirements listed in §§ 335-13.3 and 335-13.5. Additional supplemental or supporting materials may be required at the discretion of the Planning Board to demonstrate compliance with all standards of subdivision and/or site plan review.
[2]
Appeals to the City Planner's completeness determination may be made to the Planning Board.
(d)
After the application has been determined complete the application shall be placed on the next available Planning Board agenda for the full evaluation of the proposed subdivision and site plan.
(2)
Submission and application expiration.
(a)
Sketch plan submission: The sketch plan submission shall be valid for a period of six months from the date of submission to the City. If a final plan application is not filed within that period, the City Planner may require a new sketch plan submission.
(b)
Final application: A final application is valid for one year from the date of submission. The Planning Board may extend this period by no more than one additional year from the date of the first public hearing.
(3)
Public hearing; notice. A public hearing on an application for site plan or subdivision approval, be held within 30 days after an application has been determined complete. The City Planner shall give notice of the date, time and place of the hearing:
(4)
(5)
Approval expiration.
(a)
Site plan approval expires unless the work necessary to accomplish the purpose for which it was requested is commenced within one year and completed within three years after the date of Planning Board approval or is completed in accordance with a phased completion schedule proposed by the applicant and approved by the Planning Board, as incorporated in the final approval. Failure to complete a subsequent phase within the required period shall also have the effect of causing the permit to expire. Deadline dates for phased developments shall be established at the time of approval.
(b)
Any applicant may come back before the Board and request a permit extension.
[1]
An extension request must occur within one year after approval was granted.
[2]
An extension of the completion date established for the project must be requested within three years after the project was approved by the City.
[3]
The Planning Board may deny any requests for additional extensions after the second extension if it determines that substantial work has not occurred on the project during the extension periods and the applicant is unable to show good cause for such delay.
(6)
Appeal. The applicant, abutting landowner, or aggrieved party may appeal a site plan/subdivision review decision of the Planning Board to the Superior Court of the State of Maine within 30 days of the final Planning Board decision.
(7)
Performance guarantee. Prior to the commencement of any construction related to an approved site plan or subdivision development or the issuance of any permits associated with the site plan or subdivision development, the developer shall file a performance guarantee with the City. The performance guarantee shall be a certified bank check payable to the City, a performance bond running to the City, or a letter of credit from a financial institution in amount and form acceptable to the City. The check, bond or letter of credit must equal at least the total cost of furnishing, installing, and completing the site plan or subdivision public improvements and infrastructure and all related improvements within three years of its date.
D.
Joint hearing and application. If a proposed final plan requires both subdivision and site plan review, the applicant must apply for a joint review of the final plan. Procedures for both subdivision and site plan review must be met in order to initiate the review and hearing process.
E.
Change in ownership. Where there is a change in ownership of a project after approval has been granted and prior to the completion of all required improvements, the Board may request new financial capability information, as well as other factors that the Board deems necessary because of changing conditions.
F.
Notification costs. The applicant shall incur all costs for notices and public hearings conducted pursuant to this article.
G.
Revision to approved plans. When an applicant applies for approval of a revision to a plan approved by the Planning Board, such application shall, in all respects, follow the procedures and satisfy the requirements of this article. All appropriate changes must be in accordance with this chapter.
H.
Fees for consulting, review and inspection.
(1)
Notwithstanding any other provision(s) of this chapter to the contrary, and in addition to such fees as are otherwise specified by this chapter, the City shall assess fees to cover 100% of its costs related to independent geotechnical, hydrologic, engineering, planning, legal, and similar professional consulting services incurred in the review of site plan and subdivision applications. Such fees shall be subject to the following limitations:
(a)
Such fees shall only be as expressly provided by this chapter;
(b)
Such consultation shall be limited to reasonable and necessary review, as allowed by the pertinent ordinance, which exceeds the expertise of City staff or their ability to review the application materials within the time limits otherwise required by law or ordinance.
(c)
Such fees shall be assessed only to recover costs directly associated with review of the application submitted by the applicant to whom they are assessed;
(d)
Such fees shall be reasonable in amount, based upon the consulting time involved and the complexity of the review;
(e)
The results of the consultation for which such fees are assessed shall be available for public review, but such results shall be deemed to have been made solely for the benefit of the City of Westbrook and shall remain its property; and
(f)
Such fees shall be assessed for the privilege of review and shall be payable without regard to consultation results or the outcome of the application.
(2)
An escrow account shall be established with the City by the applicant to guarantee payment in advance of actual fees assessed pursuant to this chapter. The original deposit shall be an amount specific to the application, as accorded elsewhere in this chapter. If the balance in the escrow account shall be drawn down by 75%, the City shall notify the applicant and require that an additional amount be deposited to cover the cost of remaining work before any such remaining work is undertaken. The City shall continue to notify the applicant and require that any such additional amount(s) be deposited whenever the balance of the account is drawn down by 75% of the original deposit. Any excess amount deposited with the City in advance shall be promptly refunded to the applicant after final action on the application.
(3)
Any dispute regarding the application of this chapter or the amount required to be paid, either in advance or upon completion, may be appealed, in writing, within 10 days to the City Administrator. The City Administrator, after due notice and investigation and for good cause shown, may affirm, modify, or reverse the disputed decision or reduce the amount assessed.
(4)
In an effort to minimize the use of outside or independent consulting, the provisions of this chapter shall be subject to the following additional limitations:
(a)
The City Engineer will devote no less than two hours, if needed, to each development project and, if in the City Engineer's sole judgment his/her work load permits, he/she may work additional time on an individual development project without referring it to outside or independent consulting, but the City shall charge for such additional time at a rate determined by the City Council on a fee schedule adopted for that purpose; and
(b)
The City Planner will devote no less than four hours, if needed, to each development project and, if in his/her sole discretion his/her work load permits, he/she may devote additional time to a project without referring it to outside or independent consulting, but the City shall charge for his/her time at a rate determined by the City Council on a fee schedule adopted for that purpose; provided, however, in his/her sold discretion, he/she may immediately refer to outside or independent consulting any major subdivision having five or more lots or dwelling units or any major site plan.
(5)
Prior to issuance of a street opening permit, or the first permit required for the project, the applicant shall pay to the City a site improvement inspection fee equal to the amount of 2% of the site improvement costs. This shall be separate from building permit fees, which cover inspection of buildings. While this requirement applies to both subdivision and site plan approvals, a project with both subdivision and site plan approval is subject to a single site improvement inspection fee.
(6)
This chapter shall be administered by the City Planner or other City employee responsible for administering the ordinance under which review is sought. No building permit or certificate of occupancy may be issued nor subdivision plat released until all fees assessed hereunder have been paid in full.