[Ord. No. 1244, 12-7-2015; Ord. No. 1333, 12-19-2022]
A. The Program Administrator shall publish annually, in a newspaper of general circulation that provides meaningful public notice within the jurisdictions served by the POTW, a list of the users which, at any time during the previous twelve (12) months, were in significant non-compliance with applicable pretreatment standards and requirements. The term "significant non-compliance" shall be applicable to all significant industrial users [or any other industrial user that violates Subsection
(A)(3),
(4) or
(8) of this Section] and shall mean:
1.
Chronic violations of wastewater discharge limits, defined here as those in which sixty-six percent (66%) or more of all the measurements taken for the same pollutant parameter taken during a six-month period exceed (by any magnitude) a numeric pretreatment standard or requirement, including instantaneous limits as defined in Article
II;
2.
Technical review criteria (TRC) violations, defined here as those in which thirty-three percent (33%) or more of wastewater measurements taken for each pollutant parameter during a six-month period equals or exceeds the product of the numeric pretreatment standard or requirement, including instantaneous limits, as defined by Article
II, multiplied by the applicable criteria (1.4 for BOD, TSS, fats, oils and grease, and 1.2 for all other pollutants except pH);
3.
Any other violation of a pretreatment standard or requirement as defined by Article
II (daily maximum, long-term average, instantaneous limit, or narrative standard) that the Program Administrator determines has caused, alone or in combination with other discharges, interference or pass-through, including endangering the health of POTW personnel or the general public;
4.
Any discharge of a pollutant that has caused imminent endangerment
to the public or to the environment, or has resulted in the Program
Administrator's exercise of its emergency authority to halt or
prevent such a discharge;
5.
Failure to meet, within ninety (90) days of the scheduled date,
a compliance schedule milestone contained in an individual wastewater
discharge permit or enforcement order for starting construction, completing
construction, or attaining final compliance;
6.
Failure to provide within forty-five (45) days after the due
date, any required reports, including baseline monitoring reports,
reports on compliance with categorical pretreatment standard deadlines,
periodic self-monitoring reports, and reports on compliance with compliance
schedules;
7.
Failure to accurately report non-compliance; or
8.
Any other violation(s), which may include a violation of best
management practices, which the Program Administrator determines will
adversely affect the operation or implementation of the local pretreatment
program.