Any work completed or started without inspection and in an unacceptable
manner will be considered done at the developer or builder's expense
since, by proceeding without inspection, they have assumed the burden
of proof for acceptability.
A. Engineer. The Engineer's Field Services Department shall be notified
at least 48 hours in advance that field services are required. Notification
may be made either in writing or verbally, but in either instance,
notification must be received by the Field Services Department prior
to the said 48 hours.
(1) Written notification shall be directed to:
Pennoni Associates
Haddon Heights Municipal Department
515 Grove Street Suite 1B
Haddon Heights, New Jersey 08035
Attention: Hugh Dougherty
|
(2) Verbal notification shall be made to the above at: (856)547-0505.
The request for field services is the direct responsibility of the
developer or builder and should they neglect to request same (or request
same less than 48 hours prior to need, and field services cannot be
scheduled), all work accomplished without field services will automatically
be considered unacceptable. Extreme care should be taken to avoid
this situation, since:
(a)
All construction not accessible for complete visual inspection
must be reestablished in such a manner as to allow for same before
it will be accepted.
(b)
All construction which is subject to curing and hardening and/or
which must be compacted (e.g., portland cement concrete, bituminous
concrete, backfill, subgrade, etc.) must be tested in such a manner
as to allow for complete evaluation before it will be accepted.
(c)
A complete schedule of the required tests, examinations, etc.,
required in specific instance will be provided by this office.
B. Owner. The owner's Plant Superintendent shall be notified at least
48 hours in advance that inspection is required. Notification may
be made either in writing or verbally, but in either instance, notification
must be received prior to the said 48 hours.
(1) Verbal notification shall be made at: (856)461-0700. The request
for inspection is the direct responsibility of the developer or builder
and should they neglect to request same (or request same less than
48 hours prior to need, and inspection cannot be scheduled), all work
accomplished without inspection will automatically be considered unacceptable.
Extreme care should be taken to avoid this situation, since:
(a)
All construction not accessible for complete visual inspection
must be reestablished in such a manner as to allow for same before
it will be accepted.
(b)
All construction which is subject to curing and hardening and/or
which must be compacted (e.g., portland cement concrete, bituminous
concrete, backfill, subgrade, etc.) must be inspected in such a manner
as to allow for complete evaluation before it will be accepted.