A. 
Intent and interpretation.
(1) 
This chapter is intended as a guide for developers and builders within the Township. It is an addendum to the regularly adopted rules and regulations of the owner, and represent the minimum acceptable requirements. The owner reserves the right to specify greater or less stringent requirements in any case, in its judgment, to be in the best interest of the owner.
(2) 
The owner recognizes the fact that questions may arise during the planning, construction, and/or testing phases of a project that may or may not be covered by these specifications. In these cases, the owner will take whatever action is necessary to either clarify the meaning of the specifications or provide the necessary information for the builder, contractor, or developer to understand and meet the owner's requirements.
(3) 
Whenever and wherever the term "standard specifications" is used in this chapter, it shall mean the current edition of the New Jersey Department of Transportation Standard Specifications for Road and Bridge Construction.
(4) 
Whenever and wherever the term "Engineer" is used in these specifications, it shall mean the Engineer duly appointed by the owner.
B. 
General approval requirements. The applicant/developer must complete the following steps in order to receive sanitary sewer service from the owner:
(1) 
Complete all application forms and permits as required by the owner.
(2) 
Obtain NJDEP permits when required.
C. 
Permits. It is the responsibility of the developer or builder to obtain all required permits before the onset of construction. The owner will not permit construction of any sanitary sewer facilities without first obtaining a treatment works approval and/or bureau of safe drinking water permit(s) from the NJDEP, if applicable.
A. 
General.
(1) 
Submit to the Engineer shop drawings, product data and samples required by the specification sections.
(2) 
All shop drawings, product data and samples shall be reviewed and approved by the design engineer prior to submission.
(3) 
Schedule submission for shop drawings, product data and samples at least 21 days before dates reviewed submittals will be needed.
B. 
Shop drawings.
(1) 
Original drawings, prepared by contractor, subcontractor, supplier or distributor, which illustrate some portion of the work, showing fabrication, layout, setting or erection details.
(2) 
Minimum sheet size: 8 1/2 inches by 11 inches.
(3) 
Present drawings in a clear and thorough manner. Details shall be identified by reference to sheet and detail, schedule or room numbers shown on development plans.
C. 
Product data.
(1) 
Preparation.
(a) 
Clearly mark each copy to identify pertinent products or models.
(b) 
Show performance characteristics and capacities.
(c) 
Show dimensions and clearances required.
(d) 
Show wiring or piping diagrams and controls.
(2) 
Manufacturer's standard schematic drawings and diagrams:
(a) 
Modify drawings and diagrams to delete information not applicable to the work.
(b) 
Supplement standard information to provide information specifically applicable to the work.
(3) 
Manufacturer's catalog sheets, brochures, diagrams, illustrations and other standard descriptive data:
(a) 
Clearly mark each copy to identify pertinent materials, products or models.
(b) 
Show dimensions and clearances required.
(c) 
Show compliance with referenced standards.
D. 
Samples.
(1) 
Office samples:
(a) 
Of sufficient size and quantity to clearly illustrate:
[1] 
Functional characteristics of product or material with integrally related parts and attachment devices.
[2] 
Full range of color, texture, and pattern.
[3] 
After review, samples will be retained by Engineer. Upon completion of the work, contractor may submit written request for return of samples.
E. 
Contractor's responsibilities.
(1) 
Review shop drawings, product data and samples prior to submission.
(2) 
Determine and verify:
(a) 
Field measurements.
(b) 
Field construction criteria.
(c) 
Catalog numbers and similar data.
(d) 
Conformance with specifications.
(3) 
Coordinate each submittal with requirements of the work and of the owner's standard details.
(4) 
Contractor's responsibility for errors and omissions in submittals is not relieved by the owner or Engineer review of submittals.
(5) 
Contractor's responsibility for deviations in submittals from requirements of owner's specifications is not relieved by the owner or Engineer review of submittals, unless the owner gives written acceptance of specific deviations.
(6) 
Notify Engineer, in writing, at time of submission, of proposed deviations in submittals from owner requirements.
(7) 
Begin no fabrication or work that requires submittals until return of submittals with Engineer's stamp and initials or signature indicating review.
F. 
Submission requirements.
(1) 
Make submittals so as to cause no delay in the work or in the work of any other contractor.
(2) 
Number of submittals required: shop drawings: submit the number of opaque reproductions which the contractor requires, plus eight copies, two of which will be retained by the Engineer and two by the owner.
(3) 
Accompany submittals with transmittal letter, in duplicate, containing:
(a) 
Date of submission and dated of any previous submissions.
(b) 
Project title and number.
(c) 
Contractor's name and address.
(d) 
The number of each shop drawing, product data and sample submitted.
(e) 
Notification of deviations from owner requirements.
(f) 
Other pertinent data.
(4) 
Submittals shall include:
(a) 
Date and revision date.
(b) 
Project title and number.
(c) 
The names of:
[1] 
Design engineer.
[2] 
Contractor.
[3] 
Subcontractor.
[4] 
Supplier.
[5] 
Manufacturer.
[6] 
Separate details when pertinent.
(d) 
Identification of product or materials.
(e) 
Field dimensions, clearly identified as such.
(f) 
Specification section number.
(g) 
Relation to adjacent or critical features of the work or materials.
(h) 
Applicable standards, such as ASTM or federal specification numbers.
(i) 
Identification of deviations from owner standards.
(j) 
Identification of revisions on resubmittals.
(k) 
An eight-inch-by-three-inch blank space for contractor and Engineer stamps.
(l) 
Contractor's stamp, initialed or signed, certifying to review of submittal, verification of products, field measurements and field construction criteria, and coordination of the information within the submittal with requirements of the work and of the owner's standards.
(m) 
Design engineer's stamp, initialed or signed, certifying to review of submittal, verification of products, field measurements and field construction criteria, and coordination of the information within the submittal with requirements of the work and of the owner's standards.
G. 
Resubmission requirements.
(1) 
Make any corrections or changes in the submittals required by the Engineer and resubmit until approved.
(2) 
Shop drawings and product data:
(a) 
Revise initial drawings or data, and resubmit as specified for the initial submittal.
(b) 
Indicate any changes that have been made other than those requested by the Engineer.
(3) 
Samples: Submit new samples as required for initial submittals.
H. 
Distribution.
(1) 
Distribute reproductions of shop drawings and copies of product data that carry the Engineer stamp of review to:
(a) 
Subcontractors.
(b) 
Supplier.
(c) 
Contractor's file.
(2) 
Distribute samples that carry the Engineer stamp of review as directed by Engineer.
I. 
Engineer duties.
(1) 
Review submittals with reasonable promptness.
(2) 
Review for:
(a) 
Design concept of project.
(b) 
Information given in approved plans.
(3) 
Review of separate item does not constitute review of an assembly in which item functions.
(4) 
Affix stamp and initials or signature certifying to review of submittal.
(5) 
Return submittals to contractor for distribution or resubmission.
Any work completed or started without inspection and in an unacceptable manner will be considered done at the developer or builder's expense since, by proceeding without inspection, they have assumed the burden of proof for acceptability.
A. 
Engineer. The Engineer's Field Services Department shall be notified at least 48 hours in advance that field services are required. Notification may be made either in writing or verbally, but in either instance, notification must be received by the Field Services Department prior to the said 48 hours.
(1) 
Written notification shall be directed to:
Pennoni Associates
Haddon Heights Municipal Department
515 Grove Street Suite 1B
Haddon Heights, New Jersey 08035
Attention: Hugh Dougherty
(2) 
Verbal notification shall be made to the above at: (856)547-0505. The request for field services is the direct responsibility of the developer or builder and should they neglect to request same (or request same less than 48 hours prior to need, and field services cannot be scheduled), all work accomplished without field services will automatically be considered unacceptable. Extreme care should be taken to avoid this situation, since:
(a) 
All construction not accessible for complete visual inspection must be reestablished in such a manner as to allow for same before it will be accepted.
(b) 
All construction which is subject to curing and hardening and/or which must be compacted (e.g., portland cement concrete, bituminous concrete, backfill, subgrade, etc.) must be tested in such a manner as to allow for complete evaluation before it will be accepted.
(c) 
A complete schedule of the required tests, examinations, etc., required in specific instance will be provided by this office.
B. 
Owner. The owner's Plant Superintendent shall be notified at least 48 hours in advance that inspection is required. Notification may be made either in writing or verbally, but in either instance, notification must be received prior to the said 48 hours.
(1) 
Verbal notification shall be made at: (856)461-0700. The request for inspection is the direct responsibility of the developer or builder and should they neglect to request same (or request same less than 48 hours prior to need, and inspection cannot be scheduled), all work accomplished without inspection will automatically be considered unacceptable. Extreme care should be taken to avoid this situation, since:
(a) 
All construction not accessible for complete visual inspection must be reestablished in such a manner as to allow for same before it will be accepted.
(b) 
All construction which is subject to curing and hardening and/or which must be compacted (e.g., portland cement concrete, bituminous concrete, backfill, subgrade, etc.) must be inspected in such a manner as to allow for complete evaluation before it will be accepted.
A. 
Descriptions.
(1) 
All nonemergency work performed after 3:30 p.m. or before 7:00 a.m. or on Saturday, Sunday or Holidays shall be scheduled with the Sewer Department as in § 51-6B.
(2) 
If any additional staff is necessary for assistance/inspection after normal work hours, all costs will be the responsibility of the property owner. Additional staff requirements will be determined by the Sewer Department.
(3) 
Any work performed outside normal business hours without proper scheduling with the Sewer Department must be properly inspected and approved by the Sewer Superintendent or a designee from his department. In order to ensure a proper inspection, the Sewer Department can require the removal of any materials that may be covering the lines that were worked on by the contractor or homeowner.
(4) 
The work site of any emergency work or work done during normal business hours shall be maintained in a safe condition and free of hazards to the public. Failure to maintain a safe environment is cause for the Township to do whatever is necessary to make sure the work site is safe. All costs borne by Riverside Township to insure a safe environment or work zone shall be the responsibility of the homeowner and/or contractor.
B. 
"Emergency work" is defined to mean repairs to a sewer service line to correct a leak, sewer backup, or nonfunctioning sewer lateral that poses a threat to the health and safety of the property owner and/or the surrounding residents. All other work will be considered nonemergency.
A. 
Descriptions.
(1) 
Description of the work: trenching, backfilling, and compaction includes, but is not limited to:
(a) 
Excavation for trenches and trench backfilling;
(b) 
Rough and finish grading of the work; and
(c) 
Furnishing and installing trench stabilization material and select backfill material.
(2) 
Definitions. As used in this section, the following terms shall have the meanings indicated:
TRENCH EXCAVATION
Removal and disposal of all material encountered when establishing required grade elevations, including pavements, concrete slabs and other obstructions.
UNAUTHORIZED EXCAVATION
Removal of materials beyond specified subgrade elevations without approval of the Engineer.
B. 
Materials.
(1) 
Trench backfill material from on-site excavation:
(2) 
All on-site backfill materials shall be subject to the approval of the Engineer and to the following requirements:
(a) 
Free from deleterious substances, stumps, brush, weeds, roots, sod, rubbish, garbage and matter that may decay.
(b) 
Backfill to a height of two feet above the top of pipes, culverts and other structures with material free from stones or rock fragments larger than two inches in greatest dimension.
(c) 
Free of large rocks or lumps that, in the opinion of the Engineer, may create voids or prevent proper compaction.
(3) 
Select backfill material: Select backfill material shall be Type I-13. Soil aggregate select backfill materials, when designated, shall conform to Section 901.09 of the Standard Specifications.
(4) 
Broken stone material:
(a) 
Broken stone subbase material under slabs, foundations and structures shall conform to Section 901.04 of the Standard Specifications, and meeting the gradations specified in Table 901-1. Size shall be No. 57.
(b) 
Trench stabilization material for bedding shall conform to the above requirements. Size shall be No. 57.
(5) 
Other materials. All other materials, not specifically described but required for a complete and proper installation shall be as selected by the contractor and approved by the Engineer.
C. 
Methods of construction.
(1) 
Requirements of regulatory agencies:
(a) 
All excavations shall be in compliance with Federal Occupational Safety and Health Act (OSHA) and Rules and Regulations of the State of New Jersey Department of Labor and Industry, Bureau of Engineering and Safety, N.J.A.C. 12:180. Failure to comply may result in a cease-and-desist order for that portion of work.
(b) 
Excavation work shall be in compliance with applicable requirements of other governing authorities having jurisdiction.
(2) 
Reference standards included in this specification section:
(a) 
New Jersey State Highway Department Standard Specifications for Road and Bridge Construction, 1983 (Standard Specifications).
[1] 
Section 901.03: Aggregate, Coarse.
[2] 
Section 901.04: Broken Stone.
[3] 
Section 901.09: Soil Aggregate.
(b) 
American Society for Testing and Materials (ASTM):
[1] 
D-1556: Density of Soil in Place by the Sand-Cone Method.
[2] 
D-1557: Moisture Density Relations of Soils and Soil Aggregate Mixtures Using 10-1b. Rammer and eighteen-inch Drop.
[3] 
D-2049: Relative Density of Cohesionless Soils.
[4] 
D-2922: Density of Soil and Soil Aggregate In-Place by Nuclear Methods (Shallow Depth).
(3) 
Submittals: pursuant to § 51-5, Product data, of Article II, General Specifications.
(4) 
Test reports. When directed by the engineer, submit test reports on all select backfill material in accordance with the following standards:
(a) 
Particle size analysis of soils: ASTM D-422.
(5) 
Job conditions:
(a) 
Existing utilities. Should uncharted or incorrectly charted piping or other utilities be encountered during excavation, consult the utility owner immediately for directions. Cooperate with owner and utility companies in keeping respective services and facilities in operation. Repair damaged utilities to satisfaction of utility owner.
(b) 
Do not interrupt existing utilities serving facilities occupied and used by owner or others, except when permitted, in writing, by the Engineer, and then only after acceptable temporary utility services have been provided.
(6) 
Use of explosives. The use of explosives is not permitted.
(7) 
Protection of persons and property:
(a) 
Barricade open excavations occurring as part of this work and post with warning lights as required to protect persons on-site. Operate warning lights as recommended by authorities having jurisdiction.
(b) 
Protect trees, shrubs, lawns and other features remaining as part of final landscaping.
(c) 
Protect structures, utilities, sidewalks, pavements and other facilities from damage caused by settlement, lateral movement, undermining, washout and other hazards created by earthwork operations.
(d) 
In the event of damage, immediately make all repairs and replacements to the approval of the Engineer at no cost to the owner.
(8) 
Dust control. Use all means necessary to control dust on and near the work if such dust is caused by the contractor's operations during performance of the work or if resulting from the conditions in which the contractor leaves the site.
(9) 
Weather conditions. Do not place, spread, roll or fill materials during freezing, raining or otherwise unfavorable weather conditions. Do not resume work until conditions are favorable as determined by the Engineer.
(10) 
Inspection by contractor. Examine the areas and conditions under which trenching, backfilling, compacting and grading are to be performance and notify the Engineer, in writing, of conditions detrimental to the proper and timely completion of the work. Do not proceed with the work until unsatisfactory conditions have been corrected in an acceptable manner.
(11) 
Preparation:
(a) 
Prior to commencement of work, 48 hour notification shall be given to the owner's sewer department.
(b) 
Prior to commencement of work, establish location and extent of all utilities in the work areas. Maintain and protect as required existing utilities which pass through the work area.
(c) 
Prior to excavation in pavement areas, cut existing pavement vertically with sharp tool on a straight line to the limits of excavation shown on the plans or as directed by the Engineer. Maintain cut straight and neat, or recut and dress as directed by the Engineer.
(12) 
Lines and depth.
(a) 
Trenches shall be excavated along the lines and at depths necessary for laying the pipe to the grade given, as designated by the Engineer. Excavation shall not be carried below the required level except where unstable soil is encountered. Whenever excavation has been made below the required level, it shall be replaced with three-quarter-inch crushed stone and shall be thoroughly tamped. The Engineer shall determine the depth of removal of unstable soil encountered.
(b) 
Excavation for manholes and other structures shall have a twelve-inch minimum clearance and twenty-four-inch maximum clearance on all sides. The widths of trenches for pipe shall equal pipe outside diameter plus two feet, unless otherwise provided by the Engineer. Excavations shall be confined within the narrowest possible limit and made as nearly as possible in a vertical line, and any sheathing, shoring, bracing and timbering which is necessary to obtain this result shall be done as hereinafter specified.
(c) 
Preliminary excavation shall be made only to a depth of three inches above the final depth of any trench or other excavations. The remaining depth shall be carefully excavated, shaped, and formed with hand tools immediately preceding laying of pipe or placing concrete. Trench bottoms shall be accurately formed to receive and support the bottom of the barrel of the pipe. Additional excavation shall be made in pipe trenches at the pipe joints and to prevent any possibility of a pipe resting on the bell rather than the barrel.
(d) 
In rock, the bottom shall be excavated six inches below the normal support grade and refilled with compacted granular material.
(13) 
Materials excavated:
(a) 
The materials excavated shall be stored compactly on the side of the trench and kept trimmed to be of as little inconvenience as possible to travel and adjoining properties. All streets shall be kept open for travel unless otherwise directed by the Engineer. All bituminous gravel, stone surface, gravel base course and topsoil shall be kept separate from other excavated materials and shall be used as the final layer in the backfill operation where appropriate.
(b) 
Before excavating any existing surface, topsoil shall be stripped to a minimum depth of six inches and stored for reuse as final grade where planting is proposed.
(c) 
The contractor shall not remove from the site any sand, gravel or other soil excavated from the trench which may be suitable for backfilling until backfilling is completed.
(d) 
Surplus material remaining after the proper backfilling of trenches shall be used to till in low areas or where shown on the profiles. Other surplus materials shall be transported and placed by the contractor, at his expense, at a location within the Township as determined by the Engineer.
(14) 
Removal of water:
(a) 
The contractor shall at all times provide and maintain ample means and devices to promptly remove and disperse all water or sewage entering excavations and structures dry until all work therein is completed.
(b) 
The contractor shall dispose of the water from the trenches and excavations in a manner satisfactory to the owner, developer and/or owner inspector, without damage to adjacent property. In no case shall water or sewage be allowed to enter new lines. Sewage shall not be discharged onto the ground or into the stormwater system.
(c) 
If groundwater and subsoil conditions along the line of the work are such that the contractor cannot successfully remove water or provide a stable trench by ordinary trench pumping and bailing, or when necessary to protect the work, workmen, public, under- or aboveground utilities and structures, pavements and public and private property, the contractor shall, where designed by the Engineer, furnish and provide the necessary equipment, power and labor to employ the well point method of trench dewatering. The well point system or portions thereof shall be removed by the contractor upon the completion of backfill, and the holes remaining from the points shall be backfilled and thoroughly tamped.
(15) 
Shoring and sheathing:
(a) 
The contractor shall be responsible for the installation of shoring and sheathing on all faces of the excavation where it is necessary to ensure a suitable, dry, and/or safe excavation, to eliminate settlement of, or damage to structures or items adjacent to the excavation, to preserve the bearing capacity of the soil, to keep the excavation within the narrowest possible limits, to protect work from damage, and to provide conditions acceptable to the Engineer and all interested agencies.
(b) 
Bracing shall be installed so that there is no stress on or displacement of any part of the completed work until the construction thereof has proceeded far enough to provide the necessary strength, as determined by the Engineer.
(c) 
Any damage to pipelines, road structures, etc., occurring through settlement, soil pressure, cave-ins, shifts of sheathing, or any other causes associated with the contractor's activities shall be repaired or the damaged items replaced by the contractor without cost thereof to the owner.
(16) 
Backfill and compaction:
(a) 
After each joint has been made, inspected, and approved, backfill shall proceed immediately. The space between the pipe and the bottom sides of the trench shall be backfilled by hand and thoroughly tamped with a light tamper. Fill shall be placed uniformly on both sides of the pipe in six-inch layers using the material obtained from on-site excavating, except for the use of select backfill material where indicated on the plans or as directed by the owner's inspector.
(b) 
Backfill to a height of two feet above the top of the pipe with earth free from stones, rock fragments, dirt clods or frozen material greater than two inches in largest diameter, and thoroughly tamped.
(c) 
The remainder of the trench shall be backfilled in twelve-inch layers, loose measure, each layer thoroughly tamped. Dampening of the material to be tamped may be required by the Engineer.
(d) 
In light soils such as sand, loam, or light gravel, the trench may be backfilled carefully with a front-end loader at a maximum rate of one cubic yard per load. Each load shall be placed immediately on the previous load.
(e) 
Backfilling prior to approvals:
[1] 
Any of the work enclosed or covered up before it has been approved will be considered unacceptable.
[2] 
The contractor shall, at his own expense, uncover all such work for inspection and approval prior to backfilling.
A. 
Description. Provide concrete encasement at locations described herein, or as directed by the engineer.
B. 
Materials.
(1) 
Concrete:
(a) 
Use concrete developing a minimum compressive strength of 4,000 psi at 28 days.
(b) 
Use air-entrained concrete.
(2) 
Cement, aggregates, water and air entrainment methods and materials: Section 914 of the Standard Specifications.
C. 
Methods of construction.
(1) 
Reference standards included in this specification section: New Jersey State Highway Department Standard Specifications for Road and Bridge Construction, 1989 (Standard Specifications):
(a) 
Section 914: Portland Cement, Mortar and Grout Concrete.
(b) 
Section 501: Concrete Structures.
(2) 
Submittals: pursuant to § 51-5, Product data, of Article II, General Specifications.
(3) 
Certificates: All deliveries of concrete shall be accompanied by delivery slips, copies of which shall be provided to Engineer by contractor.
(4) 
Location:
(a) 
Notify the Engineer when the following conditions are encountered. Subject to the Engineer's approval, concrete encasement shall be provided at these locations. All materials, methods and equipment shall be subject to the approval of the Engineer.
[1] 
At all locations where a proposed sanitary sewer main is located closer than 10 feet to a water main (measured horizontally).
[2] 
At all crossings of sanitary sewer lines and water lines where the vertical separation is less than 18 inches.
[3] 
At all crossings of sanitary sewer mains and water mains where the sanitary sewer main is located above the water main.
[4] 
All other locations where the vertical or horizontal separation between proposed and existing utility pipes are less than 12 inches.
(b) 
Concrete encasement shall conform to the standard engineering drawings. When a situation is encountered for which there is no detail, concrete encasement shall conform to the following requirements or as otherwise approved by the Engineer.
[1] 
Minimum thickness: six inches.
[2] 
Length: At utility crossings, extend concrete encasement a minimum of 10 feet on both sides of the center line of the crossing. At all other locations, extend concrete encasement until the allowable vertical or horizontal separation between utility pipes is achieved.
[3] 
All ductile iron pipe and fittings shall be wrapped in visquene where concrete encasement is used.
(5) 
Performance:
(a) 
The method of construction for concrete encasement shall conform to Section 501 of the Standard Specifications except as modified by the supplemental requirements below:
(b) 
Earth cuts may be used as forms, provided the horizontal and vertical earth surfaces can be shaped to the proper dimensions.
A. 
General.
(1) 
This specification defines the minimum requirements imposed on the contractor when submitting as-built drawings of water, sewer or force mains and pumping stations.
(2) 
Each submittal shall be transmitted to the owner and the Engineer.
(3) 
Receipt of as-built drawings in accordance with this section is a requirement of the performance bond release.
B. 
Submittal requirements.
(1) 
Minimum as-built requirements.
(a) 
The applicant shall provide three sets of as-built plans conforming to these minimum as-built requirements.
(b) 
The as-built plan should include both the proposed information (crossed out where it has changed, but remaining legible) and the as-built information shown clearly and underlined.
(c) 
The applicant must also provide a disk or CD in AutoCAD® format of the submitted plans. The plans must be submitted on a twenty-four-inch by thirty-six-inch sheet and at a scale of 1 inch = 100 feet. All text must be drawn clearly, and at a minimum size of 0.07 inch and a maximum size of 0.10 inch.
(d) 
The following information, where applicable, shall each be drawn on its own individual layer:
[1] 
Sanitary sewer mains.
[2] 
Sanitary sewer laterals/cleanouts.
[3] 
Sanitary sewer manholes.
[4] 
Sanitary sewer text.
(e) 
The plans must include that portion of the existing systems where the proposed system connects.
(f) 
The plans must be signed and sealed by a New Jersey licensed land surveyor.
(g) 
All elevations must be on the 1929 datum (i.e., NGVD 29, NJGCS, USGCS and USC and G datum).
(h) 
As a minimum, the following survey information is required: depicting all proposed facilities and as-built information.
[1] 
Sewer mains.
[a] 
As-built manhole rim and invert elevations and invert elevation of all pipes penetrating the manhole.
[b] 
As-built pipe diameter, pipe material, pipe lengths (measured from manhole center line to manhole center line), pipe slope and flow direction arrows.
[c] 
All cleanouts for sewer laterals. Provide a station from the nearest downstream manhole to each lateral or cleanout. Provide an offset from the main to each cleanout.
[d] 
Any lateral left for a future connection shall have the pipe cover and three tie-down dimensions taken at the end of the lateral (i.e., measurements from a permanent object; corner of house, catch basin, manhole, hydrant, edge of pavement, etc.).
[e] 
All as-built concrete encasements and concrete cradles shall be noted.
[f] 
Locations of all easements and location of utility within that easement. Provide a minimum of two tie dimensions from the utility to the easement line. A tie dimension shall be provided for all changes in direction and bends with stationing.
[g] 
All the above information shall be shown on a plan drawing.
[2] 
Force mains.
[a] 
Locate the force main using tie dimensions from the face of curb/edge of paving to the force main. A tie dimension shall also be provided for all changes in direction and bends with stations from nearest manhole.
[b] 
Locations of all easements and location of utility within that easement. Provide a minimum of two tie dimensions from the utility to the easement line. A tie dimension shall be provided for all changes in direction and bends with stationing.
[c] 
The as-built pipe length between bends.
[d] 
Approximate elevations at each bend and high point.
[e] 
As-built pipe diameter and pipe material.
[f] 
Manufacturer's data on air relief valves, gauges, and all valves.
[g] 
Locations of all easements and location of utility within that easement. Provide a minimum of two tie dimensions from the utility to the easement line. A tie dimension shall be provided for all changes in direction and bends with stationing.
[h] 
All the above information shall be shown on plan drawing.
[3] 
Pumping stations.
[a] 
As-built plans shall be submitted and should include both the proposed information (crossed out where changed, but remaining legible) and the as-built information shown clearly. Show all valves, curb stops, yard hydrants, underground sewer manholes, wet wells, dry well elevations and water piping, gates, etc. All valves and curb stops must be tied down as described above for water valves.
[b] 
Ten copies of manufacturer's operation and maintenance information shall be submitted for all installed equipment.
[c] 
All the above information shall be shown on plan drawing.