[Ord. No. 23-11, 9-20-2023]
A. 201.1 Design. The design of erosion and sediment controls required
for land disturbance activities shall comply with the following minimum
requirements:
1.
Land disturbance, erosion and sediment control practices, and
watercourse crossings shall be adequate to prevent transportation
of sediment from the site.
2.
Materials brought to any site or property under a permit issued
under this Code, where said material is intended to be utilized as
fill material at the site for land disturbance, erosion, or sediment
control, shall consist of clean uncontaminated earth, soil, dirt,
sand, rocks, gravel or masonry materials or other approved materials.
3.
Cut and fill slopes shall be no greater than 3:1 except as approved
by the Department of Public Works or the Department of Highways and
Traffic to meet other community or environmental objectives.
4.
Clearing and grading of natural resources, such as forests and
wetlands, shall not be permitted, except when in compliance with all
other County Ordinances.
5.
Clearing techniques that retain existing vegetation to the maximum
extent practicable shall be used and the time period for disturbed
areas to be without vegetative cover shall be minimized to the extent
practical.
6.
Clearing, except that necessary to establish sediment control
devices, shall not begin until all sediment control devices have been
installed and have been stabilized.
7.
Phasing shall be required on all sites disturbing greater than
thirty (30) acres of land. The size of each phase will be established
by the Department of Planning at the time of plan review for the issuance
of a major land disturbance permit.
B. 201.2 Erosion control design. Erosion control requirements shall
include the following:
1.
Permit holder shall install temporary stabilization when soil
disturbing activities will cease on any portion of the site and are
not planned to resume for a period exceeding fourteen (14) calendar
days. Temporary stabilization must be initiated immediately upon knowing
the duration is more than fourteen (14) days. Temporary stabilization
must be completed within seven (7) calendar days. Final stabilization
of disturbed areas must be initiated immediately and completed within
seven (7) calendar days whenever any clearing, grading, excavating
or other earth disturbing activities have permanently ceased on any
portion of the site. County may grant allowances to the seven-day
completion period for temporary and final stabilization due to weather
or equipment malfunctions. The use of allowances shall be documented
in the SWPPP.
2.
If seeding or another vegetative erosion control method is used,
it shall become established within two (2) weeks, or the site shall
be re-seeded, or a non-vegetative option employed.
3.
Techniques shall be employed to ensure stabilization on steep
slopes and in drainage ways.
4.
Soil and material stockpiles must be stabilized or covered at
the end of each workday or perimeter controls must be in place to
prevent silt from the stockpile from leaving the site.
5.
The entire site must be stabilized, using a heavy mulch layer
or another method that does not require germination to control erosion,
at the close of the construction season.
6.
Techniques shall be employed to prevent the blowing of dust
or sediment from the site.
7.
Techniques shall be employed to divert upland runoff past disturbed
slopes.
C. 201.3 Sediment control design. Sediment control requirements shall
include:
1.
Settling basins, sediment traps, or tanks and perimeter controls.
2.
Settling basins shall be provided for each drainage area within
ten (10) or more acres disturbed at one (1) time and shall be sized
to contain one-half (0.5) inch of sediment from the drainage area
and be able to contain a two-year, twenty-four-hour storm. If the
provision of a basin of this size is impractical, other similarly
effective best management practices (BMP), as evaluated and specified
in the storm water pollution prevention plan (SWPPP), shall be provided.
3.
Settling basins shall be designed in a manner that allows adaptation to provide long-term storm water management, as required by the County department(s) having enforcement authority and responsibilities described in Section
407.103 of this Code.
4.
Settling basins shall have stabilized spillways to minimize
the potential for erosion of the spillway or basin embankment.
5.
Protection for adjacent properties by the use of a vegetated
buffer strip in combination with perimeter controls.
D. 201.4 Watercourse design. Watercourse protection requirements shall
include:
1.
Encroachment into or crossings of active water courses/riparian
areas and wetlands shall be avoided to the maximum extent practicable.
All City, County, State, and Federal permits, and approvals shall
be obtained by a permit holder prior to beginning work authorized
by a County land disturbance permit.
2.
Stabilization of any watercourse channels before, during, and
after any in-channel work.
3.
If a defined watercourse is to be re-aligned or re-configured,
clearing, and grubbing activities within fifty (50) feet of the watercourse
shall not begin until all materials and equipment necessary to protect
the watercourse and complete the work are on site. Once started, work
shall be completed as soon as possible. Areas within fifty (50) feet
of the watercourse shall be re-contoured and stabilized. Permit holder
shall install temporary stabilization when soil disturbing activities
will cease on any portion of the site and are not planned to resume
for a period exceeding fourteen (14) calendar days. Temporary stabilization
must be initiated immediately upon knowing the duration is more than
fourteen (14) days. Temporary stabilization must be completed within
seven (7) calendar days. Final stabilization of disturbed areas must
be initiated immediately and completed within seven (7) calendar days
whenever any clearing, grading, excavating or other earth disturbing
activities have permanently ceased on any portion of the site. County
may grant allowances to the seven-day completion period for temporary
and final stabilization due to weather or equipment malfunctions.
The use of allowances shall be documented in the SWPPP.
4.
All storm water conveyances shall be designed according to the
criteria of the City, County, and the St. Louis Metropolitan Sewer
District (MSD) and the necessary permits obtained.
5.
Stablization adequate to prevent erosion shall be provided at
the outlets of all pipes and paved channels.
6.
Except as otherwise permitted above, stream buffers along floodplain
zoned streams and other natural waterways as required by City Code
shall not be disturbed.
E. 201.5 Construction site access design. Construction site access requirements
for major land disturbance activities shall include:
1.
A temporary construction access entrance, located to provide
adequate sight distance, shall be provided at all land disturbance
sites including a wash down area supporting all active sites.
2.
The City or Department of Highways and Traffic may require other
measures to ensure that construction vehicles do not track sediment
onto public streets or roadways or be washed with wash effluent channeled
directly into storm drains.
F. 201.6 Control of construction materials and waste. Control requirements for construction materials, construction wastes and other wastes generated on site at the land disturbance site, including facilities that process and handle materials and waste such as temporary concrete or asphalt batch plants, temporary recycling or waste incineration facilities, and similar temporary construction material and waste handling facilities shall include provisions, satisfactory to the City or those County department(s) having enforcement authority and responsibilities described in Section
407.103 of this Code for:
1.
Spill prevention and control facilities for materials such as
paint, solvents, petroleum products, chemicals, toxic or hazardous
substances, substances regulated under the Resource Conservation and
Recovery Act (RCRA) or the Comprehensive Environmental Response, Compensation,
and Liability Act (CERCLA), and any wastes generated from the use
of such materials and substances, including their containers. Any
containment systems employed to meet this requirement shall be constructed
of materials compatible with the substances contained and shall be
adequate to protect both surface and ground water.
2.
Collection and disposal of discarded building materials and other construction site wastes, including those listed in Subsection
(F)(1) above.
4.
Control of concrete truck washouts.
5.
Assurance that on-site fueling facilities will adhere to applicable
Federal and State regulations concerning storage and dispensers.
6.
Provision of sufficient temporary toilet facilities to serve
the number of workers on major land disturbance sites as directed
by the Department of Health.
7.
Assurance that on-site temporary construction materials or waste
handling equipment and facilities including, but not limited to, batch
plants, recycling or grinding facilities, and temporary incineration
equipment also adhere to County Department of Health regulations.