[Amended 3-28-2024 by Res. No. 24-03-001]
A. At the
time a property owner makes an application for a permit to connect
to the sewer system pursuant to the Authority's then-current Rules
and Regulations, the Authority shall obtain estimates of the cost
of the connection of the property extending from the Authority's main
to the property line or curb stop. The obtained cost shall be payable
with respect to such connection at the same time the tapping fee for
such connection is payable.
B. If, upon
completion of the connection, the actual cost of connection is less
than the connection fee paid, the Authority shall issue a refund to
the property owner. If the actual cost of connection is more than
the amount paid, the additional fee shall be paid by the property
owner prior to final inspection of the property connection.