A.
Application for a conditional use shall be made to the Planning Board pursuant to N.J.S.A. 40:55D-67, or to the Board of Adjustment when permitted under N.J.S.A. 40:55D-76.
B.
Review procedures.
(1)
The Planning Board shall grant or deny the application within 95 days of submission of a complete application or within such further time as may be consented to by the applicant. The review by the Planning Board of a conditional use shall include any required site plan review, and the ninety-five-day review period shall apply to the site plan review as well.
(2)
The Board of Adjustment reviewing the application pursuant to N.J.S.A. 40:55D-76 shall approve or deny the application within 120 days of submission of a complete application.
(3)
Failure of the Planning Board or Board of Adjustment to act within the period prescribed shall constitute approval of the application, and a certificate of the administrative officer as to the failure of the Board to act shall be issued on request of the applicant.