Furnish all labor, materials, tools, and equipment
necessary to lay and join all polyvinylchloride (PVC) pipe and fittings
for gravity sanitary sewers as shown or as required to complete the
work.
Polyvinylchloride pipe and fittings shall conform
to ASTM Designation D-3034, current edition (SDR-35) or ASTM accordance
with ASTM D-1784 (Class 12454-B). Pipe lengths shall be in the longest
available.
Joint seal for PVC pipe (Type SDR-35) shall be oil-resistant
compression rings of elastomeric gasket joint material conforming
to ASTM D-3212. Fittings shall have push-on, bell and spigot joints
compatible with that type of pipe.
All pipe or fittings shall be examined before laying,
and no piece shall be installed which is found to be defective. Pipe
or fittings shall not be dropped. Any damage to the pipe lining or
coatings shall be cause for rejection of pipe. All rejected pipe shall
be promptly removed from the site and replaced with sound pipe at
the contractor's expense. Handling and laying of pipe and fittings
shall be in accordance with the manufacturer's instruction.
All pipe and fittings shall be thoroughly cleaned
before laying, shall be kept clean until they are used in the work
and, when laid, shall conform to the lines and grades required. A
firm, even bearing throughout the length of the pipe placed in not
less than three separate lifts shall be constructed by tamping selected
material at the sides of the pipe up to one foot over the top of pipe.
Blocking will not be permitted. If any defective pipe is discovered
after it has been laid, it shall be removed and replaced with sound
pipe in satisfactory manner by the contractor at his own expense.
Crushed stone as specified by § A175-22 herein shall be placed six inches below the bottom of the pipe within half the diameter of the pipe being laid through the entire width of the trench.
When laying is not in progress, the open ends of the
pipe shall be closed by watertight plugs or other approved means.
Pipelines shall not be used as conductors for trench drainage during
construction.
Pipe and fittings shall be installed using laser-beam
techniques or other approved methods. Care shall be taken to ensure
true alignments and gradients as shown on the drawings.
When pipe is cut in the field, the cut end shall be
tapered back approximately 1/8 inch at an angle of 30º with the
center line of the pipe with a coarse file or grinder to remove any
rough edges which might injure the gasket.
A tee-wye service lateral shall be installed for each existing building or as directed by the Engineer. The services shall be extended to the edge of the Town right-of-way and constructed to the standards specified in Article V herein (Sewer Services).
All gravity sewers shall be low-pressure air tested
in conformance with ASTM C-828. The Engineer shall be present during
the entire testing period for approval.
The sewer line shall be sealed at each end, and one
shall have an orifice through which to pass air into the pipe. The
pressure gauge will range from zero to five psi with minimum divisions
of 0.10 psi. The pipeline under test shall be properly blocked to
prevent displacement while the line is under pressure.
The line will be allowed to stabilize at four psi
for a period of no less than five minutes. After the stabilization
period, commence timing with a stop watch. Table 2 shall be used to
determine a one-psi drop in pressure.[1] If the actual time lapse is greater than that specified,
the section undergoing the test shall have passed. If the line has
not passed the test, the contractor, at his own expense, shall make
the necessary repairs or replacements required to permanently reduce
the leakage to within the specified limits. Testing shall be repeated
until the leakage requirements are met.
All gravity sewer pipe shall also be subject to a
mandrel deflection test 30 to 60 days after installation of the pipe
or after adequate compaction is assured. If the mandrel does not pass
through the pipeline, the entire section shall be excavated and relayed
and, after backfilling and adequate compaction is assured, the pipeline
shall be retested.