A building permit shall be required for all construction and
development, including any alterations or repairs to existing buildings
or structures.
Applicants shall file the following minimum information plus
any other pertinent information as may be required by the Building
Permit Officer to make the above determination:
A. A
completed building permit application form, along with payment of
the fees for building permits, as established by resolution of the
Township Supervisors.
B. A
determination or a certification as to whether the planned construction
is within a flood-prone area.
C. A
certification of the square footage of proposed construction.
D. A
certification as to whether the construction is for agricultural purposes.
E. A
sketch or plan of the proposed construction.
F. If
required by the Township Ordinance Officer, a copy of the application
and plans for the proposed construction or development shall be submitted
to the County Conservation District for review and comment prior to
the issuance of the building permit. The recommendations of the Conservation
District shall be considered by the Building Permit Officer for possible
incorporation into the proposed plan and building permit. If the plan
is within a flood-prone area, a copy of all plans and the application
for any proposed construction or development shall be submitted by
the Building Permit Officer to the Township Engineer for review and
comment.
[Added 10-12-2000 by Ord.
No. O-6-00]
A. If any work authorized by any permit issued by this chapter shall
not have been commenced within six months after the issuance of such
permit, the permit holder shall be required to relinquish such unused
permit, which shall thereupon become invalid. Under such conditions,
neither the permit fee nor any part thereof shall be returned to such
permit holder, and if at any future time such permit holder shall
make application for another permit for the same work, such application
shall follow the same procedure and require the same fees as if no
previous permit had been issued.
B. If any work authorized by any permit issued under this chapter shall
not have been completed within 18 months after the issuance of such
permit, the permit holder shall make application for the renewal of
such permit. Any such renewal shall be for a fixed term of six months.
C. Any request for the renewal of a building permit shall be accompanied
by a fee in the amount of $25 for each renewal request.
[Amended 9-14-2000 by Ord. No. O-3-00]
Any person or corporation who or which shall violate or permits
the violation of any of the provisions of this article shall, upon
being found liable therefor in a civil enforcement proceeding commenced
by the Township, pay a fine of not more than $1,000 plus all court
costs, including reasonable attorneys' fees incurred by the Township.