[Amended 9-9-2002 by Ord. No. O-02-74; 7-8-2003 by Ord. No. O-03-184; 5-24-2004 by Ord. No. O-04-13; 9-13-2005 by Ord. No. O-05-109; 8-14-2007 by Ord. No. O-07-106]
A. 
A permit shall not be valid until the prescribed fees have been paid and the permit issued. No permit to begin work for new construction, alteration, removal, demolition or other building operation shall be issued until the fees prescribed in this section have been paid to the Department of Building Safety, nor shall an amendment to a permit necessitating an additional fee because of an increase in the estimated cost or scope of work involved be approved until the additional fee has been paid.
(1) 
Where a permit has either been revoked or a project discontinued or abandoned within six months of the issuance of such permit, such permit may be returned to the Building Official for cancellation. One-half of the permit fee shall be refunded by the City Treasurer on certificate of the Building Official, except all penalties that may have been imposed on the permit held under the requirements of this chapter shall first be collected. If a project is abandoned without notice being made to the Code Official before a six-month interval has elapsed since the date such permit was issued, no refund shall be made. Residential or nonresidential use shall be in accordance with the intent of the Building Code of the City of Nashua, New Hampshire.[1]
[1]
Editor's Note: See Art. II of this chapter.
(2) 
The fees for permits shall be charged as follows: The total amount of the permit shall be rounded to the nearest dollar (drop the total amount due under $0.50 and increase the total amount due from $0.50 to $0.99 to the next whole dollar).
B. 
The Board of Aldermen may, at its option, waive or reimburse, as the case may be, payment of fees payable under this section, in whole or in part, to the extent of the value of municipal public improvements and/or land dedication which an applicant obligates itself to make over and above impact fees and the applicant’s fair share of off-site improvements imposed as a condition of site plan or subdivision approval.
[Amended 8-14-2007 by Ord. No. O-07-106; 12-11-2007 by Ord. No. O-07-144; 6-12-2018 by Ord. No. O-18-012]
A. 
Building permit fee schedule.
(1) 
A nonrefundable application processing and review fee shall be paid at the time of filing of any application:
[Amended 3-9-2021 by Ord. No. O-21-045]
(a) 
Building permit: $50.
(2) 
New buildings, additions, alterations, mobile homes, in-ground swimming pools, basements, connecting structures, future expansion areas and areas capable of being used as living or occupiable space shall be included to calculate aggregate floor area:
[Amended 3-9-2021 by Ord. No. O-21-045]
(a) 
Residential, one- and two-family and townhouses (per square foot of area affected): $0.18.
(b) 
Commercial, including multifamily (per square foot of area affected): $0.28.
(3) 
Structures designed and certified to LEED standards shall be eligible for the following reduction in their building permit fee:
(a) 
LEED standard certification: 5%.
(b) 
LEED silver certification: 10%.
(c) 
LEED gold certification: 15%.
(d) 
LEED platinum certification: 20%.
(4) 
Alterations, repairs, fire damage:
[Amended 3-9-2021 by Ord. No. O-21-045]
(a) 
Residential (per square foot of area affected): $0.13.
(b) 
Commercial (per square foot of area affected): $0.18
(5) 
Additional plan review for minor modifications of previously approved drawings, including commercial tenant fit-up:
[Amended 3-9-2021 by Ord. No. O-21-045]
(a) 
Residential (per square foot of area affected): $0.10.
(b) 
Commercial (per square foot of area affected): $0.15.
(6) 
Moving a building from lot to lot: $200.
[Amended 3-9-2021 by Ord. No. O-21-045]
(7) 
Demolition, the total removal and disposal of a structure:
[Amended 3-9-2021 by Ord. No. O-21-045]
(a) 
Up to 1,000 square feet: $40.
(b) 
Excess beyond 1,000 square feet (fee for each additional 100 square feet or part thereof of aggregate floor area): $3.15.
(8) 
Certificate of occupancy, existing space/owner change: $50.
(9) 
When, in the Building Official's opinion, the nature of the work is not related to floor area, excluding signs, but including and not limited to membrane structures, temporary structures, canopies and awnings, pedestrian walkways, radio and television towers, radio and television antennas, elevators, commercial solar energy systems, commercial wind energy systems and commercial (other than asphalt roofing shingles) reroofing:
[Amended 3-9-2021 by Ord. No. O-21-045]
(a) 
Fee shall be based on a construction or installation cost of $0.65 per $100.
(10) 
Retaining walls over four feet in height above base of footing:
[Amended 3-9-2021 by Ord. No. O-21-045]
(a) 
Residential: minimum $25 or $0.15 per linear foot (whichever is greater).
(b) 
Commercial: minimum $50 or $0.30 per linear foot (whichever is greater).
(11) 
Minimum fee for miscellaneous equipment (each), excluding the application fee, where not otherwise provided for by this section [for example: residential antennas, small sheds (less than 200 square feet), or construction trailers] or as deemed appropriate by the Building Official or his or her designee:
[Amended 3-9-2021 by Ord. No. O-21-045]
(a) 
Residential: $30.
(b) 
Commercial: $50.
(12) 
Reinspection of the same work due to the failure to pass an initial inspection or the unavailability of the premises at the time of initial inspection: $75.
(13) 
Phased construction (foundation permits, interior demolition permits or shell permits): Phased construction shall be charged a 25% surcharge on the original permit fee for each upgrade phase.
(14) 
Surcharge for permits issued after construction started without a permit: 100% of applicable fee, but not to exceed $275 residential/$750 commercial.
[Amended 3-9-2021 by Ord. No. O-21-045]
(15) 
Expedite-service fee for special processing and after-hours service: $80 per hour per staff member, with a minimum of $250 for weekends or time not contiguous with normal work hours.
[Amended 3-9-2021 by Ord. No. O-21-045]
B. 
Mechanical permit fee schedule.
[Amended 3-9-2021 by Ord. No. O-21-045
(1) 
Residential mechanical (one- and two-family and townhouses).
(a) 
Nonrefundable application processing and review fee: $50.
(b) 
Delivery system:
[1] 
Gas supply piping (base fee downstream of meter or regulator set; test witnessed) (each): $0.30 per 1,000 BTUs.
[2] 
Installation of fuel oil or propane storage tanks less than 499 gallons, fuel oil (each): $30.
[3] 
Dormant gas meter: $45.
(c) 
Equipment:
[1] 
Furnace, HRV/ERV, boiler or water heater: $45.
[2] 
Generator including gas piping: $45.
[3] 
Ductless split system: $40.
[4] 
Hot water storage tank: $20.
[5] 
Air conditioner coiler or condenser: $20.
[6] 
Exhaust or ventilation fan (each): $12.
[7] 
Room heater or gas appliance: $30.
(d) 
Gas or wood factory fireplace, insert, or pellet stove and associated chimney: $45.
(e) 
Masonry fireplace and associated chimney: $75.
(f) 
Manufactured chimney: $40.
(g) 
Minimum fee for miscellaneous equipment (each), excluding the application fee, where not otherwise provided for by this section: $40.
(h) 
Reinspection of the same work due to the failure to pass an initial inspection or the unavailability of the premises at the time of initial inspection: $75.
(i) 
Surcharge for permits issued after construction started without a permit: 100% of applicable fee, but not to exceed $275.
(2) 
Commercial mechanical (including multifamily).
(a) 
Nonrefundable application and review processing fee: $50.
(b) 
Delivery system:
[1] 
Gas pipe: $0.35 per 1,000 BTU.
[2] 
Installation of fuel oil or propane storage tanks less than 499 gallons, fuel oil (each): $20.
[3] 
Dormant gas meter: $45.
(c) 
Equipment:
[1] 
Furnace, HRV/ERV, boiler, water heater, unit heater or generator: $55.
[2] 
Hot water storage tank: $22
[3] 
Rooftop air handlers: $40.
[4] 
Chiller, evaporator, condenser or cooling tower (each): $30.
[5] 
Duct work (per 10 square feet of area served): $0.125.
[6] 
Fire and smoke dampers: $10.
(d) 
Chimney or chimney liner (masonry or metal): $90.
(e) 
Fans: $30.
(f) 
Kitchen exhaust systems:
[1] 
Hoods and exhaust fans (each): $90.
(g) 
Minimum fee for miscellaneous equipment (each), excluding the application and review fee, where not otherwise provided for by this section: $45.
(h) 
Reinspection of the same work due to the failure to pass an initial inspection or the unavailability of the premises at the time of initial inspection: $75.
(i) 
Surcharge for permits issued after construction started without a permit: 100% of applicable fee, but not to exceed $750.
C. 
Electrical permit fee schedule.
[Amended 3-9-2021 by Ord. No. O-21-045]
(1) 
Residential electrical (one- and two-family and townhouses).
(a) 
Nonrefundable application processing and review fee: $50.
(b) 
New construction, additions, renovations (per square feet of habitable area): $0.080.
[1] 
Service entrance (new dwelling only): $35.
(c) 
House meter: $55.
(d) 
Service change:
[1] 
Up to two units: $55.
[2] 
Each additional unit: $20.
(e) 
Adding subpanel(s) (each): $30.
(f) 
Adding or relocating meter(s): $55.
(g) 
Pools (in-ground): $60.
(h) 
Temporary service (each): $50.
(i) 
Minimum fee for miscellaneous equipment (each), excluding the application fee, where not otherwise provided for by this section: $40.
(j) 
Low-voltage wiring (per square feet of work area): $0.080.
(k) 
Reinspection of the same work due to the failure to pass an initial inspection or the unavailability of the premises at the time of initial inspection: $75.
(l) 
Surcharge for permits issued after construction started without a permit: 100% of applicable fee, but not to exceed $275.
(2) 
Commercial electrical (including multifamily).
(a) 
Nonrefundable application processing and review fee: $50.
(b) 
Electrical service entrance and service change (per amp): $0.50.
(c) 
Temporary service (each): $50.
(d) 
Panels and subpanels (each): $30.
(e) 
Outlets:
[1] 
For switches, receptacles, and fire and smoke detectors (each): $1.
[2] 
For lighting and lighting fixtures, except as otherwise provided (each four feet of continuous fluorescent lighting shall be deemed a separate lighting fixture) (each): $1.
[3] 
For ranges, dryers, and similar heating devices (each): $15.
[4] 
For high-intensity lighting and fixtures (each) (250 watt and above): $15.
(f) 
Fixed multioutlet receptacle assemblies (for each six feet): $8.
(g) 
Track lighting (each 10 feet): $8
(h) 
Motor control centers (each), automatic transfer switches (each), wiring of HVAC units (per unit): $35.
(i) 
Water heaters (each): $15.
(j) 
Electric baseboard heat (per unit): $10.
(k) 
Buss ducts (each section): $15.
(l) 
Transformers, generators, motors, x-ray machines (each): $25.
(m) 
Paging and sound systems:
[1] 
Per speaker: $5.
[2] 
Per console: $25.
(n) 
Signs (each): $35.
(o) 
Minimum fee for miscellaneous equipment (each), excluding the application fee, where not otherwise provided for by this section: $40.
(p) 
Reinspection of the same work due to the failure to pass an initial inspection or the unavailability of the premises at the time of initial inspection: $75.
(q) 
Surcharge for permits issued after construction started without a permit: 100% of applicable fee, but not to exceed $750.
(r) 
Annual permit fee: $300.
[1] 
In lieu of an individual permit for each alteration to an already approved electrical installation, the Code Official shall issue an annual permit, upon application therefor, to any person, firm or corporation regularly employing one or more certified electricians in the building, structure or on the premises owned or operated by the applicant for the permit.
[2] 
Annual records. The person to whom an annual permit is issued shall keep a detailed record of all alterations to an approved electrical installation made under such annual permit, and such records shall be accessible to the Code Official at all times or shall be filed with the Code Official as designated.
D. 
Plumbing permit fee schedule.
[Amended 3-9-2021 by Ord. No. O-21-045]
(1) 
Residential plumbing (one- and two-family and townhouses).
(a) 
Nonrefundable application processing and review fee: $50.
(b) 
Per fixture or fixture connection (tub, shower, sink, water closet, lavatory, dishwasher, outside faucet, clothes-washing machine, backflow preventer, etc.): $9.50.
(c) 
Pumps and ejectors (each): $18.
(d) 
Electric water heaters (each): $18.
(e) 
Water pipes (per 100 feet or part thereof): $18.
(f) 
Sanitary sewer connection or repair : $35.
(g) 
Drainage, waste and vent pipes: (per 100 feet or part thereof): $18.
(h) 
Minimum fee for miscellaneous equipment (each), excluding the application fee, where not otherwise provided for by this section: $40.
(i) 
Reinspection of the same work due to the failure to pass an initial inspection or the unavailability of the premises at the time of initial inspection: $75.
(j) 
Surcharge for permits issued after construction started without a permit: 100% of applicable fee, but not to exceed $275.
(2) 
Commercial plumbing (including multifamily of three dwelling units and greater).
(a) 
Nonrefundable application processing and review fee: $50.
(b) 
Per fixture (tub, shower, sink, water closet, lavatory, floor drain, drinking fountain, urinal, dishwasher, garbage grinder, outside faucet, clothes-washing machine, washdown station, etc.): $12.
(c) 
Pumps and ejectors (each): $35.
(d) 
Grease interceptor: $30.
(e) 
Electric water heaters (each): $25.
(f) 
Irrigation system (includes backflow preventer): $20.
(g) 
Backflow preventer (each):
[1] 
Atmospheric vacuum breakers: $16.
[2] 
Pressure vacuum breakers: $16.
[3] 
Dual check valve: $16.
[4] 
Reduced-pressure principle: $16.
(h) 
Water pipes: (per 100 feet or part thereof): $18.
(i) 
Sanitary sewer and storm drain connection or repair of: $18.
(j) 
Drainage, waste and vent pipes: (per 100 feet or part thereof): $18.
(k) 
Roof drain and storm drainage piping: (per 100 feet or part thereof): $18.
(l) 
Roof drain inlets (each): $20.
(m) 
Minimum fee for miscellaneous equipment (each), excluding the application fee, where not otherwise provided for by this section: $40.
(n) 
Reinspection of the same work due to the failure to pass an initial inspection or the unavailability of the premises at the time of initial inspection: $75.
(o) 
Surcharge for permits issued after construction started without a permit: 100% of applicable fee, but not to exceed $750.