Sketch plans required pursuant to RSA 155-E:3
shall be filed with the Administrative Officer and shall be prepared
by a registered professional engineer or a registered land surveyor,
at a scale of 200 feet to the inch, and shall indicate the requirements
of RSA 155-E:3 in addition to the following:
B. Water supply and sanitary sewerage systems and temporary
and permanent drainage systems for the site;
C. Topographic mapping showing contours at intervals
of not more than 10 feet;
D. Submission of plan for lighting if night operation
is permitted by Zoning Board of Adjustment;
E. Proper provision for vehicular traffic, service roads
and control of entrances and exits to highways;
F. The relocations of existing and future buildings and
operations machinery to the removal areas;
G. Delineation of the existing removal areas and the
proposed area for removal in the immediate future;
H. Location of fencing if applicable.
It is recognized that land reuse of a removal
site is in the public interest; therefore, a reclamation plan, as
described in RSA 155:E-5 and 155:E-5-a, must be submitted to and approved
by the Administrative Officer following review by the Planning Board,
subject to the following regulations:
A. The Administrative Officer may require that the reclamation
plan show up to three alternative future land reuses.
B. Any land reuse must correspond to a situation which
could reasonably occur in the immediate future (zero to five years),
and be revised as necessary as to the existing physical character
as the removal area changes.
C. The reclamation bond, required pursuant to RSA 155-E: 4-a, shall specify the time for completion of all the applicable requirements of this Part
5 and shall be of an amount determined by the City Engineer and Administrative Officer as sufficient to ensure compliance of the requirements.