[Amended 2-9-2009 by L.L. No. 3-2009]
The Planning Board may conduct a public hearing on the site plan. In the event that the Planning Board conducts a public hearing, such hearing shall be held within 62 days of the receipt of a complete application for site plan review and shall be advertised in the Town’s official newspaper or, if there is none, in a newspaper of general circulation in the Town at least five days before the public hearing. The applicant and the owners of adjacent properties (as such owners are identified in the application) shall be mailed notification of the hearing at least 10 days prior to the date of the public hearing. The Planning Board shall comply with the provisions of the State Environmental Quality Review Act under Article 8 of the Environmental Conservation Law and its implementing regulations.
A decision on the final application shall be made within 62 days after closure of the public hearing or, if no such public hearing is held, within 62 days after receipt of a complete application for site plan review; however, failure to make a decision under such time frame shall not be deemed an approval. In its decision, the Planning Board may approve, approve with modifications or disapprove the site plan. The decision shall be filed with the Town Clerk within five business days after such decision is rendered and a copy thereof mailed to the applicant. The time period in which the Planning Board must render its decision may be extended by mutual consent of the applicant and the Planning Board.
A. 
Approval. Upon approval of the site plan and payment by the applicant of all fees and reimbursable costs due the Town, the Planning Board shall endorse its approval on a copy of the site plan and shall immediately file it and a written statement of approval with the Town Clerk.
B. 
Approval with modifications. The Planning Board may approve the final site plan with modifications. After adequate demonstration to the Planning Board that all required modifications have been incorporated in the plan and payment by the applicant of all fees and reimbursable costs due the Town, the Planning Board shall endorse its approval on a copy of the site plan and shall immediately file it and a written statement of approval with the Town Clerk. A copy of the written statement of approval shall be mailed to the applicant.
C. 
Disapproval. Upon disapproval of the site plan, the decision of the Planning Board shall set forth the reasons therefor.