The following exhibits shall accompany the application
for final approval, in addition to any other exhibits that may have
been required by the Board as a condition of final approval:
A. A letter from the Township Engineer indicating:
(1) The Engineer is in receipt of a map showing utilities
under the jurisdiction of a public utility in in approximate location
and elevation, identifying those portions already installed and those
to be installed.
(2) The subdivider has either completed the installation
of all improvements in accordance with the requirements of this chapter
or posted with the Township Clerk a performance guaranty in an amount
sufficient to cover the cost of all improvements herein or uncompleted
portions thereof as estimated by the Township Engineer and assuring
the installation of such improvements on or before an agreed date.
(3) All items and amounts required for the corporate surety
maintenance guaranty.
(4) The final plat conforms to the preliminary plat as
submitted and approved.
B. A letter from the Tax Collector indicating that all
taxes have been paid to date on the property.
C. A letter from the Township Clerk indicating:
(1) That the amount, form and content of the maintenance
guaranty have been accepted by the Township Committee.
(2) Where appropriate, pursuant to this chapter, that
monies, as provided herein, have been paid to the Township as reimbursement
for engineering inspection costs of improvement construction or installation
incurred since preliminary approval.
Copies of the final plat shall be distributed
to the following:
E. Appropriate fire company.
I. Other municipal or County agencies or authorities
as may be required.
No action shall be taken until such time as
the above officials review said plat or 30 days have elapsed from
date of referral.
[Amended 7-13-1988 by Amendment 1]
Final approval shall be granted or denied within
the time prescribed by N.J.S.A. 40:55D-50b or as otherwise specified
in the Municipal Land Use Law. If the Planning Board approves the
final plat, a notation to that effect shall be made on each plat,
signed by the Chairperson and Secretary of the Planning Board. Failure
of the Planning Board to act within the period prescribed shall constitute
final approval in accordance with N.J.S.A. 40:55D-50b.
Any plat which requires County Planning Board approval pursuant to N.J.S.A. 40:27-6.2 shall be forwarded to the County Planning Board for its action. The Planning Board may grant final approval subject to approval by the County Planning Board as provided in §
115-76B.
The final plat approval shall be filed by the
subdivider with the County Recording Officer within 95 days from the
date of such approval. If any final plat is not filed within that
period, the approval shall expire. For good cause, the Planning Board
may extend the time for the filing of the plat for an additional period
not to exceed 95 days. No plat shall be accepted for filing by the
Clerk of the County unless it has been duly approved by the Township
of Alexandria Planning Board and signed by its Chairperson and Secretary.
The granting of final approval shall guarantee
to the applicant that the zoning requirements applicable to the preliminary
approval first granted and all other rights conferred upon the developer,
whether conditionally or otherwise, shall not be changed for a period
of two years after the date of final approval, provided that these
rights shall expire if the plat has not been duly recorded within
the prescribed time period.