Posts with signs carrying the names of the streets
or other ways shall be installed at the beginning of all new ways
and at the intersection of all ways whether existing or proposed within
a subdivision. There shall be at least one such sign and signpost
at each intersection. Said signs and signposts shall follow the specifications
of the Town of Dalton Highway Department.
Curbing shall be constructed on both sides of
the street. Sidewalks shall be constructed on both sides of the street
in all zones except R-1 unless deemed otherwise by the Planning Board.
Construction shall be in accordance with the specifications and standards
of the Town of Dalton Highway Department.
All construction work under these regulations shall conform to the requirements and standards of the Town of Dalton Highway Department and to the specifications for highways which may be adopted by the Select Board. Construction specifications and standards as shown on
Figures 1 to 12 inclusive are made a part of these regulations. Unless otherwise specified, all work and materials used
in the work to be done shall conform to the requirements of "The Commonwealth
of Massachusetts. Department of Public Works. Standard Specifications
for Highways. Bridges and Waterways" 1973 Edition, or any amendment
thereof, addition thereto, or substitution therefor.
To prevent erosion, shoulders and graded slopes
shall be seeded on completion or planted with shrubs or similar approved
landscape treatments. Seed and planting specifications shall be in
accordance with Section H-3 of the Standard Specifications for Highways
and Bridges of the Commonwealth. All new planting within the street
right-of-way shall be with good nursery stock and will be subject
to inspection after one year. Trees, shrubs or grass found by the
Planning Board to be dead or in an unsatisfactory condition may be
required to be replaced by the subdivider.
The entire area of the subdivision must be cleaned
up so as to leave a neat and orderly appearance from debris and other
objectionable materials. The subdivider shall be responsible for providing
thoroughly clean and unsilted storm drain lines within the subdivision.
The subdivider shall submit to the Town of Dalton
Highway Department record plans showing the roadways, sewerage and
drainage facilities as built. The record plan shall include ties to
sewer and drainage manholes, catch basins, water valves and sewer
and water house services.