At the conclusion of the work, the contractor
shall thoroughly clean all of the new sewers by flushing with water
or other means to remove all dirt, stones, pieces of wood, or other
material which may have entered during the construction period. Debris
cleaned from the lines shall be removed from the lowest manhole. If,
after this cleaning any obstructions remain, they shall be removed.
Leakage tests shall be made by the contractor
on each manhole and shall be observed by the Engineer. The test shall
be the exfiltration test made as described below:
A. The manhole shall be filled with water to the top
of the cone section. If the excavation has not been backfilled and
observation indicates no visible leakage, that is, no water visibly
moving down the surface of the manhole, the manhole may be considered
to be satisfactorily watertight. If the test, as described above,
is unsatisfactory as determined by the Engineer, or if the manhole
excavation has been backfilled, the test shall be continued. A period
of time may be permitted if the contractor so wishes, to allow for
absorption. At the end of this period, the manhole shall be refilled
to the top of the cone, if necessary, and the measuring time of at
least eight hours begun. At the end of the test period, the manhole
shall be refilled to the top of the cone, measuring the volume of
water added. This amount shall be extrapolated to a twenty-four-hour
rate and the leakage determined on the basis of depth. The leakage
for each manhole shall not exceed one gallon per vertical foot for
a twenty-four-hour period.
B. If the manhole fails this requirement, but the leakage
does not exceed three gallons per vertical foot per day, repairs by
approved methods may be made as directed by the Engineer to bring
the leakage within the allowable rate of one gallon per foot per day.
Leakage due to a defective section or joint or exceeding the three-gallon
per vertical foot per day shall be cause for the rejection of the
manhole. It shall be the contractor's responsibility to uncover the
manhole as necessary and to disassemble, reconstruct or replace it
as directed by the Engineer. The manhole shall then be retested as
specified and to the satisfaction of the Engineer.
C. No adjustment in the leakage allowance will be made
for unknown causes such as leaking plugs, absorptions, etc., i.e.,
it will be assumed that all loss of water during the test is a result
of leaks through the joints or through the concrete. Furthermore,
the contractor shall take any steps necessary to assure the Engineer
that the water table is below the bottom of the manhole throughout
the test.
D. In lieu of the water leakage test mentioned above,
and where applicable as determined by the Engineer, the contractor
shall perform a vacuum test on the manholes.
E. The vacuum test shall be done immediately after the
complete assembly of the manhole (including filling liftholes, etc.,
as specified).
F. The contractor shall plug the pipe openings and place
the vacuum testing apparatus in the manhole using a sixty-inch per
pound torque to tighten the external clamps. The compression band
shall then be inflated to seal the vacuum base. The vacuum pump shall
be connected to the outlet port of the base with the valve open. A
vacuum of 10 inches of Hg shall be drawn. The valve shall then be
closed.
G. The test shall pass if the vacuum remains at 10 inches
Hg or drops to nine inches Hg in a time greater than one minute. If
the manhole fails the initial test, the contractor shall locate the
leak and make the proper repairs. Leaks may be filled with a wet slurry
of quick-setting material as approved by the Engineer.
All new manholes shall be thoroughly cleaned
of all silt, debris and foreign matter of any kind, prior to final
inspection.