Whenever any subdivision of land is proposed, the subdivider or his agent shall apply in writing to the Planning Commission for approval of a preliminary plat and submit five (5) copies thereof prepared in accordance with Article VI of this chapter. He shall submit a fee with this application in accordance with Article XII of this chapter. This application shall be submitted at least seven (7) days prior to the meeting of the Planning Commission at which it is to be considered.
Following review of the preliminary plat, the Planning Commission shall communicate within forty-five (45) days in writing with the subdivider, informing him of action taken and stating specific changes, if any, that are required in the preliminary layout. If for any reason the subdivision is disapproved, the reasons for such disapproval shall be given. In cases where approval of the plat is conditional upon changes being made in the subdivision layout, one (1) copy of the plat shall be returned to the subdivider with the desired changes marked thereon.
After receiving notice of approval of the preliminary plat, the subdivider shall submit to the Administrator four (4) copies of plans and specifications for all improvements to be installed. The Administrator shall advise the subdivider concerning the character and extent of improvements and the estimated amount of the performance bond or other surety that will be required before final approval of the subdivision plat. The Administrator, after consultation with the Resident Engineer of the Virginia Department of Highways and Transportation, shall advise the subdivider of approval or disapproval, in writing, within sixty (60) days.
The subdivider shall, prior to filing with the Planning Commission a final plat for approval, complete all improvements and installation of utilities required under these regulations, or in lieu of completing said improvements, the subdivider shall furnish the town with a performance bond as required by Article X of this chapter.
The subdivider shall, within six (6) months after official notification of approval by the Planning Commission in respect to the preliminary plat, apply in writing to the Planning Commission for approval of the final subdivision plat and submit three (3) copies thereof prepared in accordance with Article VII of this chapter. This application shall be submitted at least seven (7) days prior to the meeting of the Planning Commission at which it is to be considered. The subdivider may file for approval only that portion of the approved preliminary plat which he proposes to record and develop at that time.
A. 
Unless an application for final approval is made within six (6) months after approval of the preliminary plat, said approval of the preliminary plat shall become null and void.
B. 
The Planning Commission shall, within forty-five (45) days from the date of submittal of the final plat, approve, modify or disapprove such plat; and failure to act within forty-five (45) days shall be deemed approval.
C. 
Approval of the final subdivision plat by the Planning Commission shall be shown on the face of the plat by the signature of the Chairman. The approval of the plat shall not be finally effective until the subdivider has made or provided for the improvements required pursuant to Article X of this chapter to the satisfaction of the Town Council and this approval has been attested by the signature of the Mayor on said plat.