The applicant shall agree in writing to construct streets and other improvements from the lot or lots to be sold or built upon to an existing improved street, subject to the provisions of § 215-4B of this chapter. The work shall be performed in strict accordance with approved plans and the Township standards and specifications or the applicable provisions of Pennsylvania Department of Transportation Specifications 408, latest edition, or any subsequent number or section thereof. No plat shall be finally approved until the developer has completed all of the necessary and appropriate improvements as required as a condition for final approval of a plat or until such time as the applicant has provided for the deposit with the Township of a security acceptable to the Township Commissioners in an amount sufficient to cover the costs of any improvements which may be required.
All water, gas, electric and other pipes and conduits and all service connections or laterals shall be laid to the full width of the ultimate right-of-way, where the need therefor can be reasonably anticipated, before streets are paved. The arrangements for said service connections or laterals shall be the responsibility of the subdivider, developer or builder.
A. 
Notice. The Township Engineer shall be notified 48 hours in advance of the commencement of any construction operation in order that provision may be made for inspection by the Township.
B. 
Samples of materials. Samples of the materials shall be furnished to the Township in the same manner as is required of contractors under the Highway and Sanitary Drainage Specifications.