The developer shall install not only the waterline in the street
but also all building water laterals with lateral shutoff valves from
the water main to the property line along any route of extension or
within the development. The developer shall cap all open ends of the
waterline and provide exact lateral ties and elevations so that the
capped ends will be readily available.
The installation of waterlines and laterals shall be in accordance
with the Town of Smithfield Water Supply Board plan review and any
adopted policies and procedures, copies of which may be obtained from
the Water Supply Board. Specifications for all special structures
and conditions shall be prepared by the developer for the Water Supply
Board or its authorized representative's review and approval.
Where site constraints may prevent installation of the waterline
within the street, twenty-foot wide easements shall be required and
deeded to the Town. The waterline shall favor one side of the easement
to allow for equipment placement in the event of a repair. The easement
shall extend beyond the waterline to a public highway. All easements
must be readily passable by way of a constructed gravel road for maintenance
vehicles and equipment and shall be gated, unless otherwise directed
by the Board. No permanent structures shall be built on any easement.
The form and location of all easements must be approved in advance
of construction by the Smithfield Water Supply Board.
Upon completion of construction and prior to acceptance of any
water connection, the completed facilities shall be tested by the
installer and witnessed and approved by the Smithfield Water Supply
Board. All final information shall be corrected and/or added to the
original drawings and two complete sets of Mylar reproducible as-built
drawings shall be furnished to the Smithfield Water Supply Board.
The developer shall also deliver the as-built set of plans in an AutoCAD
or ESRI GIS and Adobe electronic formats.
A road-opening permit from either the Smithfield Public Works
Department or RI DOT will be required along with the payment of all
applicable charges associated with this permit prior to any construction.
All construction shall be in accordance with the approved plans and
materials, standard specifications and details. Any work not meeting
the approved standards shall be immediately removed and replaced at
the full cost of the developer. Board approval for installation does
not negate the developer's responsibility to obtain any and all
other applicable local, state and federal approvals and permits.