If compliance with any of the requirements of this chapter would
result in an exceptional hardship to a prospective builder, developer
or landowner, the Borough may, upon request, grant relief from the
strict application of the requirements.
No variance shall be granted within any identified floodplain area that would cause any increase in BFE. In A Area/District, BFEs are determined using the methodology in § 125-19C.
Except for a possible modification of the regulatory flood elevation requirement involved, no variance shall be granted for any of the other requirements pertaining specifically to development regulated by prohibited activities (Article VI) or to development which may endanger human life (§ 125-26).
In granting any variance, the Borough shall attach whatever reasonable
conditions and safeguards it considers necessary in order to protect
the public health, safety, and welfare, and to achieve the objectives
of this chapter.
A complete record of all variance requests and related actions shall
be maintained by the Borough. In addition, a report of all variances
granted during the year shall be included in the annual report to
the FEMA.
Notwithstanding any of the above, however, all structures shall be
designed and constructed so as to have the capability of resisting
the one-percent-annual-chance flood.