When the County issues a permit requiring mitigation under §§ 520-37, 520-43 and 520-45, the property owner must submit a complete permit application, that is reviewed and approved by the County. The application shall include the following:
A. 
A site plan that describes the proposed mitigation measures.
(1) 
The site plan shall be designed and implemented to restore natural functions lost through development and human activities.
(2) 
The mitigation measures shall be either of the following activities:
(a) 
Implement a stormwater management plan providing that there is no increase in stormwater discharge from the lot or unit as a result of the proposed construction for storms up to and including the ten-year, twenty-four-hour storm event.
(b) 
Restore and/or maintain a shoreline buffer area of native vegetation meeting the requirements of § 520-29.
B. 
An implementation schedule and enforceable obligation on the property owner to establish and maintain the mitigation measures.
(1) 
The enforceable obligations shall be evidenced by an instrument recorded in the office of the Register of Deeds.
C. 
An inspection report by a Wisconsin licensed plumber showing that the associated sanitary system meets current standards.
(1) 
If the associated sanitary system does not meet current standards, a permit to install a code compliant system must be obtained prior to being issued a land use permit. The sanitary system shall be installed within one year of the land use permit being issued.