Screening and Visibility, Flat Roof: Building-Mounted
Solar PV System Plan
Situation B: Interior Lot
|
Type of WCF/Application
|
Notice of Incompleteness
|
Final Decision
|
---|---|---|
Co-located WCF
|
30 calendar days from receipt of application for initial notice;
10 calendar days from receipt of supplemental application for subsequent
notices
|
90 total calendar days from receipt of initial application.
|
Eligible facilities request
|
30 calendar days from receipt of initial application; 10 calendar
days from receipt of supplemental application for subsequent notices
|
60 total calendar days from receipt of initial application.
|
Small WCF (co-located)
|
10 business days from receipt of initial or supplemental application
|
60 total calendar days from receipt of initial application
|
Small WCF (new or replacement wireless support structure)
|
10 business days from receipt of initial or supplemental application
|
90 total calendar days from receipt of initial application
|
Tower-based WCF
|
30 calendar days from receipt of application for initial notice;
10 calendar days from receipt of supplemental application for subsequent
notices
|
150 total calendar days from receipt of initial application
|