[Adopted 4-4-1986 by L.L. No. 1-1986]
This local law shall be known and may be cited as Local Law No. 1 of 1986, a local law amending Local Law No. 2 of 1973 of the Town of Halfmoon entitled "Local Law Relating to Zoning for the Town of Halfmoon," providing for the creation of a planned development district to be known as "Saratoga Economic Development Corporation Industrial Park Planned Development District."
Local Law No. 2 of 1973, of the Town of Halfmoon entitled "Local Law Relating to Zoning for the Town of Halfmoon" and the Zoning Map of the Town of Halfmoon, as set forth and enacted in Local Law No. 1 of 1984, be and the same hereby are amended as hereinafter described, creating within the boundaries of said newly described area a planned development district to be known as "Saratoga Economic Development Corporation Industrial Park."
The area of said Saratoga Economic Development Corporation Industrial Park is bounded and described as set forth in Exhibit B attached hereto and made a part hereof.
[1]
Editor's Note: PDD maps and plans are on file in the Town's offices.
There shall be developed within the areas of said Saratoga Economic Development Corporation Industrial Park no more than 10 lots consisting of light industrial plants, buildings, facilities, roads or streets as follows:
A. 
There shall be constructed streets together with connecting streets and an existing street or portion thereof shall be abandoned as shown on the preliminary map on file with the Town Clerk herein.
B. 
No more than three lots will be developed before the district is connected to a municipal water source. During the time the district relies on on-site wells, no process or manufacturing use of water will be permitted.
C. 
Wastewater disposal will be provided by connection to the County Sewer District. Plans for the collection system must be approved by Saratoga County Sewer District No. 1 and the State Department of Environmental Conservation.
D. 
A stormwater management system will be installed to assure that adjacent and downstream properties, both public and private, will not suffer increased flooding.
E. 
No facilities which require exhaust stacks for manufacturing processes or process emissions will be permitted. Minor exhaust stacks may be allowed for maintenance and repair activities which are incidental to the primary use of the site.
F. 
Visual impacts will be minimized through the use of buffer areas, setbacks, architectural design, and screening such as berms, fences and plant materials for the district area as a whole and for each developed site.
G. 
The applicant will construct the interior loop road and the realignment of Werner Road in compliance with Town specifications.
H. 
Permits from the State Department of Transportation for access to Route 146 will be obtained.
I. 
Approval of the State Department of Health will be obtained for the water system, as appropriate.
J. 
Approval of the Town of Halfmoon for the water distribution system when connected to a municipal source will be obtained.
K. 
The area described is approximately 100 acres in size and is located on the west side of Route 146, westerly of Werner Road.
L. 
Before construction of Saratoga Economic Development Corporation Light Industrial Park Planned Development District is started or any building permit is issued relating thereto, final plans and specifications shall be submitted to the Planning Board of the Town of Halfmoon and filed with the Town Clerk of the Town of Halfmoon. Planning and Town Board approvals are required prior to construction.
M. 
During the construction of Saratoga Economic Development Corporation Light Industrial Park Planned Development District, there shall be constructed, as set forth as part of the plans and specifications to be approved by the Planning Board of the Town of Halfmoon, parking areas providing sufficient parking for all plants or buildings.
All improvements shall be designed and constructed pursuant to plans and specifications approved by a duly licensed architect and in strict compliance with the New York State Building Code. The Planning Board shall not give approval as referred to in said local law relating to zoning, Section 1002, paragraph 8,[1] unless and until all approvals required by each and every other government or governmental entity have been obtained. The architect performing the work herein described shall be employed by and at the expense of the developer. All construction during performance thereof and upon completion shall be subject to the inspection and approval of the Enforcement Officer of the Town of Halfmoon. All roads and/or streets to be constructed within the project limits pursuant to this local law shall be constructed pursuant to specifications at the time in effect for the construction of Town highways in the Town of Halfmoon. Any private water system must and shall be connected to public or municipal facilities when available.
[1]
Editor's Note: See now § 165-54H in the Zoning chapter.
Upon satisfactory completion in accordance with the requirements of the appropriate state agencies, all water distribution facilities including mains, valves, fittings, hydrants and that portion of the service connection which lies within the limits of the dedicated roadways shall be offered to the Town of Halfmoon with delivery to the Town of Halfmoon of duly executed deeds, easements and bills of sale, as appropriate, at no cost to the Town of Halfmoon.
For those portions of the water distribution system including mains, valves, fittings and hydrants which lie outside the limits of dedicated highways, easements for the maintenance, repair and replacement of the system shall be conveyed to the Town of Halfmoon at no cost to the Town of Halfmoon.
Upon satisfactory completion and connection in accordance with the requirements of the appropriate state agencies, all sewage facilities including mains, manholes and pumping stations shall be offered to Saratoga County Sewer District No. 1 at no cost to said district with delivery to said Saratoga County Sewer District No. 1 of duly executed deeds, easements and bills of sale, as appropriate, together with easements for the maintenance, repair and replacement of all those portions of the system which lie outside the limits of the dedicated streets. Parcels of land for pumping station and access thereto shall be offered in fee to said district with delivery to said district of a duly executed deed or deeds, at no cost to said district.
Upon satisfactory completion in accordance with the approved drawings, all stormwater management facilities within the limits of dedicated streets shall be offered to the Town of Halfmoon with duly executed deeds, easements and bills of sale, as appropriate, at no cost to the Town of Halfmoon.
For all those portions of the stormwater management facilities, including pipes, catch basins, manholes and retention areas, which lie outside the limits of dedicated streets, easements for the maintenance, repair and replacement of the system shall be conveyed to the Town of Halfmoon at no cost to the Town of Halfmoon.
This amendment shall be deemed automatically revoked and void and the previous regulations and laws shall obtain if, within one year from the approval of the Planning Board of the Town of Halfmoon for the construction of the project, commencement of the construction of Saratoga Economic Development Corporation Light Industrial Park Planned Development District has not begun, or if after construction has begun unless substantial progress continues without undue interruption thereafter or if the development is not completed within eight years of such approval. As to the area within which a building or buildings have been constructed pursuant to this local law, there shall be no voiding of the amendment and, as to said area and building or buildings, this amending local law shall continue in full force and effect and the area zoned by this local law shall be the area within which said building or buildings was or were constructed pursuant to this amending local law. For proper cause shown, the Town Board of the Town of Halfmoon may, upon such terms and conditions as it deems proper, extend either the six-month period or the eight-year period, or both, and/or may waive the requirement that substantial progress shall continue without undue interruption. Any such extension of time or waiver may be made by the Town Board without a public hearing.
Section 402 of the said Local Law 2 of 1973, Zoning Map, is hereby amended by providing that Saratoga Economic Development Corporation Light Industrial Park be set forth on a supplementary map which is hereby made a part of this local law as Exhibit A. The property set forth on such map is the real property described in the description annexed hereto made by The Environmental Design Partnership, which is hereby made a part of this local law as Exhibit B.
[1]
Editor's Note: PDD maps and plans are on file in the Town's offices.
[Added 8-5-1997 by L.L. No. 4-1997]
A. 
Title. This local law shall be known and may be cited as Local Law No. 4 of 1997, a local law amending Local Law No. 1 of 1995 of the Town of Halfmoon, entitled "Local Law Relating to Zoning for the Town of Halfmoon," as previously amended and supplemented by the local laws and an ordinance relating to zoning of the Town of Halfmoon, and further amending Local Law No. 1 of 1986, providing for the creating of a planned development district known as Saratoga Economic Development Corporation Industrial Planned Development District.
B. 
Establishment of district. Local Law No. 5 of 1995 of the Town of Halfmoon, entitled "Local Law Relating to Zoning for the Town of Halfmoon," and the Zoning Map of the Town of Halfmoon, as set forth and enacted in Local Law No. 5 of 1995 and Local Law No. 1 of 1986, be and the same hereby are amended by modifying the provisions applicable to the planned development district known and described as "Saratoga Economic Development Corporation Industrial Planned Development District," which was created by said Local Law No. 1 of 1986.
C. 
Boundaries. The area of said planned development district is contained in one lot to be added to the Saratoga Economic Development Corporation Industrial Planned Development District and is bounded and described as set forth in Exhibit A attached hereto and made a part hereof and as shown on a certain amended site plan map thereof prepared by ABD Engineers & Surveyors, dated June 21, 1996, entitled "New York State Electric and Gas Corporation."[1]
[1]
Editor's Note: PDD maps and plans are on file in the Town's offices.
D. 
Amendment. The planned development district legislation is changed to permit the setback on Lot No. 1 of the Halfmoon Light Industrial Park to be reduced from 200 feet to 70 feet and further eliminating the stormwater management area off Lot No. 1 thereof, as shown on a map made by ABD Engineers & Surveyors dated June 21, 1996, entitled "New York State Electric and Gas Corporation," subject to final site plan review and approval by the Planning Board of the Town of Halfmoon.
E. 
Zoning Map. Local Law No. 5 of 1995 and the Official Zoning Map, as revised, amended and supplemented, is hereby amended by providing that Saratoga Economic Development Corporation Industrial Planned Development District be set forth on a supplementary map which is hereby made a part of this local law as Exhibit B, dated June 21, 1996; the property set forth on such map is the same real property described in the description annexed hereto and marked Exhibit A made by ABD Engineers & Surveyors dated June 21, 1996.
F. 
All of the previous conditions stipulations and legislation contained in Local Law No. 6 of 1996 are heretofore amended and, except as inconsistent herewith, shall remain in full force and effect.
[Added 4-17-2001 by L.L. No. 1-2001]
A. 
Title. This local law shall be known and may be cited as Local Law No. 1 of 2001, a local law amending Local Law No. 1 of 1995 of the Town of Halfmoon, entitled "Local Law Relating to Zoning for the Town of Halfmoon," as previously amended and supplemented by the local laws and an ordinance relating to zoning of the Town of Halfmoon, and Local Law No. 4 of 1997 and further amending Local Law No. 1 of 1986, providing for the creating of a planned development district known as "Saratoga Economic Development Corporation Industrial Planned Development District."
B. 
Establishment of district. Local Law No. 5 of 1995 of the Town of Halfmoon, entitled "Local Law Relating to Zoning for the Town of Halfmoon," and the Zoning Map of the Town of Halfmoon, as set forth and enacted in Local Law No. 5 of 1995 and Local Law No. 1 of 1986, be and the same hereby are amended by modifying the provisions applicable to the planned development district known and described as "Saratoga Economic Development Corporation Industrial Planned Development District," which was created by said Local Law No. 1 of 1986, as thereafter amended.
C. 
Boundaries. The area of said planned development district is shown on a certain subdivision map thereof prepared by Environmental Design Partnership, dated December 11, 1989, entitled "A Portion of Lands of New York State Electric and Gas Corporation," and further set forth in the site plan thereof, dated November 8, 1995, made by Environmental Design Partnership.
D. 
Amendment. The planned development district legislation is changed to permit the use on Lot No. 1 of the Halfmoon Light Industrial Park for retail sales of new cars by New Salem Saab, all as shown on a site plan entitled "Saab of Halfmoon Site Plan" made by ABD Engineers & Surveyors, dated November 2000 and last revised March 14, 2001. It is expressly set forth herein that no retail uses will be permitted on the other lots in the subdivision, including the vacant lots 4, 5, 10 and 12 Enterprise Avenue and Lot 10 Werner Road. No other lot in the subdivision will be permitted to have retail sales or commercial uses. They shall all be light industrial or manufacturing uses as permitted by the Town Board and the Town Planning Board of the Town of Halfmoon.
E. 
Construction regulations.
(1) 
Before construction of the amended Saratoga Economic Development Corporation Planned Development District New Salem Saab site is started or any building permit is issued relative thereto, final site plans and specifications, sufficient for the site plan review and engineering analysis, shall be submitted to and approved by the Planning Board of the Town of Halfmoon and filed with the Town Clerk of the Town of Halfmoon, and said approval is a condition precedent to any construction.
(2) 
All improvements shall be designed and constructed pursuant to plans and specifications approved by a duly licensed architect and/or engineer and in strict compliance with the New York State Uniform Fire Prevention and Building Code. All construction shall be performed subject to the direction and control of a duly licensed architect and/or engineer and, when completed, shall be certified as having been constructed in full compliance with the New York State Uniform Fire Prevention and Building Code. The engineer and/or architect performing the work herein described shall be employed by and at the sole expense of the developer. The Planning Board shall not give approval as referred to in said local law relating to zoning unless or until all approvals required by each and every other government or governmental entity have been obtained. All construction during the performance thereof and upon completion shall be subject to the inspection and approval of the Enforcement Officer and Fire Marshal of the Town of Halfmoon.
(3) 
The exact location, number and size of buildings, parking areas, green space, sidewalks, interim roads and other related matters may be changed, altered or amended during the Town of Halfmoon Planning Board site plan review process in a manner generally consistent with the preliminary plan and this local law.
(4) 
During construction of the Saratoga County Economic Development Planned Development District New Salem Saab site, there shall be constructed, as set forth in general conformity with the preliminary plans, as a part of the plans and specifications to be approved by the Planning Board of the Town of Halfmoon, parking areas and access drives providing sufficient parking and access for all buildings per Town specifications.
F. 
Water distribution facilities; dedication. Upon satisfactory completion in accordance with the requirements of the appropriate state agencies, all water distribution facilities including mains, valves, fittings, hydrants and that portion of the service connection which lie outside the limits of dedicated roadways shall be offered to the Town of Halfmoon with delivery to the Town of Halfmoon of duly executed deeds, title insurance, easements and bills of sale, as appropriate, at no cost to the Town of Halfmoon with title insurance and documents as required by the Town Attorney.
G. 
Water distribution facilities; easements. For those portions of the water distribution system including mains, valves, fittings and hydrants which lie outside the limits of dedicated highways, easements for the maintenance, repair and replacement of the system shall be conveyed to the Town of Halfmoon at no cost to the Town of Halfmoon with appropriate title insurance and documents satisfactory to the Town Attorney together with title insurance and documents as required by the Town Attorney.
H. 
Sewage facilities; dedication. Upon satisfactory completion and connection in accordance with the requirements of the appropriate state agencies, Saratoga County Sewer District, all sewage facilities including mains, manholes and pumping stations shall be offered to Saratoga County Sewer District No. 1 at no cost to said district with delivery to said Saratoga County Sewer District No. 1 of duly executed deeds, easements and bills of sale, as appropriate, together with easements for the maintenance, repair and replacement of all those portions of the system which lie outside the limits of the dedicated streets. Parcels of land for pumping station and access thereto shall be offered in fee to said district with delivery to said district of a duly executed deed or deeds, at no cost to said district, if necessary.
I. 
Stormwater management facilities; dedication. Upon satisfactory completion in accordance with the approved drawings, all stormwater management facilities within the limits of dedicated streets shall be offered to the Town of Halfmoon with duly executed deeds, easements and bills of sale, as appropriate, at no cost to the Town of Halfmoon, which the Town in its sole discretion may accept for dedication at any time it determines together with title insurance and documents as required by the Town.
J. 
Stormwater management facilities; easements. For all those portions of the stormwater management facilities, including pipes, catch basins, manholes and retention areas, which lie outside the limits of dedicated streets, easements for the maintenance, repair and replacement of the system shall be conveyed to the Town of Halfmoon at no cost to the Town of Halfmoon, if requested by the Town of Halfmoon at any time, together with title insurance and documents as required by the Town.
K. 
Stormwater retention/detention tax district. In the event the Town of Halfmoon chooses to create a stormwater retention or detention tax district or stormwater management tax district or the equivalent, it is the intent that the stormwater management areas created as a part of this planned development district will be dedicated to and become a part of that tax district to be serviced and paid for pursuant to the legislation adopted therefor by the development serviced by said areas, for the development area.
L. 
Signs. All signs within the district shall comply with the requirements established by the Planning Board during site plan review and must be approved by said Planning Board.
M. 
Letter of credit.
(1) 
The developer shall file bonds or letters of credit in the amounts established by the Town Planning Board and acceptable as to amount and form to the Town Engineers and Town Attorney to guarantee the following:
(a) 
Return of the site to its original condition after clearing and grading should this be deemed necessary by the Planning Board;
(b) 
The satisfactory completion of the utilities, paving and other infrastructure for the project;
(c) 
The satisfactory completion and maintenance of landscaping on the project site.
(2) 
The bonds or letters of credit shall be filed for the period of time to be determined by the Planning Board.
N. 
Revocation; regulations for construction completed at time of revocation; waiver.
(1) 
This amending local law shall be automatically revoked and void and the previous statutory regulations shall apply under the following circumstances:
(a) 
Commencement of the construction of amended Saratoga County Economic Development Planned Development District New Salem Saab site has not begun within 12 months from the effective date of this local law;
(b) 
Substantial progress is not being made without undue interruption after construction has commenced;
(c) 
Completion of the proposed planned development is not completed within five years from the start of construction.
(2) 
As to the area within which a building or buildings have been constructed pursuant to this local law, there shall be no voiding of this amendment and, as to said are and buildings, this amending local law shall continue in full force and effect, and the areas zoned by this local law shall be the area within which said building or buildings was or were constructed pursuant to this amended local law plus an additional area of 50 feet of open space beyond the outside boundaries of each building constructed.
(3) 
For proper cause shown, the Town Board may, under such terms and conditions as it deems proper, waive either or both of said requirements by resolutions, without first conducting a public hearing thereon.
[Added 12-4-2007 by L.L. No. 8-2007]
A. 
Title. This local law shall be known and may be cited as Local Law No. 8 of 2007, a local law amending Local Law No. 5 of 1995 of the Town of Halfmoon, entitled "Local Law Relating to Zoning for the Town of Halfmoon," as previously amended and supplemented, providing for the amendment to a planned development district known as the "Halfmoon Industrial Park."
B. 
Establishment of district. Local Law No. 5 of 1995 of the Town of Halfmoon, entitled "Local Law Relating to Zoning for the Town of Halfmoon," and the Zoning Map of the Town of Halfmoon, as previously amended, be and the same hereby are amended, to be known and described as "The Halfmoon Industrial Park Planned Development District."
C. 
Boundaries shall not be modified by this amendment.
D. 
Development. In addition to the uses permitted under the original planned development district and the modifications made in 1997 and 2001, the uses permitted on Lot 1 shall be expanded as follows:
(1) 
The property known as Lot 1 in the Halfmoon Industrial Park Planned Development District (the "property") may be utilized as a church with seating for 350 attendees together with ancillary uses. The site shall be modified in conformance with the site plan proposed parking amendments for Grace Fellowship Church last revised on December 4, 2007, detailing 99 ten-foot by twenty-foot parking spaces with the remainder of the 216 spaces being nine-foot by twenty-foot or in compliance with New York States handicap accessibility regulations. Parking attendants and traffic control people will be provided by Grace Fellowship Church and shall ensure that parking does not occur on Route 146 or any Town road.
(2) 
As a condition of the Town Board granting the amendment to the existing planned development district, the Grace Fellowship Church shall provide the Town of Halfmoon the sum of $25,000 to be utilized for the benefit of the Town's municipal park thereby ensuring that the amendments establish a sufficient public benefit to merit the granting of the zoning change.
(3) 
All improvements shall be designed and constructed pursuant to plans and specifications approved by a duly licensed architect and/or engineer and in strict compliance with the New York State Uniform Fire Prevention and Building Code. All construction shall be performed subject to the direction and control of a duly licensed architect and/or engineer and, when completed, shall be certified as having been constructed in full compliance with the New York State Uniform Fire Prevention and Building Code. The engineer and/or architect performing the work herein described shall be employed by and at the sole expense of the developer. The Planning Board shall not give approval as referred to in said local law relating to zoning unless or until all approvals required by each and every other government or governmental entity have been obtained. All construction during the performance thereof and upon completion shall be subject to the inspection and approval of the Enforcement Officer and Fire Marshal of the Town of Halfmoon.
E. 
Signs. All signs within the district shall comply with the requirements established by the Planning Board during site plan review and must be approved by said Planning Board.
F. 
Letter of credit.
(1) 
The developer shall file bonds or letters of credit in the amounts established by the Town Planning Board and acceptable as to amount and form to the Town Engineers and Town Attorney to guarantee the following:
(a) 
Return of the site to its original condition after clearing and grading should this be deemed necessary by the Planning Board;
(b) 
The satisfactory completion of the utilities, paving and other infrastructure for the project;
(c) 
The satisfactory completion and maintenance of landscaping on the project site.
(2) 
The bonds or letters of credit shall be filed for the period of time to be determined by the Planning Board.
G. 
Zoning Map. Local Law No. 5 of 1995 is hereby amended by providing that the Halfmoon Industrial Park Planned Development District Map having been made by ABD Engineers & Surveyors, last revised December 4, 2007, entitled "Site Plan Proposed Parking Amendment - Grace Fellowship Road," together with the additions as detailed in the 1997 and 2001 amendments and the original 1986 approval are included as part of the local law.
H. 
Revocation; regulations for construction completed at time of revocation; waiver.
(1) 
This amending local law shall be automatically revoked and void and the previous statutory regulations shall apply under the following circumstances:
(a) 
Commencement of the construction of the amended Halfmoon Industrial Park Planned Development District has not begun within 12 months from the effective date of this local law;
(b) 
Substantial progress is not being made without undue interruption after construction has commenced;
(c) 
Completion of the proposed planned development is not completed within one year from the start of construction.
(2) 
As to the area within which a building or buildings have been constructed pursuant to this local law, there shall be no voiding of this amendment, and as to said area and buildings, this amending local law shall continue in full force and effect, and the areas zoned by this local law shall be the area within which said building or buildings was or were constructed pursuant to this amended local law plus an additional area of 50 feet of open space beyond the outside boundaries of each building constructed.
(3) 
For proper cause shown, the Town Board may, under such terms and conditions as it deems proper, waive either or both of said requirements by resolutions, without first conducting a public hearing thereon, and extend the time for completion or construction of additional facilities.
[Added 9-6-2017 by L.L. No. 4-2017]
A. 
Title. This local law shall be known may be cited as Local Law No. 4 of 2017, a local amending Local Law No. 5 of 1995 of the Town of Halfmoon entitled "Local Law Relating to Zoning for the Town of Halfmoon," as previously amended and supplemented, and amending Local Law No. 2 of 1973, as amended by Local Law No. 1 of 1986, as amended by Local Law No. 4 of 1997, as amended by Local Law No. 1 of 2001, as amended by Local Law No. 8 of 2007, providing for the creation of a planned development district known as Article XVI, Saratoga Economic Development Corporation Industrial Park Planned Development District.
B. 
Use. Werner Road Lot 10 (2 Werner Road) is permitted to conduct wholesale and retail sales at the proposed Graybar Distribution warehouse facility.
C. 
Development.
(1) 
In addition to the requirements set forth in the original planned development district and the amendments thereto, the screening plan as presented at the Town Board meeting on September 6, 2017, shall be implemented as part of the development of the Werner Road Lot 10 (2 Werner Road) Graybar Distribution warehouse facility.
(2) 
The Saratoga Economic Industrial Park Planned Development District is hereby amended to permit the setback on Werner Road Lot 10 (2 Werner Road) to be reduced from 200 feet to 150 feet for buildings and 50 feet for parking along New York State Route 146 right-of-way; all other setbacks along Werner Road and Old Werner Road shall be 50 feet as detailed in the set of plans entitled "Graybar Electric Warehouse," last revised July 21, 2017.
D. 
In the interest of the general welfare of the public, $10,000 shall be donated to a Town Board designated fund.
E. 
All other provisions of the previously approved Saratoga Economic Development Corporation Industrial Park Planned Development District, together with previously approved amendments, except as modified herein, shall remain in full force and effect.
[Added 1-17-2018 by L.L. No. 1-2018]
A. 
Title. This local law shall be known and may be cited as Local Law No. 1 of 2018, a local law amending Local Law No. 5 of 1995 of the Town of Halfmoon entitled "Local Law Relating to Zoning for the Town of Halfmoon," as previously amended and supplemented, and Local Law No. 3 of 1971, Local Law No. 1 of 1991, Local Law No. 2 of 1997, Local Law No. 1 of 2008, and Local Law No. 4 of 2015, which renamed the Planned Development District to "421 Halfmoon Flex Park Planned Development District." This amendment will also amend the Saratoga Economic Development Corporation Industrial Park Planned Development District created as Local Law No. 2 of 1973 as previously amended and supplemented by Local Law No. 1 of 1986, Local Law No. 4 of 1997, Local Law No. 1 of 2001, Local Law No. 8 of 2007 and Local Law No. 4 of 2017.
B. 
Boundaries. The area of 421 Halfmoon Flex Park Planned Development District shall be expanded by 8.65 acres which is being removed from 4 Enterprise Drive, Tax Map ID 272-4-87.1, via lot line adjustment as further detailed on the aerial site photo entitled "421 Halfmoon Flex Park."[1]
[1]
Editor's Note: Said photo is on file in the Town offices.
C. 
Use. The additional property will increase the allowable square footage of development of the property to increase to accommodate additional business development for the property consistent with the development goals of the previously approved 421 Halfmoon Flex Park, together with any uses permitted in the planned development district.
D. 
All other provisions of the previously approved 421 Halfmoon Flex Park Planned Development planned development district and the Saratoga Economic Development Corporation Industrial Park Planned Development District, together with previously approved amendments, except as modified herein, shall remain in full force and effect.