Table 550-11-1
Mobile/Manufactured Home Area and Design Standards
| |
---|---|
Area/Design Features
|
Mobile/ Manufactured Home, per Dwelling Unit
(feet)
|
Lot width at front setback line, minimum, for interior lot
|
45
|
Lot width at front setback line, minimum, for corner lot
|
60
|
Front setback, minimum
|
15
|
Side setback, minimum
|
10
|
Rear setback, minimum
|
15
|
Table 550-11-2
Multifamily Dwelling Area and Design Standards
| |
---|---|
Area/Design Features
|
Standard
|
Net lot area, minimum
|
2,000 square feet per DU
|
Lot width at front setback line, minimum, for interior lot
|
85 feet
|
Lot width at front setback line, minimum, for corner lot
|
100 feet
|
Front setback, minimum
|
25 feet
|
Side setback, minimum
|
15 feet
|
Table 550-11-3
Single-Family Attached Dwelling Area and Design Standards
| |
---|---|
Area/Design Features
|
Standard
|
Net lot area, minimum
|
2,400 square feet per DU
|
Lot width at front setback line, minimum, for interior lot
|
24 feet
|
Lot width at front setback line, minimum, for corner lot
|
39 feet
|
Side setback, minimum
|
10 feet, except 0 feet at the shared lot line of lawfully attached
dwellings constructed with a shared common party wall and the written
consent of the owner of the abutting lot and building
|
Type of WCF/Application
|
Notice of Incompleteness
|
Final Decision
|
---|---|---|
Nontower WCF
|
30 calendar days from receipt of application for initial notice;
10 calendar days from receipt of supplemental application for subsequent
notices
|
90 total calendar days from receipt of initial application
|
Eligible facilities request
|
30 calendar days from receipt of initial application; 10 calendar
days from receipt of supplemental application for subsequent notices
|
60 total calendar days from receipt of initial application
|
Small WCF (collocated)
|
10 business days from receipt of initial or supplemental application
|
60 total calendar days from receipt of initial application
|
Small WCF (new or replacement wireless support structure)
|
10 business days from receipt of initial or supplemental application
|
90 total calendar days from receipt of initial application
|
Tower-based WCF
|
30 calendar days from receipt of application for initial notice;
10 calendar days from receipt of supplemental application for subsequent
notices
|
150 total calendar days from receipt of initial application
|