[Ord. No. 2018-11 § 4]
The application shall be reviewed by the municipal engineer and, in cases involving surface water drainage facilities pursuant to section
T10B-227, by the storm drainage engineer, who shall report in writing to the Planning Board and to the applicant as to the application's compliance with the requirements for final approval.
[Ord. No. 2018-11 § 4]
The Planning Board shall grant final site plan approval if it
finds that the detailed plans, drawings, specifications, estimates
and the documentation of the application conform to the standards
established by this article for final approval and to the conditions
for preliminary approval. Otherwise it shall deny final approval.