The Superintendent of Buildings shall issue the permit applied for if
the application for permit has been approved by at least a majority of the
Board. However, if within 90 days after the date on which an application has
been filed, or within such longer period as may have been consented to by
the applicant, the Board has not disapproved same, the Superintendent of Buildings
shall issue the permit applied for if the same conforms to the provisions
of all other applicable laws and ordinances.
Every subdivision plat filed with the Board of Trustees shall be referred
to the Board within 30 days after the date on which the same was fully filed,
and the Board shall, within 90 days after said date of filing, report its
recommendations thereon, if any, to the Board of Trustees. In considering
any such plat, the Board may require the proposed developer of the land covered
by the plat to submit a plan of proposed building development, including drawings
showing the designs of the exterior appearance of all proposed buildings and
structures.
Any applicant aggrieved by the action of the Board in disapproving an
application, and of the denial of a building permit, sign permit, etc., because
of such disapproval, may request, within 30 days of the filing of the disapproval
by the Board, that the Board make formal findings of fact. In the event of
such a request, the Board shall make such findings of fact within 15 days
after the request is filed in the office of the Village Clerk, shall thereafter
provide the applicant with an opportunity to answer the findings by a submission
of formal proof and shall reconsider the application on the basis of such
response. If the application is disapproved after such reconsideration, the
applicant may appeal to the Board of Zoning Appeals, in accordance with its
rules, within 30 days after the filing in the office of the Village Clerk
the decision of the Board after reconsideration.
Fees shall be as adopted by resolution of the Board of Trustees from
time to time.