New sanitary sewers and all extensions to sanitary
sewers owned and operated by the Town of Albion shall be designed,
by a professional licensed to practice sewer design in the state,
in accordance with the Recommended Standards of Sewage Works, as adopted
by the Great Lakes Upper Mississippi River Board of State Sanitary
Engineers ("Ten State Standards") and in strict conformance with all
requirements of the NYSDEC. Plans and specifications shall be submitted
to and written approval shall be obtained from the Superintendent,
the County Health Department and the NYSDEC before initiating any
construction. The design shall anticipate and allow for flows from
all possible future extensions or developments within the immediate
drainage area.
Plans, specifications and methods of installation shall conform to the requirements of this article. Components and materials of wastewater facilities not covered in this chapter, such as pumping stations, lift stations or force mains, shall be designed in accordance with §
100-29 and shall be clearly shown and detailed on the plans and specifications submitted for approval. Force main details are covered in §
100-37. When requested, the applicant shall submit to the Superintendent and to the County Health Department all design calculations and other pertinent data to supplement review of the plans and specifications. Results of manufacturer's tests on each lot of pipe delivered to the job site shall also be furnished, upon request.
All sanitary sewers and extensions to sanitary
sewers constructed at the applicant's expense, after final approval
and acceptance by the Superintendent, and concurrence by the Town
of Albion Town Board, shall become the property of the Town of Albion
and shall thereafter be operated and maintained by the Town of Albion.
No sanitary sewer shall be accepted by the Town of Albion until four
copies of as-built drawings have been so filed with the Superintendent
and the Superintendent has approved the submitted drawings. Said sewers,
after their acceptance by the Town of Albion, shall be guaranteed
against defects in materials or workmanship for one year, by the applicant.
The guaranty shall be in such form and contain such provision as deemed
necessary by the Town of Albion Town Board, secured by a surety bond
or such other security as the Town of Albion Town Board may approve.