The purpose of this chapter is to establish procedures for the extension
of the sewer lines for the Hockanum Sewer System and the Crystal Lake Sewer
System. To gain approval for construction, the applicant should also refer
to the Town of Ellington's Sewer Ordinance and Drain Layers' Manual for additional requirements.
Prior to the start of construction, a preconstruction meeting will be
arranged by the Public Works Director. The WPCA Engineer, WPCA Administrator,
Building Inspector, and Town Planner will attend this meeting if the project's
size or complexity justifies participation.
Three copies of the as-built drawings will be submitted to the Ellington
WPCA within 30 days. For the following Town Engineer, Public Works Director
and WPCA:
A. All buildings shall be shown in proper scale and location.
B. All correct invert elevations, top of manhole from elevations
and stationing of manholes shall be shown to scale.
C. Each wye shall be stationed and shown on plans to scale.
D. All building connection laterals shall be shown on the
plan to scale and shall be tied by three dimensions on the plan. Below sill
or below ground depth shall be shown.
E. Chimneys shall be shown on cross section.
F. Size of pipe, type of pipe material, slope or grade,
and length of each manhole-to-manhole pipe run shall be indicated.
G. Areas having additional bedding, temporary sheeting or
permanent sheeting shall be shown. Any concrete encasement shall be shown.
H. A bench mark shall be referred to on each drawing.
I. Drawings shall be indicated as "revised to an as-built,"
dated and initialed by a registered professional engineer.
J. The Town-engineered as-built drawings shall be on reproducible
Mylar with a plan scale of one inch to 40 inches and profile scale of one
inch to 40 inches horizontal, one inch to four inches vertical. The drawings
shall be 24 inches to 30 inches.
Upon satisfactory completion of all the checklist items and receipt
of acceptable Mylar as-builts, with copies for the WPCA, Public Works Director,
WPCA Van, and Building Inspector, the Town Engineer will issue a notice of
final acceptance to the developer to the Ellington WPCA.
Upon acceptance by the WPCA, a final accounting will be made to have
all fees paid. Any money left on the account will be returned to the applicant.
If money is owed, the WPCA will require payment to be made within 30 days.
The reduction of the performance bond will not be approved until all outstanding
fees are paid in full.