Before submitting a proposal for the subdivision
of land, the subdivider shall familiarize himself with these regulations
and with any existing or proposed plans of the Commission or other
Town authorities in the neighborhood of the land to be subdivided
that will have an influence on the street and/or lot layout and the
installation of utilities and storm drainage.
[Amended 6-18-1990]
A proposal for the subdivision of land shall
be submitted to the Commission at any regular meeting of the Commission
and shall include all of the required information, maps, data, application
and fees. The engineering division may receive, for the developer's
convenience and for administration review as to completeness, an application
for subdivision approval prior to the regular Commission meeting,
provided that the date of submission shall be considered to be the
next following regular meeting of the Commission or 35 days after
such submission, whichever is sooner.
[Amended 6-6-2005]
The fee for each application shall be $100 or
$50 per lot, whichever sum is greater.
An applicant with a subdivision involving land
regulated as an inland wetland or watercourse shall file an application
with the Wethersfield Inland Wetlands and Watercourses Commission
within 10 days after filing such application with the Planning and
Zoning Commission. The Planning and Zoning Commission shall give due
consideration to any report filed with it by the Inland Wetlands and
Watercourses Commission prior to rendering a decision on such application.
The Commission may hold a public hearing regarding
any subdivision proposal if, in its judgment, the specific circumstances
require such action. No plan of resubdivision shall be acted upon
by the Commission without a public hearing.
A plan for erosion and sedimentation control
shall contain but not be limited to:
A. A narrative describing:
(2) The schedule for grading and construction activities,
including:
(a)
The start and completion dates.
(b)
The sequence of grading and construction activities.
(c)
The sequence for installation and/or application
of soil erosion and sediment control measures.
(d)
The sequence for final stabilization of the
project site.
(3) The design criteria for proposed soil erosion and
sediment control measures and stormwater management facilities.
(4) The construction details for proposed soil erosion
and sediment control measures and stormwater management facilities.
(5) The installation and/or application procedures for
proposed soil erosion and sediment control measures and stormwater
management facilities.
(6) The operations and maintenance program for proposed
soil erosion and sediment control measures and stormwater management
facilities.
B. A Site Plan Map at a sufficient scale to show:
(1) The location of the proposed development and adjacent
properties.
(2) The existing and proposed topography, including soil
types, wetlands, watercourses and water bodies.
(3) The existing structures on the project site, if any.
(4) The proposed area alterations, including cleared,
excavated, filled or graded areas and proposed structures, utilities,
roads and, if applicable, new property lines.
(5) The location of and design details for all proposed
soil erosion and sediment control measures and stormwater management
facilities.
(6) The sequence of grading and construction activities.
(7) The sequence for installation and/or application of
soil erosion and sediment control measures.
(8) The sequence for final stabilization of the development
site.
C. Any other information deemed necessary and appropriate
by the applicant or requested by the Commission or its designated
agent.
A plan-profile map or maps shall be considered a part of the Subdivision Map and shall contain all of the information required in Article
VI of the "Design and Construction Standards for Public Improvements" of the Engineering Division of the Town of Wethersfield. Elevations shall be based on an indicated bench mark referencing metropolitan district datum. Plans and profiles shall be drawn at a scale of one inch equals 40 feet horizontally and one inch equals four feet vertically. Said map shall be no longer than 36 inches. The original shall be drawn in ink and a reproducible Mylar supplied to the Town of equivalent quality at the subdivider's expense.
A drainage analysis map based on Coast and Geodetic
Survey (CGS) datum showing the tributary watershed at a scale of one
inch equals 200 feet shall be furnished to the Engineering Division.
[Amended 2-5-1991]
The Engineering Division shall hold the endorsed
Mylar transparencies of an approved plan of subdivision until the
subdivider submits the following to the Engineering Division:
A. A warranty deed covering all roads, easements, open
space, etc., to the Town.
B. A certificate of title for the above.
C. A letter stating that the subdivider acknowledges
that although the Town may record the deed and take legal title to
the public utility improvements, the recording and acceptance of the
deed will not constitute formal acceptance of these improvements,
which acceptance can only be accomplished by action of the Town Council;
the subdivider will accept a reconveyance of any conveyance if the
Town so elects at any time up to the time of formal acceptance of
the improvements by the Town Council.
D. A performance bond or bank book (including a signed
withdrawal slip) if building permits are desired.
E. An executed declaration of restrictions and covenants
covering the private open space, if any, in a form acceptable to the
Commission.
F. If the subdivider chooses to proceed under §
143-34A of the subdivision regulations, he must also submit a covenant prohibiting the sale of any lots until property surety is posted for that lot. Surety submitted must be approved by the Town Manager as well as the Commission.
The Planning and Zoning Commission may extend
the time for filing of plans for subdivision for two additional periods
of 90 days, and the plans shall remain valid until the expiration
of such extended time.