[Adopted 8-10-1993 by Ord. No. 7-93 as Ch. 12 of the 1993 Code]
No satellite television dish shall be erected
or placed on any property within the Village until a permit shall
have first been obtained from the Village Building Inspector.
A. Application. Application for a satellite television
dish permit shall be made, in writing, to the Building Inspector.
With such application there shall be submitted a fee as set by resolution
of the Village Board from time to time and a completed set of plans and specifications, including
a plot plan showing the location of the proposed satellite television
dish with respect to adjoining alleys, lot lines and buildings. If
such application shall be approved by the Building Inspector, it shall
then be submitted to the Village Board at its next regular meeting
for final approval.
[Amended 1-12-1999 by Ord. No. 99-01]
B. Location of satellite television dish. Any satellite
television dish approved for placement within the Village may be located
only in the rear yard of a residential lot and at least 10 feet from
any side or rear lot line. It shall also be placed as close to the
residence as is reasonable possible. Placement in the B-1 General
Commercial District and B-2 Highway Commercial District shall also
be approved by the Building Inspector.
[Amended 1-12-1999 by Ord. No. 99-01]
C. Connection of electrical lines. All electrical lines,
cables and conduits running to or from any satellite television dish
shall be buried. If a satellite dish is to be used by two or more
residential property owners, all interconnecting electrical connections,
cables and conduits must also be buried. The location of all such
underground lines, cables and conduits shall be shown on the application
for the permit.
D. Wind pressure. Each satellite television dish shall
be securely anchored to withstand a maximum wind pressure anticipated,
taking into consideration the size, shape and weight of all its components.
E. Temporary placement. A temporary, portable satellite
television dish may be placed in a yard on a trial basis for a period
of not exceeding 10 days if the Village has been informed of the dish
placement.
[Added 9-25-1997 by Ord. No. 6-97]
A. Authority. These regulations are adopted under the
authority granted by § 101.12, Wis. Stats..
B. Purpose. The purpose of this section is to promote
the general health, safety and welfare by enforcing the adopted codes.
C. Adoption of codes. The following Wisconsin Administrative
Codes, their referenced codes and standards and subsequent revisions
are adopted for municipal enforcement by the Building Inspector:
[Amended 1-12-1999 by Ord. No. 99-01; 5-11-2004 by Ord. No.
04-08]
Chapter
|
Subject
|
---|
COMM/ILHR 61 to 65
|
Wisconsin Uniform Building Code
|
COMM/ILHR 75 to 79
|
Existing Buildings Code
|
COMM/ILHR 70
|
Historic Building Code
|
D. Building Inspector. The Building Inspector authorized
by the municipality to enforce the adopted codes shall be properly
certified by the Division of Safety and Buildings.
E. Building permit required. No person shall build or
cause to be built any new public building containing less than 5,000
square feet in total area or alter a public building involving less
than 10,000 square feet in altered area without first submitting plans
and specifications to the Building Inspector and obtaining a building
permit for such building. (Note: All other larger public buildings
are required to have their plans and specifications submitted to the
Wisconsin Division of Safety and Buildings for approval prior to municipal
permit issuance.)
F. Notwithstanding Section COMM/ILHR 50.12(1)(a)1 and
(f)2, a building permit is also required for Chapter ILHR 54 occupancies
and storage garages of less than 25,000 cubic feet.
G. A local building permit shall also be required for
larger commercial buildings, which will be state reviewed but locally
inspected.
H. Commercial and industrial building standards.
[Added 1-12-1999 by Ord. No. 99-01;
amended 1-8-2008 by Ord. No. 08-05]
(1) Commercial and industrial architectural standards.
(a)
Purpose and general application. The following standards are
intended to enhance the appearance of buildings and promote a high
quality of design in order to protect the public health, safety and
welfare. The intent of these standards is to:
[1]
Encourage greater design compatibility with surrounding areas
and establish a precedent for high-quality design in areas with no
established character;
[2]
Achieve greater architectural variation and interest through
standards for the design of roofs, exterior walls and the use of exterior
finish materials;
[3]
Encourage greater architectural cohesiveness and compatibility
within a new development of multiple buildings; and
[4]
Reduce the negative visual impact of features and site improvements
such as mechanical equipment.
(b)
Application. These standards shall apply to new construction
of buildings and structures and improvements to existing structures
when a proposed building expansion exceeds 25% of the existing floor
area measured on a cumulative basis starting from the date of the
adoption of this article. These standards shall not be construed to
necessitate improvements to existing buildings or site conditions
beyond those necessary to integrate the proposed improvement with
existing conditions in a manner consistent with these standards. The
following standards apply to commercial, industrial, institutional
and other commercial buildings located in business-zoned or -designated
areas. It is intended that these standards apply to all sides of the
building.
(c)
Architectural standards.
[1]
Metal siding. Vertical metal siding or corrugated metal siding
like that typically used in the construction of a pole building shall
not be used as an exterior finish material.
(2) Metal or pole-type buildings shall be permitted if surfaces meet
the following requirements:
(a)
The building plans shall bear the seal of an architect or professional
engineer registered in the State of Wisconsin and include:
[1]
Framing plan showing all members, special erection instructions,
and any required permanent bracing.
[2]
Bearing support and connection details.
[3]
Calculations on snow load and wind load to determine compliance
with the Unified Wisconsin Building Code.
[4]
Calculations showing the depth of pole embedment.
[5]
Structural analysis of trussed rafters and prefabricated trusses.
(b)
Construction standards.
[1]
All metal exterior coverings must be factory painted.
[2]
Trim shall be installed over all exposed portions of framing
material used to construct eaves, overhangs, corners, doors, and window
frames so as to completely finish the exterior of the building.
[3]
All roofs shall be colored and incorporate a minimum eighteen-inch
soffit on eave edges, twelve-inch overhang on gable ends, and 9.5-inch
fascia.
[4]
Modern metal paneling may be used for roof and exterior wall
surfaces, provided that, on the wall sides visible from the public
street, there shall be a wainscot at least 42 inches in height which
is composed of brick, decorative masonry, stone, precast panel, architectural
concrete, glass, stucco or wood framed with horizontal lap siding.
[5]
All wood poles, grade boards, girts, and siding in contact with
the earth shall be treated with preservative. All lumber and plywood
required to be treated shall be identified by a quality mark or certificate
of inspection of an approved inspection agency.
I. Building permit fee. Building permit fees shall be
determined by resolution.
J. Penalties. Enforcement of this section shall be by
means of withholding of building permits, imposition of forfeitures
and injunctive action. Forfeitures shall be not less than $25 nor
more than $1,000 for each day of noncompliance.
[Added 4-10-2007 by Ord. No. 07-13]
A. The following structures shall be equipped with a
key lock box at or near the main entrance or such other location as
determined by the Fire Chief or Ambulance Director:
(1) All commercial or industrial buildings identified
by the Fire Chief or Ambulance Director as difficult to access during
emergencies.
(2) All buildings having an automatic alarm system, or
equipped with an automatic fire suppression system, except one- and
two-family owner-occupied dwellings.
(3) Multifamily residential structures, including senior
citizen apartment/condominium complexes, that have restricted access
through locked doors and have a common corridor for access to the
living units.
(4) All other buildings as recommended by the Fire Chief
or Ambulance Director and approved by the Village Board.
B. All new construction of commercial, industrial, or
multifamily structures with restricted access shall have the key lock
box installed and operational prior to the issuance of a certificate
of occupancy.
C. All structures in existence on the effective date
of this section and subject to this section shall have one year from
the effective date of this section to have an entry key lock box installed
and operational in a location as approved by the Fire Chief and Ambulance
Service Director.
D. The owner or operator of a structure required to have
a key lock box shall, at all times, keep a key or keys in the lock
box that will allow for access to the common areas and dwelling units
on the interior of the structure. These keys are to be marked and
identified in a manner approved by the Fire Chief and Ambulance Service
Director.
[Adopted 3-8-2022 by Ord. No. 22-01]
Pursuant to § 101.86(1), Wis. Stats., and Ch. SPS
316, Wis. Adm. Code, the Village of Osceola is exercising jurisdiction
over commercial electrical wiring in its municipality.
The purpose of this article is for the practical safeguarding
of persons and property from hazards arising from electrical wiring
and the use of electricity.
The scope of this article is for the requirements for permits
and inspections per § SPS 316.012, Wis. Adm. Code. These
areas include:
E. Manufactured
home communities.
F. A public
marina, pier, dock, or wharf.
G. A recreation
vehicle park.
The current version of the Wisconsin Electrical Code, Ch. SPS
316, Wis. Adm. Code, and all amendments thereto, is adopted in its
entirety and incorporated by reference.
The municipality shall designate and appoint an electrical inspection
agency to provide commercial electrical inspector(s) who shall administer
and enforce this article and shall be certified by the state as a
commercial electrical inspector, as specified by Wisconsin Statutes.
No electrical wiring within the scope of this article may be
started or continued unless the owner of the premises where the installation
is to occur, or their agent, holds a permit from the designated electrical
inspection agency. An electrical permit shall expire 12 months after
the date of issuance.
The fees associated with commercial electrical fees shall be
set forth by and approved by resolution by the municipality and per
its fee schedule.
All electrical wiring within the scope of this article shall
be subject to inspections.
No permit or inspection is required of any installation, repair,
or maintenance of electrical wiring within an existing industrial
facility or an existing manufacturing facility per the requirements
of § 101.875(2), Wis. Stats.
Enforcement of this article shall be by means of withholding
of electrical permits, imposition of forfeitures and injunctive action.
Forfeitures shall be not less than $25 nor more than $1,000 for each
day of noncompliance. Failure to request a permit prior to the start
of the work will have a penalty of double the original permit fee.