Upon completion of all required subdivision
improvements, the developer may request the Township to accept the
improvements for maintenance and release all performance guarantees.
Upon notice of request for acceptance, the Board Engineer
shall make or cause to be made a final inspection of the improvements.
Those improvements not in acceptable condition shall be reported to
the developer in writing for correction, repair or replacement. Upon
receipt from the developer’s engineer of a report that the necessary
correction, repair or replacements have been accomplished, the Board
Engineer shall reinspect the improvements.
Prior to the Board Engineer making a final report
and recommendations to the Township Committee, the developer will
supply as-built plans, signed and sealed by a licensed New Jersey
professional engineer, showing surface grading, including major lot
gradings, building finished floor grades and curb and gutter grades,
together with horizontal and vertical location of underground facilities.
Manholes, inlets and other such appurtenances, together with sidewalks
and curbs, shall be shown in true location and grade. The as-built
plans shall be submitted on reproducible media.
The developer shall furnish a maintenance bond in
a form acceptable to the Township in the amount of 15% of the total
improvement cost estimate for a period of two years.
After all of the requirements of § § 100-18, 100-19 and 100-20 are complied with, the Township Committee may accept the improvements for maintenance and release the performance bonds.
The creation of each new lot within the Township of
Delanco shall be assessed a one-hundred-dollar fee to offset the cost
of amending the Township Tax Map. The creation of any new streets
within the Township shall be assessed a fee of $0.20 per linear foot.