No stormwater management system shall be constructed unless approval is granted by the Planning Board and the Borough Engineer as indicated in Article VII, § 358-23, of Chapter 358, Subdivision of Land. All stormwater management systems and stormwater conveyance systems must meet NJDEP regulations and must follow NJDEP Best Management Practices (BMPs).
A. 
Prior to the construction of any stormwater management system, a performance guaranty must be posted as outlined in Article III, §§ 324-13 through 324-16 and 324-18 through 324-20, of Chapter 324, Site Plan Review.
B. 
Prior to the acceptance of any stormwater management system by the municipality, a maintenance guaranty must be posted as outlined in Article III, §§ 324-13 through 324-16 and 324-18 through 324-20.