The Plumbing Inspector of the Borough of Ho-Ho-Kus is hereby
authorized to grant applications to install dry house connections
and to make the necessary inspections thereof under the following
circumstances and subject to the following regulations.
Application shall be made to the Plumbing Inspector for a dry house connection permit, as hereinafter provided under Article
IV.
No such dry house connection permit shall be granted by the
Plumbing Inspector unless and until the house sewer lateral has been
installed by the sewer contractor for service to such building, unless
specifically authorized by resolution of the Board of Health of the
Borough of Ho-Ho-Kus. In new housing developments where dry sewer
mains and house sewer laterals have been installed by the developer
as a requirement of other public boards or bodies of the Borough of
Ho-Ho-Kus, dry house connection permits may be granted to the developer
for the installation of such dry house connections, in accordance
with and subject to the regulations herein stated.
The dry house connection to be installed shall be connected
to the house sewer lateral and run to a point near the house drain
to be designated by the Plumbing Inspector where it shall be capped
by an expandable plug at that end.
The pipe used for the installation of a dry house connection
shall be of a type and shall be laid in accordance with the provisions
of this Part 2, the Plumbing Code, and all other ordinances, both of the Borough Council
and of the Board of Health of the Borough of Ho-Ho-Kus.
No portion of the dry house connection shall be backfilled until
the same has been inspected and approved by the Plumbing Inspector
in accordance with the Plumbing Code of the Borough of Ho-Ho-Kus.
Upon official notice requiring connecting with the public sanitary sewer, in accordance with Chapter
56, Part
1, Article
I, of the Code of the Borough of Ho-Ho-Kus, final connection of the dry house connection with the public sanitary sewer shall be made, and the following steps shall be taken:
A. Application shall be made to the Plumbing Inspector for a final house connection permit in accordance with Article
IV hereof.
B. Prior to the final connection of the dry house connection with the
house drain, the expandable plug heretofore installed shall be removed,
and the entire length of the dry house connection shall be completely
flushed and cleaned in the presence of the Plumbing Inspector if,
in his opinion, this is necessary.
C. Reasonable notice of the date and time when such flushing will be
performed shall be given to the Plumbing Inspector, and no flushing
shall be done except in the presence of the Plumbing Inspector.
D. After completion of final connection of the dry house connection
with the house drain, said connection shall be inspected and approved
by the Plumbing Inspector before it is backfilled in accordance with
the Plumbing Code of the Borough of Ho-Ho-Kus.