All deeds covering land to be used for public purposes, easements, and rights-of-way over property to remain in private ownership, and rights of drainage across private property, shall be submitted in a form satisfactory to the Town Attorney.
As-built construction drawings, plan and profile, of all infrastructure improvements, buildings and structure footprints shall be prepared at a scale of one inch to 20 feet, including, but not limited to:
A. 
Underground utilities (sewer lines, storm drains, water lines, electrical, phone, cable, natural gas lines, etc.).
B. 
Drainageways, ditching, impoundments, swales, etc.
C. 
Road construction.
A financial surety shall be in an amount equal to 10% of the cost for completion of all roads (public or private) drainage, and landscaping. The financial surety shall be effective for a period two years after site improvements are completed. If such repairs are needed and are not satisfactorily installed by the developer, then such guarantee shall be used to complete and/or install such improvements.