The improvements included in this article are minimum requirements.
However, the Penndel Borough Council reserves the right in any case
to increase the same if conditions so warrant.
The minimum requirements of improvements shall be those contained
in the Pennsylvania Department of Transportation's Specifications
(Form 408), as last revised.
Adequate provisions for the satisfactory maintenance of all
improvements shall be made by means acceptable to the Borough.
The developer shall install or cause to be installed, at the
developer's expense, streetlights serviced by underground conduit
in accordance with a plan to be prepared by the developer's engineer
and approved by the Philadelphia Electric Company and by the Borough
Council. Provisions shall be made for energizing said lighting after
50% or more of the dwelling units in a given subdivision or land development
or section of a subdivision or land development have been occupied.
The developer shall be responsible for all costs involved in lighting
the streets.
The developer shall construct stormwater drainage facilities,
including retention and detention basins, curbs, catch basins and
inlets, storm sewers, culverts, road ditches, open channels and other
structures required by this chapter.
Where public water is not accessible or required, water shall
be furnished on an individual lot basis. If wells are installed on
each lot, the well shall be of the drilled type, cased and grout-sealed.