[HISTORY: Adopted by the Borough Council of the Borough of Tyrone 12-12-2016 by Ord. No. 1379.[1] Amendments noted where applicable.]
GENERAL REFERENCES
Uniform construction codes — See Ch. 71.
Vehicles and traffic — See Ch. 190.
Zoning — See Ch. 205.
[1]
Editor’s Note: This ordinance also repealed former Ch. 92, Fees, adopted 12-14-2015 by Ord. No. 1367.

§ 92-1 Rates incorporated.

The 2017 rates for various taxes, fines, fees, permits, licenses and/or other charges imposed by the Borough officials and employees shall be as set forth on Exhibit A attached hereto and incorporated herein by reference.[1]
[1]
Editor's Note: See § 92-4 et seq. hereof.

§ 92-2 Repealer.

All ordinances or resolutions or parts thereof inconsistent with the terms of this chapter are hereby repealed effective as of January 1, 2017, coincident with the imposition of the 2017 taxes, fines, fees, etc.

§ 92-3 Effective date.

This chapter shall become effective January 1, 2017.

§ 92-4 Tax rates.

A. 
Real estate: 2.225 mills.
B. 
Real estate tax, late payment penalty: 10%.
C. 
Earned income, resident: 1.25%.
D. 
Earned income, nonresident: 1%.
E. 
Local services tax (LST): $52.
F. 
Realty transfer: 1%.
G. 
Amusement device (including video games): $55 per year.
H. 
Jukebox: $55 per year.

§ 92-5 Building permits.

A. 
Building permits: $20 per $1,000.
(1) 
Every $1,000 after initial $1,000: $5 each.
B. 
Building permit obtained after construction commenced without permit: $120 per $1,000.
[Added 6-12-2017 by Ord. No. 1394]
(1) 
Every $1,000 after initial $1,000: $5 each.
C. 
Annual building permit, commercial only: $75.
D. 
Demolition permit, residential and commercial: 2% of job cost plus $4.
E. 
Demolition permit, garages and sheds (under 1,000 square feet): $25.
F. 
Tax certification/duplicate receipt and bill fee (requests to be made three days in advance): $5.
G. 
Fire Marshal reports: $15.
H. 
Fire insurance certification fee: $20.
I. 
Fire insurance administrative fee: $100.
J. 
Sign permit: $25.
K. 
Street opening permit: $25.
L. 
Certificate of occupancy: $25.
M. 
Sidewalk obstruction permit: $25.

§ 92-6 Establishments.

A. 
Tattoo parlor Borough license/renewal: $500/$250.
B. 
Eating/drinking license, fewer than 50 seats: $75 per year.
C. 
Eating/drinking license, 50 plus seats: $150 per year.
D. 
Transfer of liquor license: $750.

§ 92-7 Zoning.

A. 
Zoning permit: $25.
B. 
Zoning hearing application fee: $250.
C. 
Appeals to Blair Region Uniform Construction Board: $500.
D. 
Sexually oriented business:
(1) 
Application fee: $500.
(2) 
Annual renewal fee: $350.
E. 
Property maintenance appeals to Borough Council: $250.

§ 92-8 Soliciting.

A. 
Daily permit: $25.
B. 
Weekly permit: $75.
C. 
Monthly permit: $150.
D. 
Yearly permit: $300.

§ 92-9 Mobile homes.

A. 
Mobile home park, initial license: $500.
B. 
Mobile home park, annual renewal: $300.
C. 
Mobile home (tax) removal permit: $20.

§ 92-10 Storage of junked vehicles permit fee.

A. 
First six months: $50.
B. 
Second six months: $100.
C. 
Every six months thereafter: $150.

§ 92-11 Lot consolidation/subdivision/land development.

A. 
Residential activity.
(1) 
Lot consolidation plan: $ 100.
(2) 
Residential subdivision or land development: $ 250 (plus Borough review and inspection costs).
B. 
Nonresidential activity.
(1) 
No build commercial, industrial or institutional subdivision: $ 275 (plus Borough review and inspection costs).
(2) 
Commercial, industrial, institutional development up to 50,000 square feet of building construction: $500 (plus Borough review and inspection costs).
(3) 
Commercial, industrial, institutional development over 50,000 square feet of building construction with an additional $25 for each 5,000 square feet of building construction, maximum fee of $1,500: $750 (plus Borough review and inspection costs).
(4) 
Blair County Planning review: fee based on plans and set by BCPC.

§ 92-12 Maps/copies.

A. 
Maps:
(1) 
Borough: $2.
(2) 
Colored: $5.
B. 
Xerox copies: $0.25 per page.
C. 
Returned check fee: $35.

§ 92-13 Parks.

A. 
Park.
(1) 
Electric (all tables): $10 per day.
(2) 
Reservation (Table No. 1): $75 per day.
(3) 
Reservation (Table No. 2): $60 per day.
(4) 
Reservation (Table Nos. 3 through 12): $50 per day.
B. 
Amphitheater rental: $70 per day.
C. 
Recreational rental (organized athletic event): $15 per hour.
D. 
Electric for other Borough facilities: $10 per day.

§ 92-14 Community pool.

A. 
Pool.
(1) 
Family resident: $75 per year.
(2) 
Adult resident (18 and over): $55 per year.
(3) 
Senior (62 and over)/disabled resident: $45 per year.
(4) 
Child resident (6 to 17): $45 per year.
(5) 
Family nonresident: $100 per year.
(6) 
Adult nonresident (18 and over): $80 per year.
(7) 
Senior (62 and over)/disabled nonresident: $70 per year.
(8) 
Child nonresident (6 to 17): $70 per year.
(9) 
Daily admission, adults (18 and over): $5 per day.
(10) 
Daily admission, child (6 to 17): $5 per day.
(11) 
Child five and under: free with paid adult.
(12) 
Pool parties ($50 nonrefundable deposit): $150.
(13) 
Swim lessons: $30.
(14) 
Lifeguard fee for special events: $8.29 per hour.
[Added 8-21-2017 by Ord. No. 1403]

§ 92-15 Parking space rental.

A. 
Parking meter bags: $5 per day.
B. 
Parking spaces, municipal lots: $20 per month.
C. 
Replacement of lost or stolen parking permits: $10.
[Added 8-21-2017 by Ord. No. 1403]

§ 92-16 Police.

A. 
Police accident and incident reports: $15.
B. 
Police offense reports: $15.
C. 
Private handicapped parking space, installation fee: $75.
D. 
Annual renewal fee for private handicapped parking space: $25.
E. 
Relocation of handicapped parking sign: $30.
F. 
Annual towing license fee: $100.

§ 92-17 Parking fines (per violation).

A. 
Meter violation: $5.
B. 
Backing into meter stall: $5.
C. 
Bus zone: $15.
D. 
No parking zone: $15.
E. 
Double parking: $15.
F. 
Sidewalk: $15.
G. 
More than six inches from curb: $15.
H. 
Less than 25 feet from intersection: $15.
I. 
Parked overtime, two-hour zone: $15.
J. 
Against traffic: $15.
K. 
Handicap only: $50.
L. 
Blocking driveway or garage: $15.
M. 
Fire hydrant: $15.
N. 
Repairs of vehicle on roadway: $15.

§ 92-18 Building inspection fee schedule.

A. 
Residential fees (does not include plumbing, electrical, mechanical, fire or energy inspection fees).
(1) 
Industrialized housing (mobile home, modular and manufactured): $156.
(2) 
Single-family dwelling:
(a) 
Not over 3,500 square feet* or over three bedrooms:** $246.
(b) 
Over 3,500 square feet*: $246 plus $0.14 each square foot over 3,500.
*
"Square footage" is defined as gross floor area of all floors within the perimeter of the outside walls, including basements, cellars, garages, roofed patios, breezeways, covered walkways, and attics with floor-to-ceiling of six feet six inches or more.
**
Each additional bedroom, per dwelling unit: $48.
(3) 
Townhouse: $180.
(4) 
Decks, porches, carports: $90.
(5) 
Attached garages, additions, and nonexempt detached accessory structures, alterations, renovations to 500 square feet: $144.
(a) 
Over 500 square feet: $144 plus $0.14 each square foot over 500.
B. 
Commercial fees (includes multifamily) (does not include plumbing, electrical, mechanical, fire or energy inspection fees).
(1) 
New construction (per square foot*): $0.15.
(2) 
Alterations and renovations (per square foot*): $0.09.
(3) 
Accessibility (flat fee): $180.
*
"Square footage" is defined as gross floor area of all floors within the perimeter of the outside walls, including basements, cellars, garages, roofed patios, breezeways, covered walkways, and attics with floor-to-ceiling of six feet six inches or more.
C. 
Miscellaneous fees.
(1) 
Swimming pool/spa (public or commercial): $288.
(2) 
Swimming pool/spa (single family):
(a) 
Aboveground: $78.
(b) 
In-ground: $144.
(3) 
Reinspection fee, each: $78.
(4) 
Locked or not ready for inspection: $78.
D. 
Conditions not provided for in this schedule, apply for fee.
E. 
Minimum fee: $78.

§ 92-19 Electrical inspection fee schedule.

A. 
Fee schedule (other than residential). All switches, lighting and receptacles to be counted as outlets.
B. 
Rough wiring inspection.
(1) 
One to 25 outlets: $36.
(2) 
For each additional 10 outlets or fraction thereof: $7.20.
C. 
Finish inspection.
(1) 
One to 25 outlets: $36.
(2) 
For each additional 10 outlets or fraction thereof: $7.20.
D. 
Equipment, appliances.
(1) 
Outlet for single unit of 15 kw or less: $32.40.
(2) 
Each additional outlet of 15 kw or less: $10.80.
E. 
Motors, generators, transformers, central heating, duct heaters, air conditioning, electric furnaces and welders.
Fractional hp, kw or kva to 1 hp, kw or kva, each
$20.40
1 hp, kw or kva to 3 hp, kw or kva, each
$22.80
4 hp, kw or kva to 7 hp, kw or kva, each
$32.40
7 1/2 hp, kw or kva to 29 hp, kw or kva, each
$37.20
30 hp, kw or kva to 49 hp, kw or kva, each
$56.40
50 hp, kw or kva to 74 hp, kw or kva, each
$69.60
75 hp, kw or kva to 199 hp, kw or kva, each
$135.60
200 hp, kw or kva to 500 hp, kw or kva, each
$265.20
Over 500 hp, kw or kva, each
$333.60
Over 600 volts: Add $103 per category
F. 
Feeders or subpanels.
(1) 
Not over 200 amp: $33.60.
(2) 
Over 200 amp to 400 amp: $48.
(3) 
Over 400 amp to 600 amp: $60.
(4) 
Over 600 amp to 1,600 amp: $129.60.
(5) 
Over 1,600 amp: $177.60.
(6) 
Over 600 volts: Add $103 per category.
G. 
Modular and mobile homes.
(1) 
Modular homes, service and outlets: $105.60.
(2) 
Mobile homes, service including one feeder or one receptacle: $90.
(3) 
Feeder or power cord only (single visit only): $69.60.
(4) 
Additional trip: $33.60.
H. 
Service-meter equipment up to 600 volts.
(1) 
Not over 200 amp: $72.
(2) 
Over 200 amp to 400 amp: $96.
(3) 
Over 400 amp to 600 amp: $120.
(4) 
Over 600 amp to 1,200 amp: $270.
(5) 
Over 1,200 amp to 1,600 amp: $276.
(6) 
Over 1,600 amp to 2,000 amp: $342.
(7) 
Over 2,000 amp to 3,000 amp: $402.
(8) 
Over 3,000 amp: $510.
(9) 
Ground fault protected services: Add $96.
(10) 
Over 600 volts: Add $132 per category.
(11) 
Services exceeding one meter: $15.60 for each additional meter.
(12) 
Service reconnect: Add $18.
I. 
Primary transformers, vaults, enclosures, substations.
(1) 
Not over 200 kva: $243.60.
(2) 
Over 200 kva to 500 kva: $303.60.
(3) 
Over 500 kva to 1,000 kva: $363.60.
(4) 
Over 1,000 kva: $423.60.
J. 
Signaling systems. Burglar alarms, fire alarms, fire-suppression alarms, smoke detectors, telemetering. (Telephones or CATV outlets are each separate systems).
(1) 
For the system and first 15 devices: $72.
(2) 
Each additional 10 devices or fraction thereof: $7.20.
K. 
Signs (incandescent, fluorescent and neon).
(1) 
First sign (per occupancy): $72.
(2) 
Each additional sign (per occupancy): $10.80.
L. 
Outline lighting.
(1) 
First transformer: $72.
(2) 
Each additional transformer: $10.80.
M. 
Swimming pools.
(1) 
Bonding (each trip): $78.
(2) 
Equipment/wiring (residential only): $90.
(3) 
Commercial by fee schedule.
N. 
Residential fees.
(1) 
Flat rate schedule. One application for each new or existing building.
(a) 
Single-family dwelling, not over 200 amp service: $138.
(b) 
Two-family dwelling units, not over 200 amp service: $186.
(c) 
Over two-family dwelling, first two units, each: $90. (Note: Add service equipment.)
(d) 
Each additional unit: $60.
(e) 
Townhouses, each: $90.
(f) 
Alterations and additions (service and 25 outlets or fewer): $105.60.
(2) 
Single-family dwellings with over 200 amp service: Apply flat rate schedule plus equipment, appliances, and motor schedules.
(3) 
Dwelling with a spa, hot tub, hydromassage tub, sauna, etc.: Apply flat rate schedule plus $33.60 for each item.
(4) 
Special service and/or conditions not provided for in this schedule: Apply for fee.
(5) 
Minimum charge $72.

§ 92-20 Plumbing inspection fee schedule.

A. 
Residential fees.
(1) 
Industrialized housing (mobile home, modular and manufactured), one sewer and water connection: $78.
(2) 
Additions and alterations, one sewer and water connection: $78.
(3) 
All other: per dwelling or unit.
(a) 
Not over three full (or partial) baths: $120.
(b) 
Fourth and fifth full (or partial) baths, each: $30.
B. 
Commercial fees.
(1) 
Piping under slab (waste and supply).
(a) 
Not over five fixtures: $60.
(b) 
Each additional fixture: $6.
(2) 
Piping rough-in (waste and supply).
(a) 
Not over five fixtures: $60.
(b) 
Each additional fixture: $6.
(3) 
Piping final inspection.
(a) 
Not over five fixtures: $60.
(b) 
Each additional fixture: $6.
C. 
Miscellaneous fees.
(1) 
Sewer lateral (from house to curb): $78.
(2) 
Water lateral (from house to curb): $78.
(3) 
Sewer and water lateral at same time: $120.
(4) 
Master backflow prevention device: $78.
(5) 
Reinspection fee, each: $78.
D. 
Special service and/or conditions not provided for in this schedule: Apply for fee.
E. 
Minimum charge: $78.
F. 
Fixture definitions for the above fee schedule. As used in this section, the following terms shall have the meanings indicated:
FIXTURE
Each water closet, urinal, wash basin, bathtub, house trap, floor drain or downspout area drain, laundry tray, hot water heater or opening provided for any of the aforementioned or any plumbing or drainage appliance trap connected, either directly or indirectly, to the plumbing or drainage system, whether water-supplied or not, installed in the building or on the lot within the property lines.

§ 92-21 Mechanical inspection fee schedule.

A. 
Commercial.
(1) 
Total value of mechanical bid times 0.0075.
(2) 
Individual systems (not to be combined with above multiplier):
(a) 
Water heaters (100 gallons or more): $84.
(b) 
Air-handling units/chillers: $84.
(c) 
Circulating pumps, condensate pumps, exhaust fans, return air fans, water heaters less than 100 gallons, heat exchangers and incinerators: $24.
(d) 
Underground snow melt systems: $84.
(e) 
Kitchen exhaust equipment (per hood unit): $84.
(f) 
Gas piping system: $72.
(g) 
Fuel oil piping system: $72.
(h) 
Chimneys and vents: $72.
(i) 
Solar heating and cooling system: $84.
(j) 
Flammable and combustible liquid storage, dust collectors: Apply for fee.
B. 
Residential.
(1) 
Single-family dwelling:
(a) 
Up to 3,500 square feet: $96.
(b) 
Over 3,500 square feet: $132.
C. 
Minimum charge $72.

§ 92-22 Fire protection inspection fee schedule.

(Note: Devices shall include all annunciating and initiating devices, panels, etc.)
A. 
Fire alarm systems (panel and 10 devices): $72.
(1) 
Each additional 20 devices or fraction thereof: $12.
B. 
Sprinkler system up to 50 sprinkler heads: $132.
(1) 
Each additional 50 heads or fraction thereof: $90.
C. 
Commercial cooking hoods: $84.
D. 
Standpipe system: $108.
E. 
Dry chemical extinguishing system: $108.
F. 
Condition not provided: Please apply for fee.
G. 
Minimum charge: $72.

§ 92-23 Plan review fee schedule.

A. 
Commercial fees (includes multifamily):
(1) 
To $1,000,000: 0.0015 times construction valuation.
(2) 
$1,000,000 to $5,000,000: $1,560 plus 0.0005 times construction valuation.
(3) 
Over $5,000,000: $3,960 plus 0.00041 times construction valuation.
(4) 
Individual disciplines:
(a) 
Twenty-five percent of building plan review.
(5) 
Accessibility: $150.
(6) 
Minimum fee: $156.
B. 
Residential fees:
(1) 
Single-family dwelling not over 3,500 square feet*: $93.60.
(2) 
Single-family dwelling and additions 3,500 square feet* to 5,000 square feet*: $153.60.
(3) 
Single-family dwelling and additions over 5,000 square feet*: $300.
*
"Square footage" is defined as gross floor area of all floors within the perimeter of the outside walls, including basements, cellars, garages, roofed patios, breezeways, covered walkways, etc.
(4) 
Decks, porches, carports: $30.
(5) 
Attached garages, additions, and nonexempt detached accessory structures, alterations, renovations to 500 square feet: $72.
(a) 
Over 500 square feet: $93.60.
(6) 
Minimum fee: $30.

§ 92-24 Energy conservation inspection fee schedule.

A. 
Residential fee.
(1) 
Flat fee: $72.
B. 
Nonresidential fee.
(1) 
New construction (per square foot): $0.03.
C. 
Minimum charge: $72.

§ 92-25 Waste management and recycling fee schedule.

A. 
Dumpster/roll-off container permit fee (to be fully refunded if dumpster/roll-off container is removed before expiration of permit): $100.