The purpose of this zone is to protect stream valley habitat
and stream water quality. In particular, the purposes of this zone
are to:
A. Preserve floodplains in a natural state;
B. Preserve wetlands associated with floodplains;
C. Preserve significant habitat areas associated with stream valleys
or in other locations;
D. Prevent soil erosion and sedimentation by protecting steep slopes
associated with stream valleys;
E. Protect persons and property from environmental hazards such as unstable
or highly erodible soils and flooding;
F. Filter nutrients, toxics and sediment from stormwater;
H. Provide recreational opportunities; and
I. Minimize public investment in floodplain stormwater management.
[Amended 8-22-1994 by Ord. No. 94-80]
These regulations shall apply to all proposed development, including projects for which subdivision, site plan, building and grading permits or approvals are necessary; timber harvesting; and agricultural activities, except as provided in §§
297-480,
297-481 and
297-482 of this chapter.
The Resource Protection Zone (RPZ) shall apply to those County
streams or those portions of County streams outside of the Critical
Area Zone, including but not limited to: Zekiah Swamp, Gilbert Run,
Nanjemoy Creek, Swanson Creek, Indian Creek, Port Tobacco River, Mattawoman
Creek, Chicamuxen Creek, Popes Creek, Indian Creek, Wards Run, Kerrick
Swamp, Mill Run, Beaverdam Creek, Hancock Run, Old Woman's Creek,
Piney Branch and tributaries thereof or of the Potomac River.
[Amended 2-10-1998 by Ord. No. 98-59]
The Resource Protection Zone shall encompass stream valleys, steep slopes, associated wetlands and floodplains, if present; and a buffer, as called for in §§
297-171 and
297-172. Except as permitted in this chapter, the land within this zone is to remain in an undisturbed natural stage, and the outer edge of this zone shall constitute the limit of clearing and grading.
[Amended 8-22-1994 by Ord. No. 94-80]
A. The minimum buffer standards shall be as follows:
(1)
One hundred feet for streams of stream order three or higher.
(2)
Fifty feet for intermittent streams and streams of stream order
one and two.
B. The minimum buffer shall extend outward from both sides of the stream
channel. The buffer shall be measured horizontally from the stream
channel without regard for the lay of the land.
[Amended 8-22-1994 by Ord. No. 94-80]
A. The buffer shall be expanded beyond the minimum buffer to account
for nontidal wetlands adjacent to the stream as follows:
(1)
Within the development district, to include all lands 25 feet
from the outer edge of nontidal wetlands adjacent to the stream channel.
(2)
Outside the development district, to include all lands measured
from the edge of nontidal wetlands adjacent to the stream channel
measuring 50 feet for intermittent streams or perennial streams of
stream order one and two or 100 feet for perennial streams of stream
order three and four.
B. Where the one-hundred-year floodplain extends beyond the buffer adjusted
for nontidal wetlands, if applicable, the extent of the one-hundred-year
floodplain shall become the extent of the buffer.
C. The buffer shall be further increased to account for steep slopes
that are contiguous with or within 25 feet of the buffer.
(1)
The buffer width shall be increased by 50 feet for intermittent
streams or perennial streams of stream order one and two or 100 feet
for perennial streams of stream order three and four or shall extend
to the top of the slope, whichever is less, where average slopes greater
than 15% adjoin the minimum buffer or are within 25 feet of the minimum
buffer.
(2)
Percentage of average slopes shall be determined by plotting
a transect from the outer edge of the minimum buffer to the top of
the adjoining slope, defined as the point at the top of slope where
the slope falls below 15%, and calculating an average slope from the
slope percentages crossed by the transect. The number of transects
will vary depending on the uniformity of slopes adjoining a particular
reach of a stream. Transects may be spaced up to 100 feet apart, regardless
of slope uniformity. However, transect spacing exceeding 100 feet
shall be based on slope uniformity.
The following uses shall be prohibited in the RPZ:
A. Mining or excavation, except for existing operations.
B. Dredging, except as may be permitted under state law.
C. Deposit or landfilling of fill, refuse and solid or liquid waste,
except manure applied as a crop fertilizer, and acceptable fill permitted
by the United States Army Corps of Engineers for streambank erosion
control.
D. Alteration of the stream bed and bank of a waterway, except for best
management practices to reduce stream erosion and construction and
maintenance of stream crossings for permitted uses.
E. Clearing of vegetation and grading, except as may be permitted under
this chapter.
The following land uses shall be permitted, provided that the
conditions herein are met:
A. Agriculture. Agricultural uses shall be permitted, provided that
a soil conservation and water quality plan is approved by the Charles
County Soil Conservation District. Existing agricultural uses must
obtain approval within three years from the adoption of this chapter.
The soil conservation and water quality plan shall include twenty-five-foot
vegetative filter strips adjoining streams.
B. Timber harvesting. Landowner timber harvesting for personal use shall
be permitted. Commercial timber harvesting shall be permitted, provided
that the timber harvesting is conducted in conformance with the Natural
Resources Article, Title 5, Forests and Parks, Subtitle 16, Forest
Conservation, of the Annotated Code of Maryland, or a local program
pursuant to said subtitle.
[Amended 8-22-1994 by Ord. No. 94-80]
C. Utility transmission lines, railroads, roads, stormwater management
facilities, storm drainage improvements, recreational nonmotorized
trails, public environmental education facilities, facilities for
recreational access to a stream and associated clearing shall be permitted,
provided that:
(1)
Project location in the RPZ is essential for access or continuity
and no reasonable alternatives exist.
(2)
Crossings of the RPZ are as close to 90° as reasonably possible.
(3)
The project complies with the requirements of the United States
Army Corps of Engineers, Maryland Department of Natural Resources
and the Charles County Floodplain Management Ordinance.
(4)
The project is designed to minimize disturbance, clearing and
grading.
(5)
Approved sedimentation and erosion control, best management
practices and revegetation plans in accordance with Title 5, Subtitle
16, Forest Conservation, of the Annotated Code of Maryland, or local
program pursuant to Title 5, Subtitle 16, Forest Conservation, of
the Annotated Code of Maryland, as applicable, are implemented for
the project.
[Amended 8-22-1994 by Ord. No. 94-80]
(6)
The habitats of federal- or state-listed threatened and endangered
species or other critical habitats are fully protected.
D. New single-family dwellings and accessory structures proposed on
lots of record as of October 1, 1992. Up to a total of 5,000 square
feet may be disturbed in the Buffer, provided that any disturbance
to the floodplain must comply with County Floodplain Regulations.
[Added 8-22-1994 by Ord. No. 94-80]
Land within the RPZ may be used to meet open space requirements.
The application of this zone to the County Zoning Maps shall
be construed as general in nature and may be adjusted by the Zoning
Officer upon the presentation of engineering data which delineates
more precisely the boundaries of this zone.
The outer edge of the RPZ buffer shall be field-staked and clearly
delineated as the limit of clearing and grading prior to the commencement
of clearing and grading activities within 50 feet of the RPZ, permitted
clearing and grading in the RPZ excepted. The limits of permitted
clearing and grading within the RPZ shall likewise be field-staked
and clearly delineated.
The enforcement provisions of the Charles County Grading and
Sediment Control Ordinance shall also apply to this zone.
A performance bond or other surety in a form and amount established
as acceptable to the County shall be executed by the applicant to
cover possible damage to RPZ lands during construction. The bond or
surety shall remain in full force until the work encompassed by the
applicable grading permit has been completed and approved by the County.
Accidental or incidental construction damage to the RPZ may result
in a full or partial forfeiture of the performance bond or surety,
depending on the severity of the violation and the costs of restoring
damaged RPZ land. It shall be the applicant's responsibility to restore
damaged RPZ land in accordance with County revegetation requirements.
The variance provisions of Article
XXV shall apply to this article.