The operation and maintenance agreement shall be subject to
the review and approval of the Township Solicitor and Board of Supervisors.
Maintenance of SWM facilities during development shall be the
responsibility of the developer and shall include, but not be limited
to:
A. Removal of silt from all debris basins, traps or other structures
or measures when 60% of capacity is filled with silt.
B. Periodic maintenance of temporary control facilities such as replacement
of straw bale dikes, straw filters or similar measures.
C. Establishment or reestablishment of vegetation by seeding and mulching
or sodding of scoured areas or areas where vegetation has not been
established.
D. Installation of necessary controls to correct unforeseen problems
caused by storm events within design frequencies.
E. The contractor or developer shall be responsible for removal of all
temporary measures and installation of permanent measures upon completion
of the development.