"Following initial soil disturbance or redisturbance, permanent
or temporary stabilization must be completed within:
| ||
a.
|
Three calendar days as to the surface of all perimeter dikes,
swales, ditches, perimeter slopes, and all slopes steeper than 3:1;
and
| |
b.
|
Seven calendar days as to all other disturbed or graded areas
on the project site not under active grading."
|