[Amended 10-17-2022]
Prior to starting any construction activities, a registered
land surveyor shall set grade stakes along the roadway right-of-way,
center line, sidelines, and sidewalks at one-hundred-foot intervals.
All trees to be preserved shall be flagged. The site shall be walked
with a designated agent of the Department of Public Works. All construction
and work sequencing shall be conducted in accordance with the following
sections.
A.
The entire area to be paved of each street, way, sidewalk, and/or
bike path, if required, shall be cleared of all stumps, brush, roots,
boulders and like material, and all trees not intended for preservation.
B.
Beneath all areas proposed to be paved, all loam or soft, spongy
or otherwise undesirable material such as peat, roots, mulch or quicksand
shall be removed to whatever depth it occurs.
C.
This work shall be inspected and approved as hereinafter described
before continuance of the project.
A.
The entire length and width of the vehicular way shall be brought
to a firm subgrade at least nine inches below the finished grade shown
on the profile.
B.
The entire length and width of the sidewalk, if required, shall be
brought to a firm subgrade at least nine inches below the finished
grade desired.
C.
All fill or ordinary borrow for the subgrade shall consist of any
firm bearing material, except loam or organic matter, meeting the
approval of the DPW Superintendent and of the consulting engineer,
if any.
D.
This work shall be inspected and approved as hereinafter described
before continuance of the project.
A.
If required, permanent stone or concrete curbing matching that of
existing adjacent streets shall be installed at a nominal height of
six inches above gutter with bottom at least 12 inches below the surface
of the pavement.
B.
All subgrades of vehicular ways shall be covered with at least 12
inches of well-compacted gravel to a point three inches below the
finish grade shown on the profile, with a traverse pitch from center
line to pavement edge of 1/4 inch per foot. All vehicular ways shall
then be finished with bituminous concrete meeting MassDOT current
standards. Concrete shall be applied in a two-inch binder core and
subsequent one-inch top coat, both well rolled and compacted to maintain
the pitch above noted.
C.
If required, all subgrades of sidewalks shall be covered with at
least six inches of well-compacted gravel to the desired finish grade
and pitched 1/4 inch per foot toward the vehicular way. The surface
shall then be treated as required for vehicular ways. Where driveways
cross such paved areas of sidewalks, the elevation of such driveway
shall conform to the elevation of the paved sidewalk area.
D.
The subgrade under the roadway gravel base shall be a free-draining
material for a minimum depth of two feet and shall conform to the
requirements of Section M1.02.0 Type A of the Standard Specifications.
Existing soils that do not conform to these requirements shall be
removed and replaced with gravel base material conforming to the above.
[Amended 10-17-2022]
E.
The gravel base of the roadway and sidewalks shall consist of unfrozen,
hard, durable stone and coarse sand, free from loam and clay, uniformly
graded, containing no stone having a diameter of more than two inches
and conforming to the requirements of M1.03.0 Type C of the Standard
Specifications.
[Amended 10-17-2022]
F.
Gradation tests (sieve analysis) and Proctor tests (optimum density)
shall be performed by an approved independent testing laboratory on
the material to be utilized as gravel base and shall be submitted
to the Department of Public Works for review. This analysis shall
be done at the expense of the subdivider in advance of applying or
grading the material. The Board may, at any time during the roadway
construction, require additional testing.
G.
Before the gravel is spread, the roadbed shall be sloped to a true
surface, conforming to the proposed cross section of the road, and
no gravel is to be spread until this subgrade is approved by the Board.
H.
Gravel for base shall be spread in two layers of equal thickness,
each thoroughly rolled true to lines and grades so as to yield a total
minimum depth of 12 inches after thorough compaction. Any depression
or soft spots that appear during or after rolling shall be filled
with crushed bank gravel and be rerolled until the surface is true
and even. Gradation and compaction tests shall be performed and submitted
to the Board for review. Testing results shall be satisfactory to
the Board prior to placement of the base course of pavement. Gradation
and compaction tests shall be provided for each 2,000 square feet
of roadway area or fraction there of.
[Amended 10-17-2022]
I.
All sidewalk areas shall be provided with a gravel base foundation
consistent with that required for roadways. Gradation and compaction
tests shall be performed and submitted to the Board for review at
the rate of one test per 1,000 square feet of sidewalk, of finish
gravel base.
[Amended 10-17-2022]
J.
All frames, grates, manhole covers and water gates shall be adjusted
to the proper finished grade by setting the same in a 2,500 pounds
per square inch concrete bed. Any depressions or irregularities in
the binder pavement are to be repaired and shall be inspected by the
Board's agent at least one week before final paving.
K.
The binder course pavement must be swept clean of all loose material.
A tack coat of emulsified asphalt shall be applied with a pressure
distributor at a rate of 0.10 gallon per square yard, immediately
preceding the top course paving. An environmentally safe synthetic
mat specifically designed for the purpose may be substituted for the
tack coat of emulsified asphalt.
L.
All roadways shall be prepared in such a manner that all manholes,
catch basins, valve gates or other structures in a roadway are installed
with bituminous paving around the perimeter of each such structure
such that a smooth transition is maintained between the top of each
structure and the road surface.
M.
If requested by the Board, compaction and plane of finished surface
tests shall be performed on the top course paving once in place. All
requested testing shall be performed by an independent testing laboratory
at the expense of the subdivider. The Board my request remedial repairs
or replacement of any portion of the pavement system if it fails to
meet these and/or the Standard Specifications.
N.
The developer shall make and maintain all subdivision roadways so
that any and all occupied dwelling units within the subdivision are
easily accessible to all municipal and emergency services. In addition
to the above requirement, the developer must comply with the following
conditions to the satisfaction of the Board prior to the first day
of December (the beginning of the wintering over period).
O.
All grass strips and other areas within the street right-of-way shall
be covered with at least six inches of loam (depth after compaction)
and planted with high-quality grass seed. Seeding of lawn grass shall
be done after building construction has been completed on the adjacent
lots.
P.
This work shall be inspected and approved as hereinafter described
before continuance of the project.
A.
Standard
Type VA-4 granite curbing with six-inch reveal, sloped granite face
curbing, or bituminous concrete curbing, if determined by the Planning
Board, shall be installed along both gutter lines of all ways for
their entire lengths, except that granite curbing shall be installed
along said gutter lines under the following conditions:
(1)
All finished street grades over 5%;
(2)
All headers for catch basins (to be set back four inches from
the edge of pavement);
(3)
All street intersections on the curve and extending six feet
tangential to the point of curvature and point of tangency along the
sideline line of roadway at the intersection; and
(4)
Other specific locations as determined by the Board.
B.
Granite curbing shall be set in concrete and on at least six inches
of compacted bank gravel conforming to M1.03 Type C of the Standard
Specifications in accordance with the cross section. Straight-ended
granite curb inlet stones shall be used in all instances.
[Amended 10-17-2022]
[Amended 10-17-2022]
Drainage facilities shall be provided as indicated on the definitive
plan and in conformity with the requirements of Sections 200, 220,
230, 258, and 260 of the MassDOT Standard Specifications.
A.
Pipe culvert and pipe drains shall be in conformity with the requirements
of Section 230 of the MassDOT Standard Specifications for installation
of pipes.
B.
No backfilling of pipes shall be done unless and until the installation
has been inspected by the Town Engineer. All drainage trenches shall
be filled with clean gravel borrow in accordance with Section 150
of the MassDOT Standard Specifications.
C.
Where subdrains are required, they shall be constructed in conformance
with Section 260 of the MassDOT Standard Specifications. Such subdrains
may be required by the Board following clearing and grubbing operations.
D.
No drainage pipes from roof drains, driveway drains or other on-lot
sources shall be connected to the street drainage system without the
express written approval of the Planning Board.
E.
Catch basins shall be constructed with cast iron frames and grates.
Frames must be set in a full bed of cement mortar. Bricks shall be
used between the frame and top course for grade adjustments. They
shall be laid in a radial fashion with full bearing on the ring row.
A maximum of two brick courses will be allowed. Frames shall be at
least 265 pounds and shall be of North American manufacture. Grates
shall be 24 inches square with square openings. Grates shall be no
less than 210 pounds, in accordance with the Standard Specifications,
and shall be of North American manufacture.
F.
Granite curb inlets shall be provided at all catch basins.
G.
Manholes shall be constructed with cast iron frames and covers. Frames
must be set in a full bed of cement mortar. Bricks shall be used between
the frame and top course for grade adjustments. They shall be laid
in a radial fashion with full bearing on the ring row. A maximum of
two brick courses will be allowed. Frames shall be at least 265 pounds
and shall be of North American manufacture. Covers shall be no less
than 210 pounds, in accordance with the Standard Specifications, and
shall be of North American manufacture. Drain manhole covers shall
be 24 inches in diameter and shall have the word "DRAIN" cast into
them in letters at least three inches in height. Sewer manhole covers
shall be 30 inches in diameter and shall have the word "SEWER" cast
into them in letters at least three inches in height.
H.
Manholes shall have rung steps 15 inches on center built into the
vertical side.
I.
After the completion of roadway work, the manhole casting shall be
set flush with the designed finish grade of pavement. Catch basin
grates shall be set one inch below the finished gutter. Manhole castings
and catch basin grates shall not be raised until 30 days prior to
final paving. If paving does not occur within said 30 days, they shall
be lowered immediately. Ramping is prohibited.
A.
Concrete or granite monuments shall conform to the standard specifications
acceptable to the Massachusetts Land Court and shall be set according
to such specifications. No permanent monuments shall be installed
until all construction which would destroy the monuments is completed.
[Amended 10-17-2022]
B.
Monuments shall be installed at all street intersections, at all
points of change in direction or curvature of streets and at other
points where, in the opinion of the Planning Board, permanent monuments
are necessary.
C.
Permanent boundary markers shall be placed on lot boundaries. The
minimal number is four: either at the four corners or two at the roadway
and two at a setback distance acceptable to the Planning Board.
[Amended 10-17-2022]
The applicant shall install standard street signs displaying
the name of each street in the subdivision to be located so that the
public can identify each street. Signs shall be equivalent in size,
design and quality to those used by the Town for its streets and may
be purchased from the Town DPW.
A.
The applicant shall proceed with this work as previously specified
and when completed he shall request inspection and final written approval
of the street or way or portion that is under construction.
B.
The Planning Board shall control the construction of the streets
or ways of the subdivision by inspection and approval of the work
through the services of the Superintendent of the DPW, or his agent,
and by the consulting engineer, if any. The necessary approvals for
each step of the construction must be obtained by the applicant in
the aforementioned sequence of work.
C.
The Planning Board may, in cases of minor construction or undue hardship
upon applicant, waive any inspection, except that which is required
for final approval, by issuing provisional approval pending full approval
after the next inspection.
D.
It shall be the applicant's responsibility to notify the Board when
a portion of the work is ready for inspection; and the Board shall
cause said inspection to be made within seven days of receipt of such
notice, Saturdays, Sundays and holidays excluded.
E.
Approval of the work inspected shall be given to the applicant by
the Superintendent of the DPW before the next portion of work is commenced
in the street or way, and such approval shall be forwarded to the
Planning Board by the Superintendent of the DPW.
F.
If corrections are required in the work, they shall be made before
approval is given for a portion and before subsequent work is started,
unless written authority by the Planning Board is given to proceed
into the next portion of work while making the required corrections.
G.
Failure to carry out the provisions of this section shall be cause
for the Planning Board to order such work done as may be necessary
to make adequate inspection and correction of the work under construction,
at the expense of the applicant.