Plans and specifications for construction of sanitary sewerage systems by developers or other persons, to be dedicated to the Borough upon completion pursuant to developer's or other agreement, shall be submitted to the Borough Clerk and the SCMUA for review and approval. Said plans and specifications shall be prepared by a licensed professional engineer (signed and sealed), and shall conform with all requirements of the NJDEP for the design and construction of sanitary sewerage systems. All new sewers shall be properly designed and constructed in order to avoid the creation of infiltration and inflow sources within the sanitation sewer system. Borough endorsement of NJDEP construction permit will not be provided until plans and specifications are approved.
Approval by the Borough for construction of such sanitary sewerage systems as set forth in § 95-57 shall not be provided until each of the following has been obtained and evidence of same has been provided to the Borough Clerk:
A. 
Approval by Borough Planning Board or Land Use Board.
B. 
Approval by Borough Engineer.
C. 
Approval by SCMUA.
D. 
Receipt of NJDEP construction permit (if applicable).
E. 
Required maintenance and/or other bonds, as required by the Borough.
With respect to construction permitted pursuant to § 95-57, in the event construction conditions require field changes, a written request for approval of such changes, stating reasons for such changes, must first be submitted to, and approved in writing by, the Borough Engineer and SCMUA.
The person constructing said sewer system shall supervise and direct the work efficiently and safely. Construction permitted under this article shall be subject to inspection and approval by the Borough Engineer.
Leakage tests shall be performed by the contractor, and approved by the Borough Plumbing Inspector prior to the connection of new sewer lines to the Borough's mains. Connections to building sewers shall not be made until notice to connect is provided by the Borough.
Following completion of construction of any sewers, the developer shall submit to the Borough Clerk certified as-built plans of the system constructed.
Any new sewer system constructed pursuant to this article shall be operated and maintained by the developer in accordance with good practice, until ownership of the new sewer system is conveyed to the Borough, at which time operation and maintenance shall be performed by the Borough. Ownership of the new sewer system shall be conveyed to the Borough after 24 months of operation, in accordance with NJDEP requirements, of the new system.