[Adopted 2-2-2007 by Ord.
No. 378]
All applicants shall submit applications to the Borough Secretary
for review by the Review Officer.
The Secretary shall, upon request, issue application forms,
ordinances and other official Borough forms to applicants.
Where applicable, projects that require multiple permits shall
submit applications in the following order:
B. State permits (Labor and Industry, Department of Agriculture, DEP,
etc.).
C. Lot improvement applications (i.e., lot consolidation).
E. Zoning.
(1) Variance or other Zoning Hearing Board matters.
(2) Conditional use or permitted use applications.
F. HARB (informal review may take place at the discretion of the HARB
at any time).
Land development applications and zoning applications for the
same project shall be processed concurrently.
The approval of applications shall occur in the order set forth in §
122-3 unless the applicant for good cause shown is granted leave by the Council to proceed on another manner.
Applications for the next permit for a multiple-permit project
may not be filed until the previous stage has been completed and the
appropriate permits or approvals have been issued for that previous
application.
In the event that a DEP-approved sewage soil module is required
for a project, the applicant may request that the Borough and the
applicant agree to an alternative procedure for application review
and approval.
[Added at time of adoption of Code (see Ch. 1, General Provisions,
Art. I)]
No excavations for any building purpose shall be made, nor shall
any building or structure of any kind be erected, altered, improved
or moved, unless it shall have been previously approved by the Secretary
of the Borough Council and a building permit issued certifying that
plans and specifications therefor have been filed with the said Secretary
for the same, and that the same comply with the terms of this article.