A. 
Unless waived by the Township, prior to the start of construction, a preconstruction meeting shall be held with the developer, the developer's engineer and contractor, Township official(s) and the Township Engineer.
B. 
The Municipal Engineer or a designated representative of Fairview Township shall inspect the construction of the temporary and permanent stormwater management system for the development site. The permittee shall notify the Municipal Engineer 48 hours in advance of the following key development phases:
(1) 
At the completion of preliminary site preparation, including stripping of vegetation, stockpiling of topsoil and construction of temporary stormwater management and erosion control facilities.
(2) 
At the completion of rough grading but prior to placing topsoil, permanent drainage or other site development improvements and ground covers.
(3) 
During construction of the permanent stormwater facilities at such times as specified by the Municipal Engineer.
(4) 
At the completion of permanent stormwater management facilities.
(5) 
At the completion of final grading, vegetative control measures and any other site restoration work done in accordance with the approved plan and permit.
C. 
BMPs, facilities and structures.
(1) 
The landowner or the owner's designee (including the municipality for dedicated and owned facilities) shall inspect SWM BMPs, facilities and/or structures installed under this chapter according to the following frequencies, at a minimum, to ensure the BMPs, facilities and/or structures continue to function as intended:
(a) 
Annually for the first five years.
(b) 
Once every three years thereafter.
(c) 
During or immediately after the cessation of a ten-year or greater storm.
(2) 
Inspections should be conducted during or immediately following precipitation events. A written inspection report shall be created to document each inspection. The inspection report shall contain the date and time of the inspection, the individual(s) who completed the inspection, the location of the BMP, facility or structure inspected, observations on performance, and recommendations for improving performance, if applicable. Inspection reports shall be submitted to the municipality within 30 days following completion of the inspection.
(3) 
If such inspections are not conducted or inspection reports are not submitted as scheduled, the Township, or its designee, may conduct such inspections and charge the owner appropriate fees as established by the Board of Supervisors. Nonpayment of such fees may result in a lien against the subject property.
(4) 
Prior to conducting a scheduled inspection, the Township may inform the owner of its intent to conduct an inspection but is not required to do so.
D. 
No work shall commence on any subsequent phase until the preceding one has been inspected and approved. If there are deficiencies in any phase, the Municipal Engineer shall issue a written description of the required corrections and stipulate the time by which they must be made.
E. 
If, during construction, the contractor or permittee identifies any site condition, such as subsurface soil conditions, or alterations in surface or subsurface drainage which could affect the feasibility of the approved stormwater facilities, he/she shall notify the Municipal Engineer within 24 hours of the discovery of such condition and request a field inspection. The Municipal Engineer shall determine if the condition requires a stormwater plan modification.
F. 
In cases where stormwater facilities are to be installed in areas of landslide-prone soils or where other special site conditions exist, Fairview Township may require special precautions, such as soil tests and core borings, full-time inspectors and/or similar measures. All costs of any such measures shall be borne by the permittee.
A. 
Upon presentation of proper credentials, duly authorized representatives of the Township may enter at reasonable times upon any property over the recorded plan areas as designated on the recorded plan within the Township to inspect the implementation, condition, or operations and maintenance of the stormwater BMPs in regard to any aspect governed by this chapter.
B. 
Stormwater BMP owners and operators shall allow persons working on behalf of the Township ready access to all parts of the premises for the purposes of determining compliance with this chapter.
C. 
Persons working on behalf of the Township shall have the right to temporarily locate on any stormwater BMP in the Township such devices as are necessary to conduct monitoring and/or sampling of the discharges from such stormwater BMP.
D. 
Refusal of access to the areas subject to this chapter shall constitute a violation of this chapter.